HomeMy WebLinkAbout1438 CO1 Gunter Construction Company $316,311.28 BILL NO. 2015-064 ORDINANCE NO. L
AN ORDINANCE AUTHORIZING AND APPROVING CHANGE ORDER 1 TO THE GUNTER
CONSTRUCTION COMPANY CONTRACT RESULTING IN AN APPROVED REVISED
CONTRACT AMOUNT OF $316,311.28
WHEREAS, by and through Ordinance No. 1425 the City approved a contract between
the City of Riverside Missouri ("City') and Gunter Construction Company ("Gunter") for
completion of that certain public infrastructure improvement City Project No. 150-219, also
known as the Mattox Rd - 41s' St. to 40th Project, for an estimated cost of installation and
construction of Two Hundred Ninety Nine Thousand Nine Hundred Forty-five Dollars and Zero
Cents ($299,945.00) (the "Contract'); and
WHEREAS, Gunter requests approval of, and City staff recommends and requests, the
Board to approve the following Change Order 1, attached hereto as Attachment A, and
incorporated herein, to the Contract:
Change Order 1:
The construction of Mattox Road from 41St Street to 40th is funded with a CDBG
grant as part of the Riverside Logistic Centre Project. Substantial completion for
construction is complete. This change order consists of line item overruns and
underruns. For a total net cost INCREASE pursuant to Change Order 1 of
Sixteen Thousand Three Hundred Sixty-six Dollars and Twenty-eight Cents
($16,366.28) to increase the overall contract total to Three Hundred Sixteen
Thousand Three Hundred Eleven Dollars and Twenty-eight Cents ($316,311.28)
for Gunter; and
WHEREAS, the Board of Aldermen find that the Change Order 1 to the AGREEMENT is
in the best interest of the City in that such action fulfills a public purpose and will further the
growth of the City, facilitate the development of the entire Horizons site, improve the
environment of the City, fosters increased economic activity within the City, increase
employment opportunities within the City and otherwise is in the best interests of the City by
furthering the health, safety, and welfare of its residents and taxpayers.
NOW THEREFORE, BE IT ORDAINED BY THE BOARD OF ALDERMEN OF THE
CITY OF RIVERSIDE, MISSOURI, AS FOLLOWS:
SECTION 1. BEST INTEREST OF THE CITY TO APPROVE CHANGE ORDER.
Gunter Construction Company ("Gunter") requests, and City Staff recommends, the Board to
approve Change Order 1 to the Agreement, attached hereto as Attachment A and incorporated
herein, and the Board finds it is in the best interest of the City and that such approval fulfills a
public purpose, will further the growth of the City, facilitate the development of the entire
Horizons site, improve the environment of the City, foster increased economic activity within the
City, increase employment opportunities within the City and is otherwise in the best interests of
the City, by furthering the health, safety, and welfare of its residents and taxpayers, to approve
Change Order 1, and the Board does hereby approve of Change Order 1 as follows:
The construction of Mattox Road from 41St Street to 40th is funded with a
CDBG grant as part of the Riverside Logistic Centre Project. Substantial
completion for construction is complete. This change order consists of line item
overruns and underruns. For a total net cost INCREASE pursuant to Change
Order 1 of Sixteen Thousand Three Hundred Sixty-six Dollars and Twenty-eight
Cents ($16,366.28) to INCREASE the overall contract total to Three Hundred
Sixteen Thousand Three Hundred Eleven Dollars and Twenty-eight Cents
($316,311.28)for Gunter.
BILL NO. 2015-064 ORDINANCE NO.
SECTION 2. AUTHORITY TO EXECUTE. The Mayor, City Administrator and all other
required city officials are authorized to execute the change orders authorized herein together
with any and all documents necessary or incidental to the performance thereof and to take such
other actions and/or execute and deliver for and on behalf of the City all certificates,
instruments, agreements and other documents as may be deemed necessary or convenient to
carry out and comply with the intent of this Ordinance.
SECTION 3. EFFECTIVE DATE. This Ordinance shall be in full force and effect from
and after the date of its passage and approval.
BE IT REMEMBERED that the above was PASSED AND APPROVED by a majority of
the Board of Aldermen, and APPROVED by the Mayor of the City of Riverside, Missouri, this
�^'—°day of November, 2015.
Matfileen L. Rose, Mayor
ATTEST:
Robin Kincaid, City Clerk
Approyzd as to form:
pe s ane LLP
Special unsel to the City
By.J ednar
BILL NO. 2015-064 ORDINANCE NO.
