HomeMy WebLinkAboutR-2017-094 2018 Street Maintenance Project RESOLUTION NO. R-2017- 094
A RESOLUTION APPROVING SPECIFICATIONS FOR THE 2018 STREET
MAINTENANCE PROJECT
WHEREAS, the City of Riverside ("City") wishes to approve the specifications for the 2018
Street Maintenance Project (Prof. No. 318-018) attached hereto as Exhibit A and incorporated
herein (the "Specifications"); and
WHEREAS, upon the Board of Aldermen's approval of the Specifications, the City will
issue an invitation to bid to contractors; and
WHEREAS, the Board of Aldermen find it to be in the best interests of the City in order
to provide for the health, safety, and welfare of the businesses and citizens of the City, to
approve the 2018 Street Maintenance Specifications.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF
THE CITY OF RIVERSIDE MISSOURI AS FOLLOWS:
THAT the Specifications, attached hereto as Exhibit A and incorporated herein, are
hereby approved; and
FURTHER THAT the Mayor, the City Administrator, and other appropriate City officials are
hereby authorized to take any and all actions as may be deemed necessary or convenient to carry
out and comply with the intent of this Resolution and to execute and deliver for and on behalf of
the City all certificates, instruments, agreements and other documents, as may be necessary or
convenient to perform all matters herein authorized.
PASSED AND ADOPTED by the Board of Aldermen and APPROVED by the
Mayor of the City of Riverside Missouri the /9* day of December, 2017.
F, Rafteen L. Rose, Mayor
A I:- ST:
Rob'Rrr incaiti„ ity- terk
EXHIBIT "A"
2018 Street Maintenance Project
PROJECT MANUAL
2018 STREET MAINTENANCE PROJECT
PROJECT NO: 318-018
The City of Riverside, Missouri
January 18, 2018
TABLE OF CONTENTS
DIVISION 0 - BIDDING AND CONTRACT DOCUMENTS
ADVERTISEMENT FOR BIDS
INFORMATION FOR BIDDERS
BID FOR UNIT PRICE CONTRACT
BID FORM
BID BOND
EXPERIENCE QUESTIONAIRE
AFFIDAVIT for WORK AUTHORIZATION
AGREEMENT
EXHIBIT A PERFORMANCE BOND
EXHIBIT B PAYMENT BOND
EXHIBIT C STATE PREVAILING WAGE RATES MISSOURI
EXHIBIT D TIME FOR COMPLETION
EXHIBIT E SCOPE OF WORK
EXHIBIT F TECHNICAL SPECIFICATIONS
EXHIBIT G NOTICE TO PROCEED
EXHIBIT H EXAMPLE-APPLICATION FOR PAYMENT FORM
EXHIBIT I EXAMPLE-CHANGE ORDER FORM
EXHIBIT J CERTIFICATE OF SUBSTANTIAL COMPLETION
EXHIBIT K AFFIDAVIT OF COMPLIANCE WITH THE PREVAILING WAGE LAW
EXHIBIT L CONTRACTOR AFFIDAVIT FOR FINAL PAYMENT
EXHIBIT M SUBCONTRATOR AFFIDAVIT FOR FINAL PAYMENT
EXHIBIT N ENGINEER/CONSULT.CERT. for Acceptance&Final Payment
SPECIFICATIONS
DIVISION 1 —GENERAL REQUIREMENTS
Section Description
01015 ONTRACTOR USE OF PREMISES
01030 SPECIAL CONDITIONS
01040 OORDINATION
01051 ONSTRUCTION SURVEY AND STAKING
01060 TANDARD SPECIFICATIONS AND PLANS
01270 EASUREMENT AND PAYMENT
01310 OB SITE ADMINISTRATION
01320 ONSTRUCTION SCHEDULE
01330 SUBMITTALS
01410 TESTING LABORATORY SERVICES
01524 WASTE AREA,MATERIAL STORAGE AND SITE APPEARANCE
01567 POLLUTION CONTROL
01570 TEMPORARY TRAFFIC CONTROL
01732 EMOLITION
DIVISION 2—SITEWORK
Section Description
02230 CLEARING AND GRUBBING
02300 EARTHWORK
02350 EROSION AND SEDIMENT CONTROL
02510 ASPHALT PAVEMENTS
02520 r2RTLAND CEMENT CONCRETE PAVING
03002 JCONCIZETE
DIVISION 0 - BIDDING AND CONTRACT DOCUMENTS
CITY OF RIVERSIDE,MISSOURI
ADVERTISEMENT FOR BIDS
Separate sealed bids for the 2018 STREET MAINTENANCE PROJECT (Project No. 318-018)will
be received by the City Clerk at Riverside City Hall, 2950 NW Vivion Road, Riverside, Missouri until
10:00 A.M.,on January 18,2018,with no pre-bid and then publicly opened and read aloud at Riverside
City Hall.
