HomeMy WebLinkAboutR-2013-004 Mattox Road CO1 Northpoint Project ManagementRESOLUTION NO. R- 2013 -004
A RESOLUTION AUTHORIZING, APPROVING AND RATIFYING CHANGE ORDER 1 TO
THE AGREEMENT BY AND BETWEEN THE CITY OF RIVERSIDE AND NORTHPOINT
DEVELOPMENT, LLC (formerly Briarcliff Realty, LLC) FOR PROJECT MANAGEMENT OF
THE MATTOX ROAD PROJECT RESULTING IN A REVISED CONTRACT AMOUNT NOT TO
EXCEED $90,376.51
WHEREAS, the City issued a Request for Qualifications for Project Management for the
Mattox Road Project which was awarded pursuant to Resolution R- 2012 -019; and
WHEREAS, the Board of Aldermen find it in the best interest of the City to formally
authorize, approve and ratify Change Order 1 to the agreement with NorthPoint Development,
LLC in the amount of $26,376.51, resulting in a total revised contract amount not to exceed
$90,376.51;
NOW THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE
CITY OF RIVERSIDE, MISSOURI, AS FOLLOWS:
THAT Change Order 1 to the Agreement entered into by and between the City and
NorthPoint Development, LLC and incorporated herein by reference resulting in a revised
contract amount not to exceed $90,376.51 is hereby authorized, ratified and approved.
FURTHER THAT the Mayor, City Administrator and all other required city officials are
authorized to execute the change order authorized herein together with any and all documents
necessary or incidental to the performance thereof and to take such other actions and /or
execute and deliver for and on behalf of the City all certificates, instruments, agreements and
other documents as may be deemed necessary or convenient to carry out and comply with the
intent of this Resolution.
PASSED AND ADOPTED by the Board of Aldermen and APPROVED by the Mayor of
the City of y iverside, Missouri, this . l*Qday of January, 2013.
Arl - EST< •'�
w � v
Robintittrell, City Clerk
thleen L. Rose, Mayor
Approved as to form:
nc mps , ity Attorney
CITY OF
�RIVE F�
Upstream from ordinary.
2950 NW Vivion Road
Riverside, Missouri 64150
MEMO DATE: January 14, 2013
AGENDA DATE: January 22, 2013
TO: Mayor and Board of Aldermen
FROM: Travis Hoover
RE: Change Order I for the Mattox Road Project
BACKGROUND: Change Order I includes an additional payment for SKW. This was in the
original budget for special inspections, but not included as a cost in the original
project management agreement. The SKW contract was with NorthPoint and
not with the City.
Original Contract Amount
$64,000.00
Total of Previous Changes
$0
Total this Change Order
$26,376.51
Current Contract Total
$90,376.51