HomeMy WebLinkAboutR-2012-157 Change Order 4 Between Briarcliff Realty and Kissick Construction RESOLUTION NO. R-2012-157 A RESOLUTION AUTHORIZING, APPROVING AND RATIFYING CHANGE ORDERS 1 THROUGH 4 TO THE AGREEMENT BETWEEN BRIARCLIFF REALTY, LLC AND KISSICK CONSTRUCTION CO, INC. RESULTING IN AN APPROVED REVISED CONTRACT AMOUNT OF $1,172,400.85; FURTHER AUTHORIZING, APPROVING AND RATIFYING CHANGE ORDERS 1 THROUGH 4 TO THE AGREEMENT BETWEEN BRIARCLIFF REALTY, LLC AND GEORGE J SHAW CONSTRUCTION CO. RESULTING IN AN APPROVED REVISED CONTRACT AMOUNT OF $8,967,775.39. WHEREAS, Briarcliff Realty, LLC and the City entered into that certain Master Development Agreement dated May 10, 2011 (the "MDA"); and WHEREAS, Briarcliff Realty, LLC changed its name to BR NorthPoint, LLC and assigned all its rights and obligations under the MDA (but not its rights and obligations under the MDA First Amendment) to Briarcliff Horizons, LLC, an affiliated entity of Briarcliff Realty, LLC pursuant to Section 12.5(b) of the MDA; and WHEREAS, on or about February 13, 2012 Briarcliff Horizons, LLC filed articles of amendment with the Missouri Secretary of State changing its name to Riverside Horizons, LLC ("Developer"); and WHEREAS, pursuant to the MDA, Developer agreed to construct and complete certain public Infrastructure Improvements on the Briarcliff Horizons Site, as such terms are defined in the MDA; and WHEREAS, the MDA established Infrastructure Phase 1 improvements to consist of the lakes, canals, and landscaping and further established the cost estimate and budget for the Infrastructure Phase I Improvements to be $13,146,683; and WHEREAS, on or about August 21, 2011, Developer competitively bid the Infrastructure Project, as defined in the MDA, and subsequently submitted its recommendation to the City to award the Site Utilities portion of Infrastructure Phase 1 to Kissick Construction Co., Inc. ("Kissick") and the award the Earthwork and Grading portion of Infrastructure Phase 1 to George J. Shaw Construction Co. ("Shaw"); and WHEREAS, on or about November 1, 2011, the Board of Aldermen approved Kissick as the contractor to perform construction services related to the Site Utilities portion of Infrastructure Phase 1 and approved Shaw as the contractor to perform construction services related to the Earthwork and Grading portion of Infrastructure Phase I; and WHEREAS, on or about November 15, 2011, Developer entered into an agreement with Kissick to perform construction services related to a portion of the Infrastructure Phase 1 in an amount not to exceed $992,824.46 ("Kissick ContracY'); and WHEREAS, on or about December 1, 2011, Developer entered into an agreement with Shaw to perform construction services related to a portion of the Infrastructure Phase 1 in an amount not to exceed $7,330,477 ("Shaw ContracY'); and WHEREAS, on or about February 7, 2012 Developer received approval from the City to amend the Infrastructure Construction Plans, as defined in the MDA, to provide for an upgrade of the electrical facilities constructed at the site such that a two way duct bank would be increased in size to a four way duct bank together with an increase in the budget for RESOLUTION NO. R-2072-157 Infrastructure Phase 1 in the amount of $250,000 for such purposes resulting in a revised authorized budgeted expenditure for Infrastructure Phase 1 in the amount of $13,396,683; and WHEREAS, on or about February 7, 2012 Developer received approval from the City to further amend the Infrastructure Construction Plans to accelerate a portion of the mass grading originally scheduled and budgeted in Infrastructure Phase 2 into Infrastructure Phase 1 in the amount of $670,000 such that the Infrastructure Phase 1 budget increase in the amount of $670,000 resulting in a revised authorized amount of $14,066,683 for expenditures in Infrastructure Phase 1 and a revised budget of $4,924,512 for expenditures in Infrastructure Phase 2; and WHEREAS, on or about August 20, 2012 the Board of Aldermen approved an amendment to Exhibit C-1 of the MDA to provide for the construction of additional public infrastructure in the amount of $600,000 related to construction of the Horizons Industrial I project, which additional infrastructure costs are not subject to the Infrastructure Cost Split set forth in Section 4.2(b) of the MDA; and WHEREAS, Developer has presented Change Orders 1 through 6 for a net INCREASE to the Kissick Contract to the Board of Aldermen in the amount of $179,576.39 resulting in a revised contract amount of $1,172,400.85 for review and approval; and WHEREAS, Developer further has presented Change Orders 1 through 6 for a net INCREASE to the Shaw Contract to the Board of Aldermen in the amount of $1,631,268.39 resulting in a revised contract amount of $8,961,715.39 for review and approval; and WHEREAS, Sections 5.5 and 5.6 of the MDA require City approval for all change orders to the Infrastructure Construction Documents; and WHEREAS, the Board of Aldermen find that the Change Orders to the Kissick Contract and the Shaw Contract are in the best interest of the City in that such action fulfills a public purpose and will further the growth of the City, facilitate the development of the Briarcliff Horizons Site, improve the environment of the City, increase the assessed valuation of the real estate situated within the City, increase the sales tax revenues realized by the City, foster increased economic activity within the City, increase employment opportunities within the City, enable the City to direct the development of the area, and otherwise be in the best interests of the City by furthering the health, safety, and welfare of its residents and taxpayers; NOW THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE CITY OF RIVERSIDE, MISSOURI, AS FOLLOWS: THAT Change Orders 1 through 6 to the Agreement entered into by and between the Briarcliff Realty, LLC and Kissick Construction Co, Inc. resulting in a net INCREASE in the amount of $179,576.39 are hereby authorized, ratified and approved resulting in a revised contract amount of $1,172,400.85; FURTHER THAT Change Orders 1 through 6 to the Agreement entered into between Briarcliff Realty, LLC and George J Shaw Construction Co. resulting in a net INCREASE in the amount of $1,631,268.39 are hereby authorized, ratified and approved resulting in a revised contract amount of $8,961,715.39; RESOLUTION NO. R-2012-757 FURTHER THAT the Mayor, City Administrator, Finance Director and all other required city officials are authorized to execute the change order authorized herein together with any and all documents necessary or incidental to the performance thereof and to take such other actions and/or execute and deliver for and on behalf of the City all certificates, instruments, agreements and other documents as may be deemed necessary or convenient to carry out and comply with the intent of this Resolution. PASSED AND ADOPTED b the Board of Aldermen and APPROVED by the Mayor of the City of Riverside, Missouri, the � day of December 2012. j��� (.(.Q/�O� .' Kathleen L. Rose, Mayor � � ,� Q , A -ATTEST: • , �, � i Robin Litt�ell,, Gi y•Clejk Appro as to form: t y om son, City Attorney Kissick Construction Original Contract 992,824.46 Change Order # 1 31,214.65 Change Order #2 (100,000.00) Change Order #3 - Change Order#4 6,837.13 Change Order #5 - Change Order #6 241,524.61 Total Change Orders 179,576.39 Revised Contract 1,172,400.85 C1TY OF RIVERSIDE CHANGES 1N PLANS AND CONSTRUCTION ConVaclw Name: Kfssidc ConsVUCfion Changes in Plans antllor ConsVUCtlon Project Name: Horizons Projecl LoraUOn: Riversitle, Missouri Reauest #1 Pfojecl Numbe� Tne laiorag Man9es m me ariynel conbaa ertnrirrere muuea m cavercosi vavnee qmeGmrenor orle reMr� avligs naezq eyua Cawma u a recun are tl�ary� In Ne atluY cwWC1eE iuMNes ImnNeeaWrWM pwnitlb flwn on Ue BltlPrtpoeLL cor,��a oe�: Date Prepared: Page Number. 1 of 1 REOUIRED CHANGES IN PRESENT CONTRACT ConU�t Item No. ttem Description Net Change Reason $24,703.00 CIPP Installation on Sanitary Line 53,633.19 Small Ouantity Changes to San'itary Drsvrings $y 87g qg Soft Subgratle Excavation $31,274.65 � K Contract Change Order a�ni io, zoiz O OM u9�� Yn. w�M�� Phone: (816) 363-5530 Keneas City, MO 64132 Faz: (816) 523-1557 ��t��r'k', �� . . ... TITLE: Change Ordet No. Ol - Sanitary DATE:3/28/2012 PROJECT: Riverside Horizons Development JOB: 1177 TO: Attn: Cluis Williatns, CCIM CONTRACT NO: CONTRACT BriazcliffRealty, I.LC 6300 North Revere Drive, Suite 225 Kansas City, MO 64151 Phone:(81� 888-7380 Please ses the attached dacumentation regazding tliis change order. Item Descripdon SWCk# Quantity Units UnitPrlce NetAmount 0000i r.w,P s� r�o� �.000 su,�o3.0o su.TO3.00 ooaoz 12" PVC SDIt 26 so.000 � a�z.00 ae,aao.00 00001 8"PVCSDR26 22.000 LF 548.00 51,056.00 011004 6" PVC SDR 26 -44.000 LP 543.00 (S1,B92.00) 00005 4'mMenholeExuaDepth 3.190 VF 589.00 528�.91 00006 5' [D Dog House Manhole -1.000 EA 55,500.00 (55,500.00) 00007 5'mMmmholaExanDcpl6 -1.190 VF SI19.00 (S�4U•42) 00008 12" x 8" Tee witli 8" 90 Degree 1.000 I.S 51,849.00 51,849.00 Bend aod 12' x 6" Tm with 45 DegraBend-SaKC Winwater invoice 165976-02 Date 12-02•1I and KC Winwetar inwia 165976-03 Dam 12-02-I1 00009 8" PVC SDR 21(Sarvice Smb) ]4.000 LF 549.35 5690.90 00010 6" PVC SDR 21(Secvia SNb) I4.000 LF 544.35 5620.90 OOOII OvaheadendProStonMatoriels 0.100 % 51,649.00 5184.90 and SuLOOntlncto`a (10%) OOD12 Opaawr 4.000 Hwn 570.97 5283.88 00013 KumemuPC4007cack8zuvawr 4.000 Houca S160.00 5640.00 00014 Hunt Mutin Materiels - 1/2" Claan I10.430 Tons 516.09 51,776.89 Rack 00015 Ovethced end Profit ou Mntetink 0.100 °/a 51�776.89 SI77.69 ond 3vAconhnctara p0%) COLLECTED CONTRAGT CHANGE3 Change Type Number Title MamtNa. Ch4nge Coet PCO OOOOI CIPP Inatallation 00001 0 524,703.00 , PCO 00002 Sanitary Sewer Drewing Changes 00002 0 $3,633.19 PCO 00005 Soft Suhgiade ExcawHon - Revised 00005 0 52,878.46 Totsl: S31,Z14.65 Paye Lor 1 ConUactar Neme: IGSSitic ConswCion Changes in Plans arW/or Construc[ion Pmject Name: Naimna Projea Locetion: RiversiCe, Misaouri Reouest S2 P�qetf NutfiDef: rn. idw.��a �.�vs mm. o�ynm rnwx+.moumwer� �mwea m o� au u�.rte q wc�vxa m u nnac� uanac nnesa e�n.cmixor..a rcwx a• meny� �n �M..rva �o.+uw.a aW�n nom w.v.�.i.e p.cnuea er�� a�ma ea r�oxi Contr�t Oste: pste pfepe�eq� Page Number. i ot 1 REQUIREDCHANGESINPRE$ENTCONTRACT ConVect Item No. Item Detaiptim Net Ctienge Reason ��pp ppp,pp RBC Delatio� Mat were rwt neeCetl along Horizons Parkway •5700.000.00 ttISS1CK Contract Change Order May 14, 2012 eo�+.rnuar�ora „r••••••.y.••• phonc: (St6)363-5530 Kansaa Ciry, MO 64132 Fex: (8l6) 523-1557 CHANGE ORDER TITLE: Change Order No. U2 - RC6 Deletions DATE: 5/14l2012 PRUJECI': Riverside Horizons Development . JOB: l 177 TO: Attn: Chris Williarns, CCIM CONTRACT NO:CONTRACT Briarcliff Realcy, LLC 6300 North Revere Drive, Suite 225 Knnsas City, MO 64151 Phone: (816) 888-7380 Please see the attached documcnt�ltion rogarding this chunge order. Item De�cripUon Stock# Quandly Units UnitPrice NetAmuunt OUtl01 CnnaactEx6ibitF-Sto�m•Lina -I.OUO LS 59d,tU0.Utl (59J,SOO.OU) Itcm1U-8'x6'RC� OOOU2 ContrectEshibitF-Srorcn-Line •I.00Q [,S 55,500.OQ (53,500.00) Item I 1- b'r 3' RCB COLLECCED CONTRACT CHANGES ChanQe Type Number Title Mgmt No. Change Cast PCO 00004 RCB Erteneion Delerions 00004 0 (S I OO,OOO.00J TOYaI: {$100,000.00) The Original Contrnct Sum was ................................................................................................. 5992,824.46 Net Change by Prevlously AuthoMzed Requests und Changes ................................................ 531,214.65 The Co�truct Sum Prtor to This Change Order wus ......... 51,024,039.11 The Contract Sum Will bc Decreased ................................................................................... ($100,000.00) The New Contract Sum including This Change Order ..... 5924,039.11 TheContract Time Will LYot Be Changed ...............:................................................................. T D of S ubstsntial Compledan ss of this Change Order Therefore is ... ContreGOr Name: Kissick CansWCtion changes in Plans andlorCOnsVuction PmjeMName: Horizons ProjeG Lacafion: Riversiae, Missouri Reauest #3 Projecl NumEer. memiu..m m.�an�� n ww+n.�am�..,.,.00rm m�x mn.�..�me er m. coMr«rw m ie nnen....n: wa.e er m. conw�w n. rewu �i. CdlheCl Dale: m.�u�� me.ew.ann,mw e+�mr.. ��u..v.wa w.mie.. Mwm m n. em v�ow� Date Preparetl: Page Number 7 ot 1 REQUIRE� CHANGES IN PRESENT CONTRAC7 CoMrect Item No. Item DeeafpUai Net Che�ge Reason W�ther related eztension - No Change to Contracl Price CoMreclp ry91�e: IGSSick Constniction CAanges in Plans anNOr Construction PmjeU Name: Morizons Project LocaEOf1: RiversiGe, Missouri Reauest p4 PIOjBCI NUfIIOBf: �ne iawnre <brec+m m. any�.i mno-:�v�a.x.nr� nwvaw m.�c wu:Fw.a er mec..�n�m.wm nnm...�c....ia.e qc. cmu.m�... rc.unar. m.� Cof1t2U 0216: i.m..m�.i �eNU.ea+.��we�m. enm.ma•���..�* ��n. ae v�opa.i Da[e Preparetl: Pa9e Number. 1 of 1 REWIRED CHANGES IN PRESENT CONTRACT Conlrotl Item No. IBem DescriP� NM Cnange Reason $8,837.73 h3I2tl8GOn IN UGliy Sk'EVES 91Ug 413t SUEEt y8.837.13 KIS�StCK Contract Change Order whr oe, zoi� oows wy t�or .......�n..u....� Phone: (816) 888-7380 Kansaa City, MO 64151 CAANGE ORDER TITLE: Change Order No. 4- Utility Sleeves DATE: 7/6/2012 PROJECT: Riverside Horizons Development JOB: 1177 TO: Attn: Brian Glynn, E.I.T. CONTRACT NO; CONTRACT Kissick Construction Company, Inc. 8131 Indiana Avenue Kansas City, MO 64132 Phone:(816)363-5530 Fa�;(816)523-1557 Please see the attached documentation regarding this change order. Item Deacdpdon 5tackt{ Quantity Unite Unit Price Net Amount OOOOI 5[eveFisher-Operator-Overtime I0.500 Houct SIOO,BI 51,058.S1 00002 BrandooCur-Labwer-Wertime 10.500 Hrnue 584.77 5890.09 00003 1azobCola-i.aborar-Wertime I0.500 Houra 584,77 5890.09 p0004 KomauuPC158TtackF�ccavator 10.300 Haus SI10.00 SI,I55.00 00005 TdceuchiTT.t50TrackOniloada I0.500 Hours 560.00 5630.00 00006 HeAzFquipmmlRentallnvoice 1.000 LS SI38.05 SI78.05 26291368•001 Date 06-19-12 - Forl� Aaachmrnt for Tekeucbi TL150 7Yack Uniloader 00007 Kaneas City Winweter Works I.000 [.S 51,074.00 51,074.00 Company, lnc. Invoice 170215-00 Dete 0615-12 - Pipe Slxve Mate�iels end Aceessorica 00008 MidwestProfessionalUlility 1.000 LS 540.00 540.00 Wcating Servicw lnvoice 12-06I5-Ol Dete O6-� 5-12 - Utllity Loca[ing Smica 00009 MabilizatlonlDamobili�ation I.000 LS SG00.00 E600.00 Allowmcc for Komatsa PC158 Treck Excavator 00010 Mobilization/DemobilizaUon I.000 LS 5250.00 5250.00 Allowance for Tekeuchi TLI50 Track Uniloada OOOII Oved�eedandProfit(l0Y)ao 0.100 °/a 51,114.00 SI11.40 Malerlsls and SubcanUecloB COLLECTED CONTRACT CHANGES Change Type Number TiUe M�mf. No. Change Cost PCO 00010 InstallafionofUtilitySleevea OOOIO 0 56,837.13 Total: $6,837.13 Page laf 1 Cmtraclar Name: Kissick Constructlrn Changes in Plans anClor Constructlon ProjeCt Neme: Horimns PmjeU Locatlon: RNersiOe, Atisaoun Reauest 05 ProjBCtNumbBr. meais.aou�+mm.uaw�wavn. r� n..mmm�,,,,���w�.aq�m.cmo-.�w«mr.nw..mmwmeaMU.ca.��,...,..wa,wna. n quntiW��NxmmMeebPrupvJ COf148C1 D818: Dale Preparetl: Page NumCec 1 oH RECUIRED CHAHGES IN PRESENT CONTRACT Conuact I�m No. Icem OexriPtion Pbt Chan9a Reawn WeaMer related e�Rension - No Cl�anye to ConVad Price K! CK Contract Change Order ]uly i6, 2012 oo. �o� ,......,�..,....., PEwne: (81� 363-5530 Kansas City MO 64132 Faz (816) 523 1557 +tn+:r n � 6 ,pp r q2q. R° W �' � '"Lya w i i i s i[ ?`�A G 7 � 5�:i� -�. �� ' v � . � �'' � �r SY w �ur.. �sc„ • - � n:i.�9?e '�� �. .'�',:�'?f�l��'f��,.��:' '��h ��.. i. i � �1� � F.+r�+.;1 �3:r.�.J�.�...°'i�w�'��'� '1T-TLE: Change Order No. OS - Tixne Extension DATE: 7/ 16/2012 PROJECT: Riverside Horizons Development JOB: 1177 TO: Attn: Chris Williams, CCIM CONTRACT NO: CONTRACT Briarcliff Reslty, LLC 6300 North Revere Drive, Suite 225 Kansas Ciry, MO 64151 Phone: (816) 888-7380 Plaasa sea the attached docirmantation regsrd'uig this change order. �Ct'ens ..Descr lp[lon. : i.. .i.:Sf6ck& ;,':.;Qu9nt�ty.:,YSaits�:�i Unitp'?%te.' �' _`.`t .Netclaio$6f°' 00001 No Cwt CMnge 1.000 50.00 50.00 '� q y 4�� -. !� a z :k k 7+ }i � -: Cd�%�����{)�1Vl��st� i p-. 1�Y +� �. s � W N K l' Y � i .. � 4. aK' p r e .k�' yr f"' �L . � L �'i . ` �� + t � n r A' � � �t lAw� at r �, �.��t �'"'ry� � �C��Y�T r � ° t 3 �., ` . � .: Y ��'�i `,_`. Num6er�' s { ����. <� ,.r � �Y.<.R� 4 ::.r ..4:;� �' `q�.���i' s�$.:r IY�E s mt.Lvai`�"c . �.�C6an8e ... . . . s C0.1t � PCO 0001t ContrectTimeExtmaionII OOOII 0 $0.00 TotaL• $0.00 Th Ortginsl Contract Sum was ..........................................................»....»............«................. $992,824.46 Net Change by Prevlously Authorized Requests and Changes ................................................ (561,948.23) The Contract Sum Prior to This Chsnge Order was ......... $930,876.23 1'he Contract Sum �Yill Not be Changed ................................................................................... $0.00 The New Contract Sum Iuclnding T6is CLange Order ..... $930,876.23 Th Contract Time Will Not Be Chaaged ...........................................»........_.......................... T h e Date o S ubstenNel Completion as of this Change Order Therefore is ... ContrecNr Neme: Kissick ConsWCfion Changes in Plans and/or ConsWCtion Projed Name: Horizons ProjectLocetion: Riverside Missouri ReouestM6 Pmject Number: m. �aiw.m=�+nw m m. ondnx mm.e.mwn.wn �.n+�em ew« �n��ea p m. com.�m� erm renm.an�m �wina W me comxmi.. �m wecmrc. m rce xws mm�ue o.�a. �m rce «amme vmmnr enw..� o� me aa wroow. Contract Dete: Dele Preparetl: Page Number: 1 of 1 REQUIRED CHANGES IN PRESENT CONTRACT Contract Item No. Item Descnptbn Net Change Reason 541,307.02 Storm Changes - increaseing sae at central lake / decreasing size at Intlutlrial ioeds in Phase II y4,254.00 Tracer Wire for Wetedine 520,562.00 WateAine drewing changes Oue to MAW $7,061.59 Instell 6" contluk far power at 42nd streel $174,320.00 Instell Sanifery b Spec 2 building TBD Raise Hydrents at 42ntl streel tlue Po sheet Deing raisetl $241.524.61 Brad Haymond Subject: FW: Horizons Change Order Summary From: John Garvey fmailto:JGarvevCalkissickco.coml Sent: Thursday, November O8, 2012 2:23 PM To: bradCalnortt�pintkc.wm Cc: Dennis Richardson; Jim Kissick Subject: Horizons Change Order Summary Bred, Below is a summary of the upcoming change orders. We are waiting to confirm final quantities on the storm and water. Storm should be final now, water line will be determined once the office portion of the waterline design is finalized. It is my intention to send you Change Order 6 for the items below