The Information for Bidders, Form of Bid, Agreement, Specifications, and Forms of Bid Bond,
Performance and Payment Bond, and other Contract Documents may be examined at the office of the
City Engineer at the above city hall address. Copies may also be obtained at the above city hall address.
You can also view the Information for bidders and advertisement on the City of Riverside's website
http://www.riversidemo.coMLrft!s.
The City reserves the right to waive any informality or to reject any or all bids. Each bidder must deposit
a bid security in the amount, form and subject to the conditions provided in the Information for Bidders.
No bidder may withdraw a bid within 90 days after the actual date of the opening thereof.
Attention of bidders is particularly called to the requirements as to conditions of employment to be
observed and minimum wage rates to be paid under the agreement, Section 3-DBE, Segregated Facility,
Section 109,and E.O. 11246. MBE and WBE bidders are encouraged to bid.
Dated: December 19.2017
5
CITY OF RIVERSIDE.MISSOURI
INFORMATION FOR BIDDERS
The City of Riverside,Missouri(the"City")invites sealed bids on the forms contained in the Bid Package
and Contract Documents for the
2018 STREET MAINTENANCE PROJECT
(Project No.318-018)
1. Receipt and Opening of Bids. Bids will be received by the City at the office of the City Clerk,Riverside City
Hall, 2950 NW Vivion Road, Riverside, MO 64150, until 10:00 a.m. on January 18,2018 at which time all
sealed bids will be publicly opened and read in the presence of one or more witnesses. The envelope(s)containing
the bids must be sealed, clearly marked on the outside of the envelope "2018 STREET
MAINTENANCE PROJECT (Project No. 318-018)" and addressed to the City Clerk at Riverside City
Hall.
The City reserves the right to award the contract by sections, to accept or reject any and all bids, to waive any
technicalities or irregularities therein, to determine in its sole discretion the lowest responsive and responsible
bidder,and to award the contract on such basis. Any bid may be withdrawn at the request of the bidder for return
of the bid packet submitted by filing a written request with the City Clerk prior to the above scheduled time for
the opening of bids or authorized postponement thereof.Any bid received after the time and date specified shall
not be considered. No bidder may withdraw a bid within 90 days after the actual date of the opening thereof
without forfeiture of the Bid Security.
2. There will not be a Pre-Bid Meeting.
3. Resection of all Bids. If the City rejects all Bids,the City may: (1)re-advertise or re-solicit Bids following
the City's normal bidding procedure;or(2)use an expedited Bid submission schedule when the City determines
that the delay would not be in the best interest of the project or the City.
BIDDER AGREES THAT REJECTION SHALL CREATE NO LIABILITY ON THE PART OF THE CITY
BECAUSE OF SUCH REJECTION, AND THE SUBMISSION OF ANY BID IN RESPONSE TO THIS
INVITATION SHALL CONSTITUTE AN AGREEMENT OF THE BIDDER TO THESE CONDITIONS.
4. Preparation and Submission of Bid. Each bid must be submitted on the prescribed form(s)and accompanied
by:
(1)Qualifications of Bidder(Experience Questionnaire)with Certificate of Good Standing
(2)Affidavit of Work Authorization with E-Verify attached(2 pages)
(3)Bid Bond
(4)Bid Foran
All blank spaces for bid prices must be filled in,in ink or typewritten,in both words and figures,and the foregoing
Certifications must be fully completed and executed when submitted. On alternate items for which a bid is not
submitted,a written indication of"no bid"on the bid form is required. No oral,electronic,facsimile or telephonic
bids or alterations will be considered.
A complete set of the bidding documents are on file for examination at the office of the City Engineer at Riverside
City Hall or on the City of Riverside's website hn://www.riversidemo.com/rfps. A copy the bidding documents
may be obtained from Riverside City Hall,Telephone 816-741-3993.
CONTRACTORS SHOULD READ AND BE FULLY FAMILIAR WITH ALL BIDDING AND CONTRACT
DOCUMENTS BEFORE SUBMITTING A BID. IN SUBMITTING A BID, THE BIDDER WARRANTS
6
THAT IT HAS READ THE BIDDING AND CONTRACT DOCUMENTS AND IS FULLY FAMILIAR
THEREWITH, THAT CONTRACTOR HAS VISITED THE SITE OF THE WORK TO FULLY INFORM
ITSELF AS TO ALL EXISTING CONDITIONS AND LIMITATIONS, AND CONTRACTOR HAS
INCLUDED IN THE BID A SUM TO COVER THE COST OF ALL ITEMS OF THE WORK.
The submission of a bid will constitute an incontrovertible representation by the bidder that the Bid Documents are
sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance of
the work.
Bids by a corporation must be executed in the corporate name by the president or a vice-president (or other
corporate officer accompanied by evidence of authority to sign)and the corporate seal must be affixed and attested
by the secretary or an assistant secretary. The corporate address shall be shown below the signature.
Bids by a partnership must be executed in the partnership name and signed by a partner,whose title must appear
under the signature and the official address of the partnership must be shown below the signature.
5. Addenda and Interpretations: No interpretation of the meaning to the specifications, or other pre-bid
documents will be made to any bidder orally.Every request for such interpretation should be in writing addressed
to:
City Engineer,City of Riverside: Travis Hoover;thoover@riversidemo.com or 816-372-9004
and to be given consideration must be received at least five(5)calendar days prior to the date fixed for the opening
of bids.
Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the
Bid Documents which, if issued, will be either hand delivered by a deliverer with receipt of delivery, or mailed
by the fastest delivery method available via registered mail or overnight delivery, and may also be mailed
electronically or faxed to all prospective bidders recorded as having received the Bid Documents, not later than
three (3) calendar days prior to the date fixed for the opening of bids. Failure of any bidder to receive any such
addendum or interpretation shall not relieve such bidder from any obligation under his bid as submitted. All
addenda so issued shall become part of the Contract Documents. Addenda may also be issued to modify the Bid
Documents as deemed advisable by the City. At the time of Bid submission,each Bidder shall verify that it has
considered all written addenda. No one is authorized to make any clarifications, interpretations or
modifications or give any instructions to the bidders during the bidding period except as described in this
Section.
6. Substitute Material and Equipment: The contract,if awarded,will be on the basis of material and equipment
described in the drawings or specified in the specifications without consideration of possible substitute of"or-
equal'items. Whenever it is indicated in the drawings or specified in the specifications that a substitute"or-equal'
item of material or equipment may be furnished or used by Contractor if acceptable to City, application for such
acceptance will not be considered by City until after the"effective date of the Agreement'.
7. Subcontracts:The bidder shall submit to the City with the Bid a list of all proposed sub-contractors to be used
on the project. The list shall indicate those portions of the work each sub-contractor will be performing. The
Contractor shall also submit a list of suppliers of major materials to be used on the project. The list shall indicate
which materials each supplier is furnishing.
The Bidder must be capable of demonstrating to the satisfaction of City that bidder has the capability at the time
of submission of the bid to manage or perform all of the Work required to be performed on the project by
Contractor under the Agreement.
8. Oualificatious of Bidder(Experience Questionnaire): The City may make such investigations as it deems
necessary to determine the ability of the bidder to perform the work, and the bidder shall furnish to the City all
such information and data for this purpose as the City may request.The City reserves the right to reject any bid if
the evidence submitted by, or investigation of, such bidder fails to satisfy the City that such bidder is properly
qualified to carry out the obligations of the contract and to complete the work contemplated therein. Conditional
bids will not be accepted. At a minimum,each Bidder must submit the following information with the Bid:
Authority to Do Business in Missouri. Each bid must contain evidence of bidder's qualification and
good standing to do business in the State of Missouri or covenant to obtain such qualification prior to
award of the contract.
Key Personnel. Identify the following Key Personnel proposed for the Project. (NOTE: Key Personnel
must be committed to the Project for its duration,and may not be removed or substituted without the
City's prior written consent.)
GC Project Manager
On-Site Field Superintendent
QC/QA Manager
Safety Officer
For each of the Key Personnel,provide the following background information:
• Years of employment with current employer;
• Other projects this person will be involved with concurrently with the project;
• Provide professional registrations, education, certifications and credentials held by the
person that are applicable to the Project.
Quality Assurance/Quality Control Plan. Provide a summary of Bidder's Quality Assurance/Quality
Control Plan for this project
• Describe key issues that might affect the Project schedule and how Bidder proposes to address
them
• Provide a statement regarding all work performed two(2)years immediately preceding the date
of the Bid that contains either(a)any written notices of violations of any federal or state prevailing
wage statute in which prevailing wage penalties were assessed against the Bidder or paid by the
Bidder; or (b) a statement that there have been no such written notices of violations or such
penalties assessed
Statement of Assurances. Provide affirmation of the following items:
• Statement that Bidder is current on payment of Federal and State income tax withholdings and
unemployment insurance payments
• Statement that the Bidder has not been rescinded or debarred from any bidding, contractual,
procurement or other such programs by federal state or local entities.
• Statement of Bidder's litigation and/or arbitration history over the past seven(7)years including
final ruling. Pending cases must be disclosed with a notation that the matter is still unresolved.
• Statement of Bidder's bond history over the past seven (7) years including any incidences of
failure to perform.
• Provide sworn affidavits as outlined in the Information to Bidders' concerning Bidder's
participation in the federal work authorization program.
8
• Statement that there is no collusion or fraud with reference to illegal relationships of bidders and
representatives of the City,bid pooling or strawbids
9. Bid Security: Each bid must be accompanied by a bid bond payable to the City for five percent(5%)of the
total amount of the bid. A certified check made payable to"The Treasurer of the City of Riverside"may be used
in lieu of a bid bond. Attorneys-in-fact who sign bid bonds must file with each bond a certified and effectively
dated copy of their power of attorney.
As soon as the bid prices have been compared, the City will return the bonds of all except the three (3) lowest
responsible bidders. The bid bond of the remaining bidders will be retained by the City until the earlier of(a)the
91"day after the bid opening, or(b) execution and delivery of the Agreement together with all bonds, evidence
of insurance, work authorization affidavit and other documents required under the Agreement by the bidder to
whom Notice of Award is given. The Bid Security shall be forfeited to the City if the bidder to whom an award
is made fails to enter into the required contract or fails to deliver the required performance or payment bonds.
10. Liquidated Damages for Failure to Enter into Aereement: If the Bidder fails or refuses to execute the
Agreement and deliver such additional documentation within ten(10)days of Notice of Award,any Bid Security
shall immediately become due and payable and forfeited to the City as liquidated damages. Bidders agree that
this is a fair and reasonable approximation of the actual damages incurred by the City for the Bidder's failure to
honor its bid and that the liquidated damages in this Section are not penal in nature but rather the parties' attempt
to fairly quantify the actual damages incurred by the City for the Bidder's refusal to honor its bid.
11. Time of Completion and Liauidated Damages: Bidder must agree to commence work on or before a date
to be specified in a written"Notice to Proceed"of the City and to fully complete the project by 6/30/2018.Bidder
must agree also to pay as liquidated damages, the sum of $500 for each consecutive calendar day thereafter as
hereinafter provided in the Agreement and Contract Documents. No time extensions will be granted, except in
case of unusual(unseasonable)weather conditions or additional work requested by the City. Bidder agrees that
the sum of$500 per day is a fair and reasonable approximation of the actual damages incurred by the City
for the Bidder's failure to complete the project within the time outlined above and that such liquidated
damages in this Section are not penal in nature but rather the parties'attempt to fairly quantify the actual
damages incurred by the City for such delays.
12. Conditions of Work:Each bidder must inform himself fully of the conditions relating to the construction of
the project and the employment of labor thereon. Failure to do so will not relieve a successful bidder of its
obligation to furnish all material and labor necessary to carry out the provisions of the contract.Insofar as possible
the Contractor, in carrying out the work,must employ such methods or means as will not cause any interruption
of or interference with the work of any other contractor.
13. Laws and Regulations: The bidder's attention is directed to the fact that all applicable State laws,municipal
ordinances,and the rules and regulations of all authorities having jurisdiction over construction of the project shall
apply to the contract throughout,and they will be deemed to be included in the contract the same as though herein
written out in full.
