HomeMy WebLinkAbout1435 Authorizing and Approving CO 18 George J. Shaw Construction Z
BILL NO. 2015-061 ORDINANCE NO./4d 5
AN ORDINANCE AUTHORIZING AND APPROVING CHANGE ORDER 18 TO THE GEORGE
J. SHAW CONSTRUCTION CO. CONTRACT
WHEREAS, Briarcliff Realty, LLC and the City entered into that certain Master
Development Agreement dated May 10, 2011 (the "MDA"); and
1 WHEREAS, Briarcliff Realty, LLC assigned all its rights and obligations under the MDA,
but not its rights and obligations under the MDA First Amendment, to Briarcliff Horizons, LLC, an
affiliated entity of Briarcliff Realty, LLC pursuant to Section 12.5(b) of the MDA; and
WHEREAS, on or about February 13, 2012, Briarcliff Horizons, LLC filed articles of
amendment with the Missouri Secretary of State changing its name to Riverside Horizons, LLC
("Developer"); and
WHEREAS, pursuant to the MDA, Developer agreed to construct and complete certain
Public Infrastructure Improvements on the Briarcliff Horizons Site, as such terms are defined in
the MDA; and
WHEREAS, the MDA established Infrastructure Phase 1 improvements to consist of the
lakes, canals, and landscaping, and further established the cost estimate and budget for the
Infrastructure Phase I Improvements to be Thirteen Million One Hundred Forty-Six Thousand
Six Hundred Eighty-Three Dollars ($13,146,683.00); and
WHEREAS, on or about August 21, 2011, Developer competitively bid the Infrastructure
Project as defined in the MDA and subsequently submitted its recommendation to the City to
award a portion of the project known as Horizons Earthwork I Site Utilities (City Project No. 607-
1 001)to George J. Shaw Construction Co. ("Shaw"); and
WHEREAS, on or about November 1, 2011, the Board of Aldermen approved Shaw as
the contractor to perform construction services related to the Earthwork portion of Horizons
Earthwork/Site Utilities; and
1 WHEREAS, on or about December 1, 2011, Developer entered into an agreement with
I Shaw to perform construction services related to a portion of the Horizons Earthwork / Site
Utilities in an amount not to exceed Seven Million Three Hundred Thirty Thousand Four
Hundred Seventy-Seven Dollars ($7,330,477.00) ("Shaw Contract"); and
WHEREAS, on or around August 1, 2012, Developer assigned all of its duties and
obligations under the MDA to construct and complete the public infrastructure and other public
1 improvements as set forth in the MDA to Northpoint Development, LLC ("NPD") pursuant to
Section 12.5(b) of the MDA; and
WHEREAS, the Board has previously approved Change Orders 1 thru 17 to the Shaw
Contract totaling an additional cost of THREE MILLION TWO HUNDRED NINETY-EIGHT
THOUSAND FOUR HUNDRED FIFTY THREE Dollars and Twenty-Two Cents ($3,298,453.22);
and
WHEREAS, NPD and Shaw request approval of, and City staff recommend and request
the Board to approve, the following Change Order 18 attached hereto as Attachment A and
incorporated herein, to the Shaw Contract:
1 WA 6057970.1
Change Order 18: Upon receiving prior approval from the City Administrator or
the City Administrator's designee in each instance, Shaw may add an additional
weir and perform necessary work related thereto as provided for in Attachment A;
For a total net cost INCREASE pursuant to Change Order 18 of SIXTY NINE
THOUSAND SEVEN HUNDRED SIXTY ONE DOLLARS ($69,761.00) to increase the overall
contract total to TEN MILLION SIX HUNDRED NINETY EIGHT THOUSAND SIX HUNDRED
NINETY ONE DOLLARS and Twenty-Two Cents ($10,698,691.22) for Shaw; and
WHEREAS, Section 5.5 and 5.6 of the MDA require City y a pproval for all change orders
1 to the Infrastructure Construction Documents; and
WHEREAS, the Board of Aldermen find that Change Order 18 to the Shaw Contract is in
the best interest of the City in that such action fulfills a public purpose and will further the growth
of the City, facilitate the development of the entire Horizons site, improve the environment of the
City, foster increased economic activity within the City, increase employment opportunities
within the City and otherwise is in the best interests of the City by furthering the health, safety,
and welfare of its residents and taxpayers.
NOW THEREFORE, BE IT ORDAINED BY THE BOARD OF ALDERMEN OF THE
CITY OF RIVERSIDE, MISSOURI, AS FOLLOWS:
SECTION 1. BEST INTEREST OF THE CITY TO APPROVE CHANGE ORDER. NPD
and Shaw request approval of, and City staff recommend and request the Board to approve,
Change Order 18 to the Shaw Contract, attached hereto as Attachment A and incorporated
herein, and the Board finds it is in the best interest of the City and that such approval fulfills a
public purpose and will further the growth of the City, facilitate the development of the entire
Horizons site, improve the environment of the City, foster increased economic activity within the
City, increase employment opportunities within the City and otherwise is in the best interests of
the City by furthering the health, safety, and welfare of its residents and taxpayers, to approve
Change Order 18, and the Board does hereby approve of Change Order 18 as follows:
Change Order 18: Upon receiving prior approval from the City Administrator or
the City Administrator's designee in each instance, Shaw may add an additional
weir and perform necessary work related thereto as provided for in Attachment A;
For a total net cost INCREASE pursuant to Change Order 18 of SIXTY NINE
THOUSAND SEVEN HUNDRED SIXTY ONE DOLLARS ($69,761.00) to increase the overall
contract total to TEN MILLION SIX HUNDRED NINETY EIGHT THOUSAND SIX HUNDRED
NINETY ONE DOLLARS and Twenty-Two Cents ($10,698,691.22) for Shaw; and
1 SECTION 2. AUTHORITY TO EXECUTE. The Mayor, City Administrator and all other
required city officials are authorized to execute the change order authorized herein, together
with any and all documents necessary or incidental to the performance thereof, and to take such
other actions and/or execute and deliver for and on behalf of the City all certificates,
instruments, agreements and other documents as may be deemed necessary or convenient to
carry out and comply with the intent of this Ordinance.
SECTION 3. EFFECTIVE DATE. This Ordinance shall be in full force and effect from
and after the date of its passage and approval.
2 WA 6057970.1
1
BE IT REMEMBERED that the above was PASSED AND APPROVED by a
majority of the Board of Aldermen, and APPROVED by tpe Mayor of the City of Riverside,
Missouri, this 8th day of September, 2015.
Kathla6n L. Rose, Mayor
A7F-S;
Robin Kincaid, City Clerk
Approved as to form:
Spenc ane Britt & Browne LLP
Spe ' I C nsel to the City
by J P,Bed r
3 WA 6057970.1
ATTACHMENT A
COVER MEMO, CHANGE ORDER 18, AND BACKUP DOCUMENTS
1
9a
4 WA 6057970.1
9
f+ �
4.
/
Serving Greaser Kansas City Since 1928
Phone (816)231-8200 1601 Bellefontaine Fax (816)231-8203
Kansas City,MO 64127
July 14,2015
Northpoint Development
5015 NW Canal Street,Suite 200
Riverside,MO.64150
Re: Riverside Horizons-Added Rock Walls,Earth Berms,&Concrete Work
Attn: RI Agee
As discussed in various phone conversations and emails,we are pleased to provide the price below
for the added rock walls,earth berms,concrete weir,&culvert walls per Olsson's drawings dated
05/12/2015.
Schedule of Work:
General Conditions: $ 6,060.00
Retaining Wall Prep: $ 5,919.00
Leveling Trench: $ 7,828.00
Wall Construction: $16,680.00
Wall Backfill &Misc.Grading: $ 8,652.00
Earth Benns Construction: $15,364.00
3ueir Wstl .
8-4;9-72700—
Concrete
--4;9}Concrete Overflow: $ 9,258.00
Qualifications:
> Permits
• Summer/Winter Concrete Protection
> Dewatering
> Rock Retaining Wall Material
> Any retaining walls not accessible from the main site,will need to be constructed from inside
the canal(prior to any liner). Liner construction will need to be completed on a time and
material basis.