once the waterline design in finished. Please contact me with any questions. Upcaming Change Orders Change Order 6 - Pending PCO#00006— Storm Changes $41,307.02 PCOti00007—Tracer Wire for Waterline $4,254.00 PCO#00008—WaterlineDrewingChanges $20,562.00 PCO#00013 — Install 6" Conduit T&M $1,081.59 Proposal for Sanitary to Spec 2 $174,320.00 T&M Ticket to Raise Hydrants TBD Total for all items (Estimate base on above) $1,172,400.85 Thanks, John Garvey ProjectEngineer KISSI ao..s�twuoi �oM 8131 Indiana Avenue Kansas City, Missouri 64132 Phone: (816) 363-5530 Fax:(816)523-1557 Cell: (816) 365-3321 No virus found in this message. Checked by AVG - www.avg.com Version: 2012.0.2221 / Virus Database: 2441/5382 - Release Da�: 1 I/O8/12 i George Shaw Construction Original Contract 7,330,447.00 Change Order # 1 27,112.48 Change Order #2 163,607.75 Change Order #3 173,475.93 Change Order #4 193,426.86 Change Order #5 347,440.78 Change Order #6 726,204.59 Total Change Orders 1,631,26839 Revised Contract 8,961,71539 CITY OF RIVERSIDE CHANGES IN PLANS AND CONSTRUCTION Contractor Name: George Shaw Consfiuction Changes in Plans anNor Conawction Projecl Name: HOlimns Projecl Localion: Rivefsitle. Missouri Reauest �1 ProjeCt NumOer. tro tdwNq cnaipes mme wyiw wix�ra anwmYae m�ea m u..crmu incunea M� caa�aevam rsnee aewqi wrtea ey me can�m« n. muY ma �wq. m.emacwwaeaamawa�mmu..ammac�wu�essw.mmu.ma�ow ContraG Date: �� P� Page Number. 1 ot 1 RE�UIRED CHANGE8IN PRESENT CONTRACT ConhaG Item No. Item Desa�f'wn Net Change Reason 527.� �p.q8 ConsWclion of berms at 835 porM to Oetour waler, Pumping water from lakes, & Building aossings for conswction access 527.112.48 .� .� . Serving Grealer Kansas Ci1y Since 1928 ._.,----- --------_---------- --- �— _ — Phone: (816) 231-8200 1601 Bellefontaine Fax: (816) 231-8203 Kansas City. MO 64127 � May 1, 2012 Northpoint Development Group 1300 NW Briarcliff Parkway, Suite 250 Kansas City, Missouri 64116 Re: Riverside Horizons Change Order li1 Summary Attn: Brad Haymond Per your request, I have summarized the items included in change order #1 which was billed on our May 2012 pay application for the Riverside Horizons project. The items noted below are per our onsite meetings and phone conversations. Please see the summary below and feel free to call if you have any questions. Change Order #1 Value: $27,112.48 ✓ PCO item #1- The wark included in PCO #1 consisted of building berms to cut off drainage from the 635 lake under the 635 highway, pumping water from onsite lakes, and building crossings so work could proceed while the utility contractor utilized their "dewatering trenches". o PCO #1 value: $27,112.45 Sincerely, George J. Shaw Construction Co. Andy Nimz Project Manager CONCREfE • EXCAVATION • GRADING • WRECKING ConhacOOrName: Geoige Shaw Construc6on C�angea in Plana anNOrConrtrucNOn ProjeG Neme: Haimns PmjectLOCaCwn: Rivenitle.Miawuri Reauesttl2 PfajBCt NYIfIEer l�e tofvM�g wmm m �neanped cwp�ee emauitxae �quna mmr ert IrnrM q w cmewor am ieno unrqe iwYVe pne tw+nmrn s mup re • tlimqe b tlro Mu�l ¢mYUCIN pumptin kom Me eatlmpeU y wnlYlu Mtwn m T e Bb PrcW xl CU�bE� DBM: pg[� p�.pg�: Page Number. 1 of 7 REqUIREDCHANGE5IN PRESENTCONiRACT Contlaq Nem No. Ran �esaiP� N� CMrge Reason $92 490.75 Importetl Waterial usetl on 80 K 8uiltlinp Pa0 (Premlum Waters Ma[erlal) pp�.pp SpeC I suiainq - Inaease0 squate foo�ape from aiperel CeBipn 549.178.00 EnhBnm 419t SUeet subCese W iocic for all we9Nef treffiC 5783,607.75 . e t5�� Serving Greater Kansas C�ly Since 1928 -,—.--- ______._.__ — ___._ _. —_.._—.__ _.__ Phone: (816) 231-8200 1601 Bellefontaine Fax: (816) 231-8203 Kansas City. MO 64127 July 18, 2012 Northpoint Development Group 1300 NW Briarcliff Parkway, Suite 250 Kansas City, Missouri 64116 Re: Riverside Horizons Change Order tt2 Summary Attn: Brad Haymond Per your request, I have summarized the items included in change order t!2 which was billed on our June 2012 pay application for the Riverside Horizons project. The items noted below are per our onsite meetings and phone conversations. Please see the summary below and feel free to call if you have any questions. Change Order H2 Value: $163,607.75 ✓ PCO item q9- GSC billed 82% of the summary provided to Northpoint for the material imported from Premium Waters until Olsson's surveying perform a complete topographic survey of the area initially surveyed. Upon completion of the entire survey, GJS will bill the remaining amount of PCO #9. This material was gathered in lieu of digging canals deeper. o PCO i19 preliminary value: $92,490.75 ✓ PCO item It18- The work included in PCO #18 consisted of the added square footage to the spec I building