14. Method of Award-Lowest Responsible Bidder: If at the time this contract is to be awarded,the lowest bid
submitted by a responsible bidder does not exceed the amount of funds then estimated by the City as available to
finance the contract; the contract will be awarded to the "lowest responsible bidder". If such bid exceeds such
amount,the City may reject all bids or may award the contract on such items as identified by and deemed in the
best interest of the City, in its sole discretion, as produces a net amount which is within the available funds.
Discrepancies between words and figures will be resolved in favor of words. Discrepancies between the indicated
sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
9
If this solicitation includes Bid Alternates, the City, in its sole discretion, may include any, all or none of the
Alternates in determining the lowest responsible Bid. The City may include the Alternates in any combination
and in any order or priority as deemed in the best interest of the City. The City may make this determination at
any time after bid closing and prior to contract award. The City will act in the best interest of the City in
determining whether to include any, all or none of the Alternates and the combination and priority of any
Alternates selected. If additional funding becomes available after Contract award,the City may add any or all of
the Alternates to the Agreement by Change Order.
The City may consider the qualifications and experience of subcontractors and other persons and organizations
(including those who are to fumish the principal items of material or equipment) proposed for portions of the
work. Operating costs,maintenance considerations,performance data and guarantees of materials and equipment
may also be considered by the City.
The City reserves the right to reject any and all bids,to waive any and all informalities,and the right to disregard
all nonconforming, non-responsive or conditional bids. In evaluating bids, the City shall consider the
qualifications of the bidders,whether or not the bids comply with the prescribed requirements,and alternates and
unit prices if requested in the Bid.
The City may conduct such investigations as it deems necessary to assist in the evaluation of any bid and to
establish the responsibility, qualifications and financial ability of the bidders, proposed subcontractors and other
persons and organizations to do the work in accordance with the Contract Documents to the City's satisfaction
within the prescribed time.
The City reserves the right to reject the bid of any bidder who does not pass any such evaluation to the City's
satisfaction.
If the contract is to be awarded,it will be awarded to the lowest responsible bidder whose evaluation,in the sole
determination by the City,indicates to the City that the award will be in the best interests of the project.
15. Obligation of Bidder:At the time of the opening of bids,each bidder will be presumed to have inspected the
site and to have read and to be thoroughly familiar with the Contract Documents (including all addenda). The
failure or omission of any bidder to examine any form,instrument,or document shall in no way relieve any bidder
from any obligation in respect to the bid submitted. On request,City will provide each Bidder access to the site
to conduct such investigations and tests as each Bidder deems necessary for submission of his bid.
REJECTION OF BID SHALL CREATE NO LIABILITY ON THE PART OF THE CITY OF RIVERSIDE,MISSOURI
BECAUSE OF SUCH REJECTION,AND THE FILING OF ANY BID IN RESPONSE TO THIS INVITATION SHALL
CONSTITUTE AN AGREEMENT OF THE BIDDER TO THIS CONDITION.
16. Federal Work Authorization Program Participation: Bidders are informed that pursuant to Section
285.530, RSMo, as a condition of the award of any contract in excess of five thousand dollars ($5,000), the
successful bidder shall,by sworn affidavit and provision of documentation,affirm its enrollment and participation
in a federal work authorization program with respect to the employees working in connection to the contracted
services.The affidavit shall further provide that the successful bidder does not knowingly employ any person who
is an unauthorized alien in connection to the contracted services.
17. Proof of Lawful Presence: RSMo 208.009 requires that contractors provide affirmative proof that the
Contractor is a citizen or permanent resident of the United States or is lawfully present in the United States.
Affirmative proof can be established through a Valid Driver's License; US Birth Certificate (certified with an
embossed,stamped or raised seal issued by a state or local government—hospital certificates are not acceptable);
US Passport (valid or expired); US Certificate of Citizenship, Naturalization or Birth Abroad; US Military
10
Identification Card or Discharge Papers accompanied by a copy of US Birth Certificate issued by a state or local
government.
18. Safety Standards and Accident Prevention: With respect to all work performed under this contract, the
Contractor shall:
a. Comply with the safety standards provisions of applicable laws, building and construction codes, and
the"Manual of Accident Prevention in Construction"published by the Associated General Contractors of
America,the requirements of the Occupational Safety and Health Act of 1970(Public Law 91-596),and
the requirements of Section 292.675,RSMo
b. Exercise every precaution at all times for the prevention of accidents and the protection of persons
(including employees)and property.
c.Maintain at Contractor's office or other well known place at the job site,all articles necessary for giving
first aid to the injured,and shall make arrangements for the immediate removal to a hospital or a doctor's
care of persons(including employees),who may be injured on the job site.
d. Bidders are informed that the Project is subject to the requirements of Section 292.675,RSMo, which
requires all contractors or subcontractors doing work on the Project to provide, and require its on-site
employees to complete, a ten (10) hour course in construction safety and health approved by the
Occupational Safety and Health Administration("OSHA")or a similar program approved by the Missouri
Department of Labor and Industrial Relations which is at least as stringent as an approved OSHA program.
