HomeMy WebLinkAbout1148 Agreement Amendment with HDR BILL NO. 2012-054 ORDINANCE NO. II ��
AN ORDINANCE AMENDING THE AGREEMENT FOR ENGINEERING SERVICES WITH
HDR ENGINEERING, INC. TO PROVIDE FOR A CHANGE IN THE SCOPE OF SERVICES TO
INCLUDE SPECIFIC DESIGN AND CONSTRUCTION SERVICES IN CONNECTION WITH
THE INTERURBAN BRIDGE AND TRAIL BANK STABILIZATION PROJECT AND
AUTHORIZING PAYMENT FOR SERVICES IN CONNECTION WITH SUCH PROJECT IN AN
AMOUNT NOT TO EXCEED $40,813.21
WHEREAS, the City of Riverside, Missouri ("City") approved the qualifications of HDR
Engineering, Inc. ("HDR") to provide certain engineering services within the City and entered
into an agreement with HDR at such time for provision of on-call engineering services within the
City pursuant to Ordinance 2009-110 (hereinafter the "AgreemenY'); and
WHEREAS, there is a need to amend the Scope of Services under the Agreement to
authorize specified engineering services related to the Interurban Bridge and Trail Bank
Stabilization Project; and
WHEREAS, the amount of $30,063.21 has previously been paid out of the city treasury
for such services with a remaining amount due not to exceed an additional $10,750.00; and
WHEREAS, the Board of Aldermen find it is in the best interest of the citizens of the City
of Riverside to provide for such additional services, ratify prior expenditures and authorize
additional expenditures as set forth in Exhibit A attached hereto;
NOW THEREFORE, BE IT ORDAINED BY THE BOARD OF ALDERMEN OF THE
CITY OF RIVERSIDE, MISSOURI, AS FOLLOWS:
SECTION 1— AMENDMENT APPROVED. Execution and delivery of an amended
scope of services to the Agreement with HDR Engineering, Inc. in substantially the form attached
hereto as Exhibit A, is hereby approved and all prior actions taken with regard to the acquisition
and payment of such services from HDR in connection with the Interurban Bridge and Trail Bank
Stabilization Project are hereby approved, ratified and authorized.
SECTION 2— AUTHORITY GRANTED. The Mayor, the City Administrator, the City
Attorney and other appropriate City officials are hereby authorized to take any and all actions as
may be deemed necessary or convenient to carry out and comply with the intent of this
Ordinance and to execute and deliver for and on behalf of the City all certificates, instruments,
agreements and other documents, as may be necessary or convenient to perForm all matters
herein authorized and any actions taken prior to the adoption of this ordinance are hereby
ratified and approved.
SECTION 3— EFFECTIVE DATE. This Ordinance shall be in full force and effect from
and after its passage and approval.
BE IT REMEMBERED that the above was read two times by heading only, passed and
approved by a majority of the Board of Aldermen and APPROVED by the Mayor of the City of
Riverside, Missouri, this �I�"day of August, 2012.
����� � �
o Kathleen L. Rose, Mayor
� .
ATTE�� -� A pr s to Form:
'.�x�� �F-�
Robin Littrell, City Clerk� a hom , City Attomey
. , ,
p
i� i
, . �
nu�st �, zoia
City of Riverside
Attn: Mr. Travis $oover, P.E., Capital Projects Engineer
2950 NW Vivion Road
Riverside, MO 64150
Re: Interurban Bridge snd Trail Bank Stabilization
HDR ProJect No.178226
Deaz Travis: �
At the City of Riversjde's request HDR Engineering Inc. (HDR) completed design and
development of conshuction plans and specifications for the referenced project on August 6,
2012 as part of our On-Call City Engineering Services contract dated August 4, 2009. The
services completed by HDR to date include the following tasks.
• Obtained U.S. Atmy Corps of Engineers 404 Pemut Authorization
• Preliminary Plan Development
• Coordinarion with KCMO Water Services
• Supplemental Topographio Survey
+ Final Construction Plans and SpecificaUon Development
• AdveRised Project for Bid and Bid Package Reproduction/Distribution
These services have been completed on an howly basis plus reimbursable expenses: HDR's
August invoice, which will account for charges through July 28, 2012, indicates total project
related billings of $28,470.84. Work completed to finalize the Bid Fackage for Advertisement
between July 29, 2012 and August 6, 2012 indicates an additional $1,592.37 witl be invoiced in
September resulting in total project related chazges to date of $30,063.21.
HDR's anticipated Scope oF Services for bidding and oonstruction phase services for this
project will include: � ,
Bidding Phase Services
• Plan Distriburion and tracking of Plan Holder's List
• Attend Pr�Bid Conference, Prepare and disfribute minutes
• Address Bid Phase inquiries �
• Prepaze and issue applicable addendum .
• Attend Bid Opening
HDH Enpinearing, Inc.
Travis Hoover, P.E.
City ofRiverside
Page 2 of2
• Prepaze Bid Tabulation and review bids for responsiveness and mathematical
conectness
• Submit a written award recommendation and attend one (i ) Board of Aldermen meeting
Constructlon Phase Services .
• Attend Pre-Construction Conference
• Attend Construction Pmgress Meerings — Monthly (2)
• Provide Contract Document Interpretation
. Prepaze and Issue Applicable Change Orders
• Substanrial Completion Inspection and Punch list
• Final Complerion Inspection, Closeaut Documentation
As compensation for the performance of the Bidding and Construction Phase Scope of Services
described in this Letter, HDR respectfulTy requests compensation in the amount of $10,750.00.
This compensation is broken down into the project components describe above as follows:
Bidding Phase Services $5,03Q.00
Construction Phase Services $5,720.00
If you have any questions while seviewing this infoimation please feel free to contact me at
816-347-1120. We have enjoyed working with the City of Riverside on tivs project and look
forward to its successful completion.
Sincerely,
/�
Aaron L resette, P.E.
Cc: Nancy Thompson, City Attomey
�ii
August 14, 2012
City of Riverside
Attn: Mr. Travis Hoover, P.E., Cspital Projects Engineer
2950 NW Vivion Road
Riverside, MO 64150
Re: Interurban Bridge snd Trail Bank StabilizaHon
HDR Pro ject No. 178226
Dear Travis;
At the City of Riverside's request HDR Engineering Inc. (HDR) completed design and development of
conshvcflon plans and specifications for the referenced project on Aug¢st 6, 2012 as part of our On-Ca11
City Engineering Services contract dated August 4, 2009. T'he services completed by HDR to date
include the foilowi,ng tasks.
• Obtained U.S. Army Corps of Engineers 404 Pernrit Authorization
• Preliminary Plan Development � '
• Coardination with KCMO Water Services
• Supplemental Topographic Survey .
• Final Construction Plans and Specification Development
• Advertised Project for Bid and Bid Package Reproduction/Distribution
These services have been completed on au hourly basis plus reimbursable expenses. HDR's August
invoice, which will account for charges through July 28, 2012, indicates total project related billings of
$28,470.84. Work aompleted to finalize the Bid Package for Advertisement between July 29, 2012 and
August 6, 2012 indicates an additional $1,592.37 will be invoiced in September resulting in total project
related charges to dafe of $30,063.21.
HDR's anricipated Scope of Services for bidding and construction phase services for this project will
include:
Bidding Phase Servtces
• Plan distribution to Plan Rooms and prospective bidders and tracking of Plan Holder's List.
• Attend Pre-Bid Conference with the City and prospective bidders appro�cimately 14 calendar
days prior to the bid opening to discuss the project requirements and bidder questions. Issue
minutes from the meeting in the form of an addendum:
• Address and answa bid phase inquiries up to seven (7) calendar days before the bid date
, • Evaluate bidder inquiries and issue resulting addenda to all recorded document holders seven
(7) calendar days before the bid date
. HDNEngineering.lnc. �
TravisNoover, P.E.
City ojRiverside ,
Page 2 oj1
• Attend bid opening
• Tabulate and review bids for responsiveness and mathetnatical correctness
• Submit Bid Tabulation and a written awazd recommendation to the City and attend one (I )
Boazd of Aldermen meeting
Construction PLase Services
• Attend Pre-ConsWCtion Conference at City offices and assis[ City staff with project related
questions. Notes will be provided to City staff for compelation and distribution by the City
• Attend two (2) Consuuction Progress meetings with City staff and Contrador to discuss
conshuction status, project schedule, site conditions, and possible design modifications.
• Respond to City staff requests for interpretations of the contract documems
• Provide Contract Document Interpretation
• Assist the City in drafting Change Orders and modifying the constiuction documents ro reflect
construction changes. The changes included in this task are to be considered minor in nature,
any significant change in the design due to unforeseen sight conditions may require redesign
beyond the scnpe of this task which can be completed as an additional service.
• Attend the Substantial Corapletion Inspection and assist City staff with the development of the
Punch list
• Attend Final Completion Inspection and provide fhe Engineer's Certification for Acceptance
and Final Completion
As compensation for the performance of the Bidding and Construction Phase Scope of Services
described in this Letter, HDR respectfiilly requests compensation in the amount of $1Q,750.00. This
compensation is broken down into the project components describe above as follows:
BiddingPhaseServices $5,030.00
Construction Phase Services $5,720.00
If you have any questions while reviewing this information please feel free to oontact me at 816-347-
1120. We have enjoyed working with the City of Riverside on this project and look forwazd to its
successful completion.
