HomeMy WebLinkAboutR-2015-028 CO 4Tenoch Construction 2013-14 Street Maintenance RESOLUTION NO. R-2015-028
A RESOLUTION AUTHORIZING, APPROVING AND RATIFYING CHANGE ORDER 4 TO
THE AGREEMENT BY AND BETWEEN TENOCH CONSTRUCTION INC FOR 2013-14
STREET MAINTENANCE PROJECT (313-013) RESULTING IN A REVISED CONTRACT
AMOUNT OF $488,827.05 FOR SUCH PURPOSES
WHEREAS, the City issued an Invitation to Bid for the 2013-14 Street Maintenance
Project which was awarded to Tenoch Construction Inc. pursuant to Resolution R-2014-033,
and Change Order 1 to said contract was approved by Resolution R-2014-068; and Change
Order 2 to said contract was approved by Resolution R-2013-083; and Change Order 3 to said
contract was approved by Resolution R-2014-103; and
WHEREAS, the Board of Aldermen find it in the best interest of the City to formally
authorize, approve and ratify Change Order 4 to the agreement with Tenoch Construction Inc.,
resulting in a total revised contract amount not to exceed $488,827.05;
NOW THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE
CITY OF RIVERSIDE, MISSOURI, AS FOLLOWS:
THAT Change Order 4 to the Agreement entered into by and between the City and
Tenoch Construction Inc. and incorporated herein by reference resulting in a revised contract
amount not to exceed $488,827.05 is hereby authorized, ratified and approved.
FURTHER THAT the Mayor, City Administrator and all other required city officials are
authorized to execute the change order authorized herein together with any and all documents
necessary or incidental to the performance thereof and to take such other actions and/or
execute and deliver for and on behalf of the City all certificates, instruments, agreements and
other documents as may be deemed necessary or convenient to carry out and comply with the
intent of this Resolution.
BE IT REMEMBERED that the above was PASSED AND APPROVED by a majority of
the Board of Aldermen and APPROVED by the Mayor of the City of Riverside, Missouri, this
2nd day of June, 2015.
U
. ' a een L. Rose, Mayor
ATTEST:
Rollin Littrgll, illy CI@rR
CITY OF
RIVER'S
�- MISSOURI
Upstream from ordinary.
2950 NW Vivion Road
Riverside, Missouri 64150
MEMO DATE: May 28, 2015
AGENDA DATE: June 2, 2015
TO: Mayor and Board of Aldermen
FROM: Travis Hoover
RE: Change Order 4: TENOCH CONSTRUCTION COMPANY
2013-14 Street Maintenance Project (313-013)
BACKGROUND: The 13-14 Street Maintenance Project was approved on 5-20-14 and consists of:
• Curb and Gutter replacement throughout the City
• Sidewalk Connection along 50`h Terr into Gatewoods
• Mill and overlay of St.Joe Blvd
• Trail connection from Argosy Casino Parkway to EH Young Park
• Trail connection from Klamm to Interurban
Change order#1 was approved on 7-1-14 for a total of$12,865.00
Change order#2 was approve on 8-19-14 for a total of$25,838.25
Change order#3 was approve on 12-2-14 for a total of$118,590.76
Change order#4 Items to include:
• -$5,391.96 for an underrun of additional street patching (line item approved on
12-2-14)
• $17,200.00 for additional approach work on the Argosy Casino Parkway Bridge
over BNSF (line item approved on 5-5-15)
• $28,800.00 for additional sidewalk repair, pedestrian rail cleaning, and crack seal
on the Vivion Rd bridge over Line Creek (New Request)
BUDGETARY IMPACT: Approximately $488,827.05 will be expended out of the total 2013-14 Street
Maintenance budget of$750,000.00 for the construction under this contract.
Original Contract Amount $ 290,925.00
Total of Previous Changes $157,294.01
Total this Change Order $40,608.04
Current Contract Total $488,827.05
RECOMMENDATION: Staff recommends approval of the resolution and acceptance of the change order
with Tenoch Construction to continue with work for the 2013-2014 Street
Maintenance Project.