The training must be completed within sixty(60)days of the date of work on the Project commences.On-
site employees found on the worksite without documentation of the required training shall have twenty
(20)days to produce such documentation.
19. Prevailing Wage: Wage rates for the project shall be not less than the prevailing wage rates for Platte County
currently in effect as determined by the Division of Labor Standards of the State of Missouri,pursuant to RSMo
290.210 et seq. The Contractor will forfeit a penalty to the City of$100 per day, or portion thereof, for each
worker that is paid less than the prevailing rate for any work done under the contract by the Contractor or any
Subcontractor.
20. Reserved
21. American Products: Pursuant to RSMo 34.353, any manufactured good or commodities used or supplied
in the performance of the contract(or subcontract)shall be manufactured or produced in the United States,unless
determined to be exempt as provided in state law.
22. Transient Emplovers: Pursuant to RSMo 285.230, every transient employer(employer not domiciled in
Missouri) must post in a prominent and easily accessible place at the work site a clearly legible copy of the
following: 1) Notice of registration for employer withholding issued by the Missouri Director of Revenue, 2)
Proof of coverage for workers' compensation insurance or self-insurance verified by the Missouri Department of
Revenue through the records of the Division of Workers Compensation; and 3) Notice of registration for
unemployment insurance issued to such employer by the Division of Employment Security. Contractor shall be
liable for a penalty of$500.00 per day until such notices required by RSMo 285.230 et seq.are posted.
23. Current City Business License: The successful bidder, and all subcontractors, shall obtain a current city
business license prior to beginning construction.
24. Sales Tax Exemption Certificate: The City will supply the Contractor with a Project Exemption Certificate
for use in purchasing materials and supplies used on the project. The Contractor shall, in preparing its bid,omit
11
from its computed costs all sales and use taxes related to the purchase of materials or other tangible personal
property incorporated into or consumed in the construction of the Project.
25. Non Discrimination and Eaual Oonortunity: Contractor shall ensure that all employees are treated equally
without regard to their race, color, religion, sex, age, handicap or national origin. The City hereby notifies all
bidders that it will affirmatively insure that in any contract entered into pursuant to this bid, socially and
economically disadvantaged business enterprises will be afforded full opportunity to submit bids in response to
this invitation and will not be discriminated against on the grounds of race,color, religion, sex, age, ancestry or
national origin in consideration for an award. The City of Riverside is an equal opportunity employer and
encourages minority,women and disadvantaged contractors to submit bids.
26. Security for Payment and Faithful Performance: Simultaneously with delivery of the executed contract,
the Contractor shall furnish a surety bond or bonds as security for faithful performance of this contract and for the
payment of all persons performing labor on the project under this contract and furnishing materials in connection
with this contract. The Bond furnished by bidder shall contain the requirements and conditions set forth in and
shall comply in all respects with Section 107.170 RSMo and other applicable legal requirements. The surety on
such bond or bonds shall be a duly authorized surety company satisfactory to the City and shall have a rating of
at least f°A-"from Best's in an amount equal to one hundred percent(100%)of the contract price that does not
include the cost of operation,maintenance and money. Attorneys-in-fact who sign contract bonds must file with
each bond a certified and effectively dated copy of their power of attorney.
27. Shmiag of Agreement: When City gives a Notice of Award to the successful bidder, it will be accompanied
by the required number of unsigned counterparts of the Agreement and all other Contract Documents. Within ten
(10)days thereafter Contractor shall sign and deliver at least three(3)counterparts of the Agreement to City with all
other Contract Documents attached and signed as required,together with the required bonds,evidence of insurance,
city licenses and work authorization affidavit and documentation. Within ten(10)days thereafter City will deliver
all fully signed counterparts to Contractor. The City may issue a Notice to Proceed with or at any time after delivery
of signed counterparts to Contractor.
12