HomeMy WebLinkAboutR-2013-120 Utility Agreement KCP&L Vivion Road Bridge Over Line Creek RESOLUTION NO. R- 2013 -120
A RESOLUTION APPROVING AN AGREEMENT WITH KANSAS CITY POWER AND LIGHT
COMPANY IN CONNECTION WITH THE VIVION ROAD BRIDGE OVER LINE CREEK
PROJECT
WHEREAS, the Board of Aldermen find it is in the best interest of the City to provide for
the relocation of certain existing overhead electrical lines to underground along NW Vivion Road
in connection with the reconstruction of the Vivion Road Bridge over Line Creek as set forth in
Exhibit A attached hereto;
BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE CITY OF RIVERSIDE,
MISSOURI AS FOLLOWS:
THAT the Utility Agreement, in substantially the form attached hereto, with between the
City of Riverside and Kansas City Power and Light Company is hereby approved and the Mayor
is hereby authorized to execute the Agreement on behalf of the City;
FURTHER THAT funds to reimburse KCPL for the cost to perform such relocation in the
amount of $29,316.35, are hereby approved and authorized;
FURTHER THAT the Mayor, the City Administrator, the Finance Director, the City
Attorney and other appropriate City officials are hereby authorized to take any and all actions as
may be deemed necessary or convenient to carry out and comply with the intent of this
Resolution and to execute and deliver for and on behalf of the City all certificates, instruments,
agreements and other documents, as may be necessary or convenient to perform all matters
herein authorized.
PASSED AND ADOPTED b the Board of Aldermen and APPROVED by the Mayor of
the City of Riverside, Missouri, the/if day of7/oile n be) , 2013.
1
Kat leen L. Rose, Mayor
/"ti 1 T: •
Robin Littfell, City Jerk
RESOLUTION NO. R- 2013 -120
Exhibit A
Utility Agreement
Authority: City of Riverside, Platte County, MO
Project Route: NW Vivion Rd — NW Karen Blvd to NW
Klamm Rd
WR. No. 503599
LINE C.O. No. 03 -68192
Distribution Facilities
ev ILI2tYAGWEJKE9v!T
THIS AGREEMENT is made this 23rd day of October, 2013, by and
between KANSAS CITY POWER & LIGHT COMPANY, a Missouri corporation,
with its address at P.O. Box 418679, Kansas City, Missouri 64141, hereinafter called
"Company ", and The City of Riverside, Missouri in the State of Missouri acting by
and through the City Council, hereinafter called "City ".
WITNESSETH:
WHEREAS, the City proposes to relocate existing overhead electrical lines to
underground along NW Vivion Rd from NW Karen Blvd to NW Klamm Rd in
Riverside, Missouri for Vivion Road improvements and Line Creek bridge replacement.
WHEREAS, in order to construct said electric line in accordance with said plans, it will
be necessary to adjust certain facilities of the Company so as to maintain the present
services of said Company, such changes being generally shown in legend on Company's
plans, identified as Company's C.O. No. 03 -68192 consisting of two (2) sheets, which
plans are by reference incorporated herein and made a part hereof.
NOW, THEREFORE, in consideration of the mutual covenants herein contained, it is
agreed as follows:
I. Company's facilities which will be relocated and rebuilt include distribution lines
which are essential for Company to keep in operation in order to furnish continuous
electrical service to Company's customers served by said lines. Therefore, Company
may maintain such facilities in their existing locations until such time as new right of way
is acquired or made available and /or governmental permits are secured by the Company
for placement of its relocated facilities and it has relocated existing facilities or
constructed new facilities as required.
Company will proceed with the relocated and /or construction without
unreasonable delay after the new right of way is available.
2. Company shall develop the adjustment costs of the work by using the actual and
related indirect costs accumulated in accordance with Company's established work order
accounting procedure, and Company shall keep a detailed and accurate account of all
labor, materials, supplies, incidentals and other necessary costs involved in such work.
The City Engineer, or any other authorized agent of the City shall have access at all
reasonable times to such Company records.
3. Company shall notify the City of the nature and extent of any substantial change
made in the plans hereinabove referred to, and such plans shall thereupon be deemed
modified to include such changes.
4. City is responsible for the cost of special ditching required for soil conditions
including, but not limited to the presence of rock or other environmental issues which
prevents the use of normal trenching and backfilling practices used in trenchable soil.
City is responsible for maintaining grade and clearance during Company's construction.
5. City will reimburse the Company for the cost of adjustments affecting those
portions of Company's facilities, which were installed on private property and are being
relocated due to this project.
6. City's obligation for such relocation is estimated to be $29,316.35. This estimate is
based on 2012 labor and material costs, and may change significantly depending upon the
actual date of construction. Again, these are estimated costs, with final costs dependent
upon actual construction. Upon completion of the work in accordance with the plans,
City will promptly reimburse Company for the cost of such work upon submission of a
statement for such cost to the City.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement
be duly executed as of the date first above written.
KANSAS CI "OW OW - GHT COMPANY
By: t// i�ti
ay. dr
CITY OF RIVERSIDE MISSSOOURI
By: ` CQ.t�u eet
Title:
EXHIBIT A
VIVION RD & LINE CREEK BRIDGE - WR 503599
AMOUNT OF ORIGINAL UTILITY AGREEMENT = $133,037.25
(MINUS) JOB SCOPE CHANGE - $41,050.00
(MINUS) 3 ADDITIONAL 6" PIPES ON LINE CREEK BRIDGE - $62,670.90
FINAL UTILITY AGREEMENT AMOUNT = $29,316.35
CITY OF
Riv „si
MISSOURI
Upstream from ordinary.
2950 NW Vivion Road
Riverside, Missouri 64150
MEMO DATE: November 7, 2013
AGENDA DATE: November 18, 2013
TO: Mayor and Board of Aldermen
FROM: Travis Hoover
RE: Vivion Road Bridge over Line Creek (137 -009)
KCPL Utility Agreement
BACKGROUND: The original SKW plans consisted of undergrounding all utilities within the
project limits including utilities in Northmoor. KCPL designed their respective
work under 2 project numbers due to the separate equipment needed for
different phasing. Complications in acquiring the necessary utility easement in
Northmoor resulted in undergrounding only the utilities within the Riverside
City limits. One utility agreement was approved and paid by the City. The
estimated costs paid were similar to the costs of the overall reduced scope of
work. However KCPL requires 2 utility agreements to coincide with the
respective phasing. The City will receive a partial refund for the previously
executed agreement due to actual costs resulting Tess than estimated costs. This
2 " agreement is for the remainder of the work completed in the additional
phase. This agreement includes a deduction for a partial refund for the actual
costs resulting Tess than estimated costs, and a refund for additional facilities
installed for KCPL.
RECOMMENDATION: Staff recommends approval of the resolution and acceptance of the utility
agreement with KCPL for the Vivion Road Bridge over Line Creek project.
BUDGETARY IMPACT: Approximately $29,316.35 will be expended out of the Vivion Road Bridge over
Line Creek budget for the construction under this contract.