pad. o PCO �18 value: $22,001.00 ✓ PCO item t►19- The work included in PCO #19 included the added costs to undercut 41 street 9", place fabric, provide and place 2" to 4" clean rock in lieu of stabilizing with 9" of CKD. This provided an all weather road that would hold up until asphalt paving was laid. o PCO S39 value: $49,116.00 Sincerely, George J. S6aw Construction Co. Andy Nimz Project Manager CONCREfE • EXCAVA710N • GRADING • WRECKING Contractu Name: Georpe Shaw Construction Changes in Plana amUOr ConsVuctlon ProjeU Name: Haimna Pmject Lxepon: Riveni0e, Missouri Reouest 7q PfOled NNllhlt: rK rau«iw aunw�ro �nea'vw evnm.mw.e.a.. na�:•a mm�rwx �nart.t W n. conmmw um rm«� rrhs� rmv.a hue cumum u. mw w• C011�. �8�8: <IOMM�NIM�atuYMLMM9u�M4aM1OTWAMn�ItlWn��MwnmIMBqPrt9wl pete PRparM� Page NumDer: � of � REWIIRED CHAMGES IN PRESEM CONiRACT Ca1Vaa INm Na ttem Oesctiption NM Cturqe Reasat yy n5.gp Pledng Fill Meteriel Importatl by Lillig 55 745.87 Cosls aaeodeletl wNh IipM pleirta for nigM 9liifls 55.188.75 hmporery Gewaterin9 on ske in lakes enE carels � y�g 5p Buld GeASyher Ped -Thia wi0 be credibd Dedc on en uproming CO E78.57274 Spec 1 BuaCifq' Increasetl aquare footape b patl $15 356.85 Spec 1 Biid"ng - Increesed square fuotege b peC 573.54320 RemeAlafion ol soR spots in Spec I petkin9 area pet Olsson's recammendeliona =t7 594.85 Bui�d C,aAeBher Ped - This wiA he crcditad beck on an upcoming CO 55784.80 RBmeEiation U saX spots in Gallagher paiking area tlue to VFA tlewatering trench 51.585.� RemetllaUon of soR spots in Spec 1 peilung area per Olsson's recommerWaGons t8 a88.74 Pledng entl compeding impateE maMriel (ar 280,000 af ped f23.S10.00 8uild Galhghar Pe0 - Thia will be creCrteE hedc on en upmmuq CA E5,249.85 Pledrp eM mmpectln0 �mP� ��I for 280,000 sf patl 515133.43 Spec 2 EuilEing - Increase0 aquarelootepe m pad �� �q Plarinp antl compeding imported materiel for 280,000 sf patl 5173.475.93 e �Sf .. . Serving Greater %ansas City Since 1928 � (816) 231-8200 1601 Bellefontaine Fax: (616) 231-8203 � Kansas City, MO 64127 • I August 30, 2012 Northpoint Development Group 1300 NW Briarcliff Parkway, Suite 250 Kansas City, Missouri 64116 Re: Rlverside Horizons Change Order #3 Summary Attn: Brad Haymond Per your request, I have summarized the items included in change order I#3 which will be billed on our August 2012 pay application for the Riverside Horizons project. The items noted below are per our onsite meetings and phone conversations. Please see the summary below and feel free to call if you have any questions. b Change Order #3 Value: $173,475.93 ✓ PCO item q4- The work included on this PCO item included placing, watering, & compading imported material for the 280,OOOsf pad site. o PCO 7i4 Value: $3,775.80 ✓ PCO item tt5:- The work included on this PCO item included providing light planu to the site for night shihs to take advantage of the dry conditions. o PCO #5 Value: $5,745.87 ✓ PCO item p 6-The work included on this PCO item included dewatering throughout the site during wet portions of the project. This included both lakes and the canals. o PCO q6 Value: $5,186.15 ✓ PCO item li10- The work included on this PCO item was constructing the Gallagher pad. $31,485.00 of this Invoice was paid direct and $33,328.50 is included in CO #3. This cost will be credited back as Gallagher paid for the pad construction as part of their land sale which was not finalized at this time. o PCO k10 Value: $33,328.50 (LO value only, see above) ✓ PCO item N32- We were directed to bill on our August 2012 pay application. The work included on this PCO item included increased square footage on Spec I. o PCO #12 Value: $16,512.15 ✓ PCO item #13- The work included on this PCO item included finishing the pad's increased square footage on Spec I in addition to PCO #12. o PCO tf13 Value: $15,358.95 ✓ PCO item lil6- The work included on this PCO item included T&M work fnr soil remediation af the Spec I parking area per Olsson's recommendations. Due to unknown depths and material failure, the soil remediation had to be done as a field directive with Olssan. o PCO ql6 Value: $13,543.20 CONCRETE • EXCAVATION • GRAD[lVG • WRECKING ✓ PCO item #17- The work included on this PCO item included re-vising the footprint of the Galiagher pad per the revised drawings. This cost will be credited back as Gallagher paid for the pad construction as part of their land sale which was not finalized at this time. o PCO #17 Value: $17,594.85 ✓ PCO item q21- The work included on this PCO item included performing parking area remediation in the Gallagher parking lot per Olsson's recommendations in areas where the sanitary sewer dewatering