ATTACHMENT A
COVER MEMO
CHANGE ORDER
PROVIDED BY LARISSA ANDERSON
CITY OF CHANGE ORDER NO. 1 DaleP,iPamd 0130/2015
(,RIVERSADE
--- - _ -
hussouRl Contractor Name: Gunter Construction
Project Nein: Matlox Rd.-41 at Street to 401h - - pago Nember 16 1
Purled Nunn.,. 150-210ad Pas Attached 0
Conked 0.0; 6130/2015 The following changes to the original contract amount were required to cover cost incurred by the
Project Location: Riverside,Missouri Contractor or(o reflect savings realized by the Contractor as a result of a change In the actual
Constructed quantities from the estimated quantities shown on the Bid Proposal
REQUIRED GRANGES IN PRESENTCONTRACT
Contractor Contractor Contractor Nom Description &Reason for Change Order(Please describe turn below and than follow with lesson for New or New or New or
Lina Ilam No. Previous Previous Previous Unit Change Older) 1) Requested by City 2)Unknown Site COr1tl11Gn8 3)Not Incorporated In ptans/specs Adjusted Adjusted Adjusted
Quantity Unit Price Amount QuantityUnit Price Amount
3 3,0520 $6.50 $25,042.00 SY 2"APWA Type 8.01 Asphaltic Concrete Solace 3,327.00 $8.60 $28,279.50
4 _3052 0- $20.00 $85,458.00 SY _ 9"APWA Type 5Al Asphaltic Concrete Surface 3 327.00 $28.00 $93.156.00
5 197.0 $65.00 $955500 SY 8"KCMM84K COOCmIe Commercial Entrance 157.00 $65.00 $10.205.00
9 31152.0 $5.50 $18,708.00 SV Fly Ash Treatment 3,327.00 $5.50 $18,288.50
7 1.2090 $5.00 _ $6,495,00 CY _ _ _ _ - Embankment 1,349.00 $5.00 $8,745.00
8 2,480.0 $000 S'22,320.00 CV Unclassified Gxcavalion 2,580.00 $9.00 $23.220.00
._ - Curb ---'- Cu_ --_ ---. . _ - -
9 1,1880 . $25.00 _$20650 Do LF 2'.0"Concrete CuN&Gullenvilh ReUar in ul�Type"CG�� 1,235.00 525.00 530,875.00
702240 $2A 00 $5,370 00 LF 2'.0"Concrale Curb&Gutter without Rebar In Curb tY eP CG I) 280.00 $24.00 1 56.720.00
11 2,703.0__ $6.00 S16,758.01) SF __ 5'-0"Concrete Sidewalk 2,A45.00 $6.00 $14,670.00
12 4,0 $Iy175.00 $4,7OOo0 Each __ _ Type"A"$iJewalk Ramp _. _ 5,00 i 175.00 $5,875.00
13 578.0 $850 53,757.00 BY Sodding530.00 $6,60 $3445.00
14 0.34 $4,352.04 S1,4a000 AC Seeding 0.42 $4,352.04 S7.828.23
17 10_$3,345.00 $3.345.00 LS Signage 0.88 $3,345.00 $2875.20
16 1.3060 $1.25 S1632.50 LF 4"Solid Yellow Striping 1296.00 $1.26 $1020.00
19 1510 . $700 $105700LF 6"Solid White Bill,Ling 127.00 $7.00 5889.00
- -_- ____
20 220 $1n.50 5319.00 LF 2.4"Solid Wfum S(riping 0.00 $14.60 $0.00
25 00 so.001 $0.00 1.6 Additional Curb&Gutter and AOA ramp on north end of project 100 _$2293.3_5 _ $2,203.35_
Previous Talar $234,628.50 Adjusted Total $250,994.78
Net Change X16,366.28
SNlemeel of Conked
Original Contract Amount - -- - $299,045.00
Net AIPGUIIt of Previous Additions and Deductions $0.00
Net Contract Amount Prior to This Request $209,045.00
Amount of This Request $16,366.28
New Contract Amount $316,311.28
Percent Change in Contract Amount 546
DESIGN ENGINEER: �1, CITY OF RIVERSIDE,MISSOURI:
compeer IV f/y _ City EnOh :
u.me Pnm<d Travis HooveooVe!
3 ,eeCity Administrator: _
W.. Greg Mills � a!e1.4y- - --
CONTRACTOR: ON-SITE PROJECT MANAGER:
CONTRACTOR'S Certification for Channo Order ON-SITE PROJECT MANAGER Certification for Change Ordo
The unceirgned CONTRACTOR cendies/hat all Manges In accordance with Ire Contract DaunMts.IM on site observations,std
descrboil ebovo no necessary h ad#for the CON I FACTOR Io the data.,.IN INI Meige ores,,IM ms4e pored manager cerlfas
posed w�lh exertion of the contmOdocpnems,end that the 10 the Oise,that to IN bell of the on s4e po:ect emnagers Yfon1ed�e.
vabeI setW of are correct Stith sespcl to the work in!ormalbn art be'or the above relerenced<hiNom are nedeedary In doer to
ani:oaled ceder Inas mange a do, paeedwAhIM...cutand IM contract documents,and Into the vaWs
slated above are cared%h respell to the work enlcWte4 Wa the change order
Cow.nV
INm.woad 7L�Qs,�y D C� ,< �:o Nine Ponid N/A
�1j.
one ',I r.� Dn.: -
ATTACHMENT A
CITY OF
RIVERS
MISSOURI
Upstream from ordinary.
2950 NW Vivion Road
Riverside, Missouri 64150
MEMO DATE: October 15, 2015
AGENDA DATE: November 2, 2015
TO: Mayor and Board of Aldermen
FROM: Travis Hoover
RE: Change Order 1: GUNTER CONSTRUCTION COMPANY
Mattox Rd. —41 st St. to 40th (150-219)
BACKGROUND: The construction of Mattox Road from 41n Street to 40th is funded with a CDBG
grant as part of the Riverside Logistic Centre Project. Substantial completion for
construction is complete. This change order consists of line item overruns and
underruns.
BUDGETARY IMPACT: The addition of $16,366.28 for Change Order No. I will result in a total amount
of$316,311.28 for Gunter Construction.
Original Contract Amount $ 299,945.00
Total of Previous Changes $ 0
Total this Change Order $ 16,366.28
Current Contract Total $ 316,31 1.28
RECOMMENDATION: The City Staff requests approval of the ordinance and acceptance of the change
order with Gunter Construction Company for Mattox Rd. - 41' St. to 40th.