Sincerely,
George J.Shaw Construction Co.
Andy Nimz
Project Manager
CONCRETE • EXCAVATION • GRADING • WRECKING
B`mR S;o n p
g.� : �y+." = 0 m a? a v
S a $di-, F1 z N g 's
'o
glIg la . j ya' li _ Razz
B 0 z _ m ° m m$ JJjJJ
V 3m Qa3 2 ;„ Nr $ A o 5g o a ON
�O
} E .� sgn G1 m a _ 3 m Ici
V�1 O % $uo m 5. Ivo ° a I
2 $ � o ti aff
Foie m u s $ R a
_,9Ya CP
'iii8
c -on c
II
pm
'sasass " a m
f' S$ $ $ $ $ $ n
vzazz0
8 . 800 =
3F c n o
=0383_ ° a 011 101
o
L m 2 j�^ i s i 3 ? a i O
NI m.isa3 z2 Vn sga i v "3 'c o� m
50223 > i "a lis, L+ oS 3
FRgs$ O n 891 awc 3o' Y gia as0
Q n a. CD
33sm m T 3 tis € $ 5 zm :fin O
a= 1 • 'z z S aw m Rail € " y� a' co
F m° s m O m n ? o § Y a w 5 m„i L n
aLt ra ~ n N CO 3 g a 4 S nk mn 18 • D
's 0 o
ge y n o A8 a S F c s z
/Oraa Raz 3 ? m E. g E i il N9 n �Eng f m
Eggs - 33 > 3 ti4Zy _ F a / P `-0943 O 0
a s35o 0 S mm a gg
E ° 8 t 6Qin sa m S' a =a a ; 1 s 3g move z
9 m x — 3
_ z n
• Y3 G. gl.Y . a 2m P sS � .�
Orr
'''5. 'NI °sftag ' a ' s 8 Si o £s
a = n
N og. S U u I - 5 `3'Cr g w m g
f.1 r.ps Qqj S ; z .4 n 8
I• .tA aYm Say . • 4, HMVI S x I2 Ra _
O O :ar,J —11 .
A
9 a 0.301.3t4 R a $ 7 e C m
R .. % 50 ,4= 00
2, 1 a r G
O 0--..i
W U q O
6-“.PC. , b • 5 C O
rNio rat. O g 3f c c
Ig mq
;a
IS
Es
R
: g
Rkz iii
r a.•B
$ R
0
S' � 8 3 ng CD 4
Oa cgz
11 -
CA
CD
0
so $ 80" 0
CD z
"al
s0
�� mm SR
0.— P SR
W M
00 ° ..o.
pO�
lk O O O O O O O o
CITY OF
RIVERSI
MISSOURI
Upstream from ordinary.
2950 NW Vivion Road
Riverside, Missouri 64150
MEMO DATE: September 04, 2015
AGENDA DATE: September 08, 2015
TO: Mayor and Board of Aldermen
FROM: Travis Hoover
RE: Change Order 18: SHAW CONSTRUCTION
Horizons Earthwork& Site Utilities (607-001)
BACKGROUND: The original plans called for riprap to be installed in the canal along the 1-635
ramp. Due to the undesired look of riprap and the high cost of stacking rock,
the decision was made during the May 5, 2015 board meeting to add a new weir.
The modifications to the plans are as follows;
• $6,060.00 for General Conditions
• $30,427.00 for Retaining Wall Labor for additional wall
• $8,652.00 for Retaining Wall Backfill for additional wall
• $15,364.00 for Cuts and Fills (Earth Berms)
• $9,258.00 for Concrete Overflows
*Note: Liner work will be performed on a T&M basis. We expect the costs
for the liner work to be at or below the budget.
BUDGETARY IMPACT: An additional cost of $69,761.00 for Change Order 18 will result in a total
amount of$10,698,691.22 for Shaw Construction.
Original Contract Amount $ 7,330,477.00
Total of Previous Changes $ 3,298,453.22
Total this Change Order $ 69,791.00
Current Contract Total $ 10,698,691.22
RECOMMENDATION: Staff recommends approval of the ordinance and acceptance of the change order
with George Shaw Construction for Horizons Earthwork& Site Utilities.