trench was previously used and filled in. o PCO It21 Value: 55,784.60 ✓ PCO item i►22-The work included on this PCO item included further remedial measures due to wet conditions in the Spec I parking area. o PCO #22 Value: $1,585.65 ✓ PCO Rem #23- The work included on this PCO item included placing, watering, & compacting imported material for the 280,OOOsf pad site. o PCO 1t23 Value: $6,486.75 ✓ PCO item A27- The work included on this PCO item included additional pad work for Gallagher re- construction of the pad from its original layout. This cost will be credited back as Gallagher paid for the pad construction as part of their land sale which was not finalized at this time. o PCO IF27 Value: $23,330.00 ✓ PCO item q32- The work included on this PCO item included placing, watering, & compacting imported material for the 280,OOOsf pad site. o PCO #32 Value: $5,249.85 ✓ PCO item ri33- The work included on this PCO item included additional square footage to Spec II building pad. o PCO #33 Value: $15,133.43 ✓ PCO item ri34 The work included on this PCO item included placing, watering, & compacting imported material for the 280,OOOsf pad site. o PCO k34 Value: $4,880.18 Sincerely, George J. S6aw ConstrucNon Co. Andy Nimz Project Manager CONCRETE • DCCAVATION • GRADING • WRECKING Conirector Name: Geoipe Shaw Constructian Changea in Plana aMlor ConaWction Pmject Name: Homm�s ProjectLocation: Riverside, Missouri Reauest#4 Project Number: m.ram..wwro� m m.onuw �mm.moi.a.� �.a.�am m.s�.� izw.e n m. com,m� o� m�.nm..nw �.s�e b m. com,m� s.,s�cd. a.�w ConUact Date: '�.m..�wa <o..uucm w.mu. mm m..am,�.a w•oam.'a+.� on me ae r�ew. Date Preparetl: Pape Number: 1 of i REQUIREDCHANGESINPRESENTCONTRACT Contract kem No. Item Descnption Net Change Reamn $18,775.90 Imported Material used on 80,000 sf Building Pad gg,5qg_�g Atltlitional tlrying p�ocetlures tor 41st s4eet due to high moisture content levels $42,157.50 Dirtwork associatetl wilh Spec 2 pad DreD $28,425.00 DirtwoAC assxiated wilh 80,000 sf patl prep $80,599.50 Dirhwrk essociated wiM 280,000 sf pad prep $5,663.70 Placing and wmpacting imported material for 280,000 sf pad $5,559.08 Placing and compacting imported matenal for 280,000 st pad 52,697.00 Placing and compecting imported material for 280,000 sf pad $193,426.Bfi e `5�:� . Serving Greater Kansas City Since 1928 -- ------- —... Phone: (816) 231-8200 1601 Bellefontaine Fax: (816) 231-8203 Kansas City, MO 64127 September 28, 2012 Northpaint Development Group 1300 NW Briarcliff Parkway, Suite 250 Kansas City, Missouri 64116 Re: Riverside Horizons Change Order H4 Summary Attn: Brad Haymond Per your request, I have summarized the items included in change order #4which will be billed on our September 2012 pay application for the Riverside Horizons project. The items noted below are per our onsite meetings and phone conversations. Please see the summary below and feel free to call if you have any questions. Change Order #4 Value: $193,426.86 ➢ PCO item if9- We billed 82% of this invoice on change order ti2. Upon completion of topographic surveys by both Sitewerks and Olsson, we billed the remaining 18% of PCO #9 on change order #4. o PCO It9 Value: $18,775.90 ➢ PCO item #20- The work included in PCO #20 consisted of appiying fly-ash to 41" street following the undercut of 41" street and uncovering saturated soils. 41" Street allowed access to the site for all contractors. o PCO p20 Value: $9,549.18 ➢ PCO item #28- The work included in PCO #28 consisted of additional material due to square footage of Spec II. o PCO #28 Value: $42,157.50 ➢ PCO item p29- The work included in PCO tf29 consisted of placing additionai material on the west SOk pad in a sloped fashion to allow water to drain off. o PCO 1t29 Value: $28,425.00 ➢ PCO item #30- The work included in PCO #30 consisted of placing additional material on the 280k pad in a sloped fashion to allow water to drein off. o PCO #30 Value: $80,599.50 ➢ PCO item #37- The work included in this PCO consisted of placing and compacting imported material on the 2n 280k pad site in lieu of taking the canals and lakes deeper. o PCA t137 Value: $5,663.70 CONCRETE • EXCAVATION • GRADING • WRECKING ➢ PCO item #40-The work included in this PCO consisted of placing and compacting imported material on the 2 n° 280k pad site in lieu of taking the canals and lakes deeper. o PCO q40 Value: $5,559.08 ➢ PCO item #41- The work included in this PCO consisted of placing and compacting imported material on the 2"" 280k pad site in lieu of taking the canals and lakes deeper. o PCO tf41 Value: $2,697.00 Sincerely, George J. Shaw ConstrucHon Co. Andy Nimz Project Manager CONCREfE • EXCAVATION • GRADING • WRECKING Conhaclp Name: Geaue Shaw Con8WClian Changes in Plans anAlor ConsVUCHon PtojeU Nema: Hofimns PmlectLOCatiwf: Rivarside.Missou�f Reouest#5 Prajecl Wmber. m. iaw��n a.�w mwwynnm.e�aNwr�.w ��cw.e um.«ma....�.0 p m.rmamv u m nw mo+wM1.mee m e�camm.s. m.aa ��*.nw � ww�.imnnun.e werou. rom u.mmme au+ie...w..�o� m. ea wepo.+ Cofnract Dale: Date Preparetl: Page Number. 1 d 7 REQUIRED CHPNGES IN PRESENT CONTRACT COnVacl ttdn �. Mem �esc�tiaf Ne[ Clian9a Reason yL,898.45 Ofying metlatl6 useE 41at StreSt antl 280k patl 577.915.00 ABJ 8 CKD Por 43rtl street e#enspn to IIR gtatlon 510,750.80 Pledng antl oompecGng Nnporle0 ma[erial tor 280,000 sf pnd f4,531A3 RemediaMq eoft areas tivoug�oul Spec 3 parking area EtM285.00 Dirtwork assaiatW wHh SP� 3 P� PreP 5105,06270 Requiretl svrale changes per MODOT abnp 635. Wo�lc Eone m T8M (wNh rat to exceed price) Oue to saWrakd ard incansiatent sotl E347.440.76 e �S' .. Serving Greater Kansas City Since 1928 Phone: (816) 231-8200 �� 1601 Bellefontaine Fax: (816) 231-8203 Kansas Ciry, MO 64127 October 24, 2012 Northpoint Development Group 1300 NW Briarcliff Parkway, Suite 250 Kansas City, Missouri 64116 Re: Riverside Horizons Change Order #5 Summary Attn: Bred Haymond Per your request, I have summarized the items included in change order #5 which will be billed on our October 2012 pay application for the Riverside Horizons project. The items noted below are per our onsite meetings and phone conversations. Please see the summary below and feel free to call if you have any questions. Change Order � Value:$347,440.78 ✓ PCO item #36- The work included on this PCO item included remediating soft spots on 41�` street and the Spec III/PFG building pad site prior to pad construction. o PCO q36 Value:$4,896.45 ✓ PCO item q44:- The work included on this PCO item included extending 43`� street to the pump station to allow access for the City of Riverside and Kansas City M0. The street work included stabilizing the sub-grade with CKD and placing 6" of AB-3 on top. o PCO #44 Value:577,915.00 ✓ PCO item # 45-The work included in this PCO consisted of placing and compacting imported material on the 2"" 280k pad site in lieu of taking the canals and lakes deeper. o PCO 1t45 Value: $30,750.80 ✓ PCO item 1i50- The work included in this PCO item included over excavating soft spots throughout the PFG/Spec III parking area where the existing sanitary sewer trench was backfilled o PCO ti50 Value: $4,531.43 ✓ PCO item ri51- The work included in this PCO item included placing and compacting additional material for increased pad square footage for PFG/Spec III. o PCO fi51 Value: $144,285.00 ✓ PCO item #53-. The work included in this PCO item included placing and compacting the berm along the 635 canals per the PR 2 drawings. The berm was an added requirement from MODOT that was not in the original drawings. This work was priced and then trecked on an hourly basis (notto exceed) the quoted price. o PCO #53 Value: $105,06210 CON�RETE • EXCAVATION • GRADING � WRECKING Sincerely, George J. Shaw Construction Co. Andy Nimz Project Manager CONCREfE • EXCAVATION • GRADING • WRECKING ContreCla Name: Geor9e Shew CoruNxBo� �hanges In Plans anNOr ConsVUCdon Projec[ Naine: Hamm�s PrqeU Location: R"rvBrslEe, Missouri Reaues[ 96 ProjeCl Nulnbef: m. nw'�o w�s�m n. �wnn.mwex.. �.awe m m.smu ��.,nea M u»cxauaw� m mwa.,.�nw m� W u. c�ean«. �.,�na. wm. � in..me w�mwau� rtom m..w�.w a�.mi...mmm m. ae niopow cmaaa oere: papg prepared: Page Number 1 of 1 REWIIRED CHANGES W PRESENT CONTRACT ConffxM ttent No. Ilem �esap�n Net Change R�san T/Zg ypa Sg AtlA Asphatt Rosds Into ConUaG 5728.204.59 e s� Serveng Creater Kansas Ctty Since 1928 _»_� _ _ — ----- __...-- Phone: (816) 231-8200 1601 Bellefontaine Fax: (816) 231-8203 Kansas Cfty, MO 64127 October 24, 2012 Northpoint Development Group 1300 NW Briarcliff Parkway, Suite 250 Kansas City, Missouri 64116 Re: Riverside Horizons Change Order q6 Summary Attn: erad Haymond Per your request, I have summarized the items included in change order q6 which will be bilied on our October 2012 pay application for the Riverside Horizons project. The items noted below are per our onsite meetings and phone conversations. Please see the summary below and feel free to call if you have any questions. Change Order #6 Value: $726,204.59 ➢ PCO item #52-The work included in PCO #52 consists of the industrial road asphait paving scope. This item was not included in our contract originally and also includes asphalt index changes to today's market. o PCO k52 Value: $726,204.59 Sincerely, George J. Shaw Construction Co. Andy Nunz Project Manager CONCRECE • EXCAVATION • GRADING � WRECKING