Sincerely,
Aaron J. B sette, P.�
Cc: Nancy Thompson, City Attomey
HOfl Engineering, Inc.
AMENDMENTTO AGREEMENT
FOR
ENGINEERING SERVICES
WHEREAS:
HDR ENGINEERING, INC. ("HDR") entered into an Agreement on Auaust 9th . 2009 to
perform engineering services for the C� of Riverside ("Riverside");
Riverside desires to amend this Agreement in order for HDR to perform services beyond those
previously contemplated;
HDR is willing to amend the agreement and perform ihe addiGonal engineering services.
NOW, THEREFORE, HDR and Riverside do hereby agree:
The Agreement and the terms and conditions therein shall remain unchanged other than ihe additional
scope of work associated with the Interurban Bridge and Bank Stabiliza6on Project listed below;
Bidding Phase Services
• Plan Distribu6on and tracking of Plan Holder's List
. Attend Pre-Bid Conference, Prepare and distribute minutes
• Address Bid Phase inquiries
• Prepare and issue applicable addendum
• Attend Bid Opening
• Prepare Bid Tabulation and 2view bids for responsiveness and mathemaGcal correctness
• Submit a written award recommendation and attend one (1) Boarcl of Aldermen meeting
Construction Phase Services
. Attend Pre-Construction Conference
. Attend Construction Progress Meetings — Monihly (2)
. Provide Contract Document Interpretation
. Prepare and Issue Applicable Change Orders
• Substantial Completion Inspection and Punch list
• Final Completion Inspection, Closeout Documentation
Estimated Fee associated with the addi6onal scope of work is 10 750.00 as detailed on the attached
Detailed Scope and Fee Es6mate.
IN WITNESS WHEREOF, the parties hereto have executed this Amendment as of the day and year written
bebw:
HDR ENGINEERING, INC. ("HDR") CIN OF RIVERSIDE ("RIVERSIDE')
By: Stan risto r,,3r. V.P. By:_L1;��k���__°��L�
�ts: �ts: �af1, lee,�, L.�ose ;� o�e
Date: �I t�� � Z Date: � vi ���
CITY OF RIVERSIDE - INTERURBAN BRIDGE AND BANK STABILIZATION PROJECT
HDR Engineering, Inc.
Scope and Fee
, i4 �, ��� ,_ , y ��
� , ��� � � is� ��� �� "p �, �� ,i�
�� �Mi9. fi � i � �y Gd& p� .
i�' � .". i b di N t G��� t'. � Mi9 h � 9i � � d�f,�� ° 14 �(' H ���� `��R��i
� '* �� � � �� � �� �� ����ir } . '� � � I � M�j�
x u. � ' � ,a �.-.. iN�9d � .+t1 4 . +� t�v ��
. .
�, ' .. �� ^ ,'�.�Q �. � �� . �.��W�: �� .�3 � i .. *
� � � -� � �� � �
�+ �, E r H� ' �' 9 d v �. i t��i
�+ � i �'t . �.,,:l.. . 3.�'�..?�s �E .a r . 3 a�u�'� �,n r�
TASKS
a Biddi Phase
1 Plan Distribution and hackin of Plan Holder's List 16 $960
2 Attend Pre-Bid Conference, Pre aze Minutes 2 4 2 $2$ $898
3 AddressHidPF�asel uiries ' 1 2 4 4 $1,161
4 and Issue A licable Addendum 2 4 4 $990
5 Aitaul Bid O �n � 2 $28 $342
Pmpare Bid Tabulation ard Rcview Bids for
6 res ivencss and mathematical correctr�as � 2 2 $338
Submit a writtrn award recommrndation and attend one (1)
7 Board of Aldrnnrn meeti 2 $27 $341
Subrotal Hours 1 10 14 28
Su6tota/ Dollars 171 1570 1526 1680 83 55,030
Tota/8ldding Phase 55,030
b ' ConsWCtion Phase
1 AttmdPrc-ConsWC[ionConference 2 2 $32 b564
2 AttrndConstructionPro essMeetin —Monlhi (2 4 4 $60 $1,124
3 Provide Contract Document Int retation 4 4 $1,064
4 P are and Issue A licable Ch e Ordtts 4 8 $1,500
5 Subs[antial Com kUOn Ins ection and Punch list 2 2 4 $32 $1,124
6 Finai Com le[ion Ins rion. Closeout Documrnta6on 2 $30 $344
Subrota/ Hours 2 78 22 0
Subrota/ Dollars 342 2826 2398 0 154 55,720
Total Construction Phase 55,720
Total Hours 3 28 36 28 95
Total Billing Amount 5513 54,396 E3,924 $1,� 5237 510,750