HomeMy WebLinkAbout2006-058 - Construction Contract with Havens Construction Company for Storm Sewer Repair Project.•
BILL N0.2006-58 ORDINANCE N0.2006-58
AN ORDINANCE APPROVING AND AUTHORIZING THE EXECUTION OF A
CONSTRUCTION CONTRACT WITH HAVENS CONSTRUCTION COMPANY,
INC. FOR STORM SEWER REPAIR PROJECT AT 5014 NW MERRIMAC IN
THE CITY OF RIVERSIDE, MISSOURI
WHEREAS, the City of Riverside, Missouri ("City") desires to engage the
services of a contractor to perform construction services in connection with the Storm
Sewer Repair Project located at 5014 NW Merrimac and;
WHEREAS, the City requested multiple bids for the Storm Sewer Repair Project
and;
WHEREAS, Havens Construction Company, Inc. has provided the City with a
contract detailing the costs and services approved by the City.
NOW, THEREFORE, be it ordained by the Board of Aldermen of the City of
Riverside, Missouri as follows:
Section 1. The City of Riverside shall employ Havens Construction Company, Inc. to
perform the construction services, and shall pay to Havens Construction Company, Inc.
an amount not to exceed Six-Thousand Four Hundred Dollars and No/100 Cents
($6,400.00) for such construction services which are described in the bid form attached
hereto as Exhibit A ("Agreement for Construction").
Section 2. The contract, in substantially the form attached hereto as Exhibit A, and
payment by the City for-the construction services described therein, is approved, and the
Mayor is authorized to take such actions reasonably necessary to carry out the intent of
this Ordinance on behalf of the City.
Section 3. This Ordinance shall be in full force and effect from and after its passage
and approval.
Passed this 2°a day of May 2006.
A .TE
Cit Jerk
Mayor
~:
~: ,~H A
OWNER/CONTRACTOR
AGREEMENT FOR CONSTRUCTION
4..:
AGREEMENT
made this Twenty Fourth day of April in the year Two Thousand Six.
BETWEEN City of Riverside, Missouri
2950 NW Vivion Road
Riverside, MO 64150 the OWNER
and Havens Construction Company, Inc.
9400 Liberty Drive
Liberty, MO 64068 the CONTRACTOR
for Storm Sewer Repair
5014 Merrimac
Riverside, MO 64150 the PROJECT
Engineered By Shafer, Kline & Warren, Inc.
2005 Swift
North Kansas City, MO 64116 the ENGINEER
Latest Dwg Date None
The Owner and the Contractor agree as set forth below.
CONTRACT DOCUMENTS
The contract documents consist of this agreement, the conditions of the contract
(general, special and other conditions), the drawings, the specifications, all
addenda issued prior to and all modifications issued after execution of this
agreement. These form the contract and are as fully a part of the contract as if
attached to this agreement or repeated herein.
WORK
Havens Construction Company, Inc. shall perform all the work required by this
agreement as follows:
816.781-0769
Fax:816-792-1277
9400 Liberty Drive
Liberty, MO 64068
www.havensco.com
i q ,.
~;
+ :r
City of Riverside, MO
Storm Sewer Repair
5014 Merrimac
April 24, 2006
Page No. 2
Storm Sewer Structure Replacement
1. Remove Existing 4' 0 Grate Inlet
2. Install new 4' x 4' Field Inlet (Open on all 4 sides)
3. Slope Grades to Drain to the Field Inlet (Up to Approximately 8'-0", in all
Directions, from the Structure)
4. Haul-off Removed Grate Inlet
Total Estimated Amount $6,400.00
Adjustments to the contract amount for extra work or deductions will be
determined by one or more of the following methods:
A) By a lump sum price
B) By unit prices named in the bid or as otherwise agreed
C) By Contractors cost plus ~a fixed fee
D) By Contractor's cost plus a percentage
SPECIAL CONDITIONS
.Adequate access to the site will be provided by others.
All dirt is estimated to remain on site. Any soil left will be in a pile or laid over
existing grades (no compaction). Haul off and/or haul in are excluded.
An insurance certificate will be furnished by Havens.
All bonds-and permits are excluded.
If any existing utilities are encountered which are in conflict with Havens' work
and either these services or the existing utilities must be relocated, this will be
considered changed work and an equitable adjustment will be made to the
contract.
Seeding, sodding and construction staking are to be done by others.
This price is based on preliminary plans. Any changes in the final plans are to
be renegotiated.
,, w
., ,• ~.
City of Riverside, MO
Storm Sewer Repair
5014 Merrimac
Apri124,2006
Page No. 3
This proposal is based on the use of hoe ramming to aid in the excavation of
shale, sandstone, or rock. The cost associated with the use of hoe ramming wilt
be an extra cost, which will be billed to the owner on the following basis:
1. In the event shale, sandstone.or rock is encountered while digging and
hoe ramming is utilized, there will be an additional charge of $95.00 per
cubic yard for every cubic yard excavated.
Engineered drawings and as-builts are to be done by others.
Rock backfill and/orflowable fill for trenches is NOT included in our bid.
Our proposal is subject to acceptance within thirty (30) days.
PAYMENT
Payment is to be 100% of the monthly estimate, due within 30 days of the date
of the invoice.
Final payment, constituting the entire unpaid balance of the contract .sum, shall
be paid by the owner to the contractor when the work has been completed.
Respectfully submitted,
H VENS CONSTRUCT OMPANY, INC.
James R. Burton
Project Manager
JRB:skh
ACCEPTANCE:
Signed By:
Print Name:
Title:
Date: