HomeMy WebLinkAbout1695 CO1 Beemer Construction Co. Contract for the 2019 Mattox & 39th Water Main Extension BILL NO. 2019-058 ORDINANCE NO. 9.5�
AN ORDINANCE AUTHORIZING AND APPROVING CHANGE ORDER NO. 1 TO THE
BEEMER CONSTRUCTION CO., INC. CONTRACT FOR THE 2019 MATTOX & 39TH WATER
MAIN EXTENSION (PROJECT 618-227) ORIGINALLY AUTHORIZED BY ORDINANCE NO.
1674.
WHEREAS, the City previously determined the need for certain infrastructure work
necessary to accommodate the doorLink Manufacturing, Inc. ("doorLink") industrial
warehousing and distribution facility, as well as other future projects, to be located
adjacent to the doorLink site; and
WHEREAS, the 2019 Mattox and 39th Water Main Extension fulfills a public
purpose and will further the growth of the City, facilitate the development of the entire
Horizons site, improve the environment of the City, foster increased economic activity
within the City, increase employment opportunities within the City, and otherwise be in
the best interests of the City by furthering the health, safety and welfare of its residents
and taxpayers; and
WHEREAS, the City previously approved the 2019 Mattox and 39th Water Main
Extension specifications through the passage and approval of Ordinance No. 1663
("Project No. 618-227"); and
WHEREAS, the City and Beemer Construction Co., Inc. ("Beemer"), entered into
a contract authorized by and through Ordinance 1674, for the installation and construction
of Project No. 618-227 (the "Project Agreement") which is beneficial for other City
purposes in exchange for the City paying Beemer no more than Two Hundred .Sixty-Five
Thousand Eighty-Seven Dollars and No Cents ($265,087.00); and
WHEREAS, the staff recommends approval of Change Order No. 1, as described
in the Change Order No. 1 Memo attached hereto as Exhibit A and incorporated herein,
which increases the authorized expenditure by an additional Twenty-Four Thousand
Seven Hundred Eighty and 46/100 Dollars ($24,780.46), for a total amount to be paid
pursuant to the Project Agreement not to exceed Two Hundred Eighty-Nine Thousand
Eight Hundred Sixty-Seven and 46/100 Dollars ($289,867.46), for Beemer to directional
drill the water line under the drive approaches along the west side of Mattox Road, which
allows for no disruption of the business as well as a simpler method of dealing with the
additional costs of the high groundwater table in Horizons; and
WHEREAS, the City has determined that authorization for the aforesaid additional
expenditure pursuant to the Project Agreement with Beemer fulfills a public purpose and
will further the growth of the City, facilitate the development of the entire Horizons site,
improve the environment of the City, foster increased economic activity within the City,
increase employment opportunities within the City, enable the City to direct the
development of the entire Horizons site, and otherwise be in the best interests of the City
by furthering the health, safety, and welfare of its residents and taxpayers.
WA 13870141.1
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF ALDERMEN OF THE
CITY OF RIVERSIDE, MISSOURI, AS FOLLOWS:
SECTION 1 — BEST INTEREST OF THE CITY TO APPROVE CHANGE ORDER
NO. 1. The Board of Aldermen finds that it is in the best interest of the City to approve
Change Order No. 1, attached hereto as Exhibit A and incorporated herein, and that
such approval fulfills a public purpose and will further the growth of the City, facilitate the
development of the entire Horizons site, improve the environment of the City, foster
increased economic activity within the City, increase employment opportunities within the
City, and otherwise is in the best interests of the City, by furthering the health, safety, and
welfare of its residents and taxpayers, and the Board of Aldermen does hereby approve
Change Order No. 1 to increase the authorized expenditure to Beemer by an additional
Twenty-Four Thousand Seven Hundred Eighty and 46/100 Dollars ($24,780.46), for a
total amount to be paid pursuant to the Project Agreement not to exceed Two Hundred
Eighty-Nine Thousand Eight Hundred Sixty-Seven and 46/100 Dollars ($289,867.46).
SECTION 2 — AUTHORITY GRANTED. The City hereby authorizes the City
Administrator and the City Engineer to execute and deliver Change Order No. 1,
consistent with the terms of this Ordinance and Missouri law, and hereby authorizes the
Mayor, the City Administrator, Special Counsel to the City and other appropriate City
officials to take any and all actions as may be deemed necessary or convenient to carry
out and comply with the intent of this Ordinance and to execute and deliver for, and on
behalf of, the City all certificates, instruments, agreements and other documents, as may
be necessary or convenient to perform all matters herein authorized. Further, the City
Administrator is hereby authorized to expend an additional Twenty-Four Thousand Seven
Hundred Eighty and 46/100 Dollars ($24,780.46), for a total amount paid pursuant to the
Project Agreement authorized by and through Ordinance No. 1674, not to exceed Two
Hundred Eighty-Nine Thousand Eight Hundred Sixty-Seven and 46/100 Dollars
($289,867.46).
SECTION 3 — EFFECTIVE DATE. This Ordinance shall be in full force and effect
from and after its passage and approval.
[Remainder of Page Intentionally Blank]
2
WA 13870141.1
BE IT REMEMBERED that the above was read two times by heading only,
PASSED AND APPROVED by a majority of the Board of Aldermen and APPROVED by
the Mayor of the City of Riverside, Missouri, this 19th day of November, 2019.
Kathleen L. Rose, Mayor
ATTEST: ! i
Robin Kincaid, City Clerk
Approved as to form:
Ter e LLP
sel to the City
ar
3
WA 13870141.1
EXHIBIT A
CHANGE ORDER NO. 1 WITH COVER MEMO
4
WA 13870141.1
CITY OF
RI\/E RS
MISSOURI
Upstream from ordinary.
2950 NW Vivion Road
Riverside, Missouri 64150
MEMO DATE: October 29, 2019
AGENDA DATE: November 19, 2019
TO: Mayor and Board of Aldermen
FROM: Travis Hoover
RE: Change Order I: BEEMER CONSTRUCTION CO., INC.
2019 Mattox & 39`h Water Main Extension (618-227)
BACKGROUND: This change order for an additional $24,780.46 allows Beemer to directional drill
the water line under the drive approaches along the west side of Mattox Rd.
The assumed method of installing the waterline was to remove and replace the
approaches to Riverside Logistics Centre. The directional drill allows for no
disruption of the business as well as a simpler method of dealing with the
additional costs of the high groundwater table in Horizons.
BUDGETARY IMPACT: $24,780.46 would be authorized for budget year 2019-2020.
Original Contract Amount $ 265,087.00
Total of Previous Changes $ 0.00
Total this Change Order $ 24,780.46
Current Contract Total $ 289,867.46
RECOMMENDATION: Staff recommends approval of the ordinance and acceptance of the change order
with Beemer Construction Co., Inc.
CITY OF CHANGE ORDER NO. 1 Date Prepared: 10/29/2019
"-�RIVERS
Contractor Name: Beemer Construction Co., Inc.
Project Name: 2019 Mattox&39th Water Main Extension Page Number: 1 of 1
Project Number: 618-227 #of Pgs Attached:
Contract Date: 08/06/2019 The following changes to the original contract amount were required to cover cost incurred by the
Project Location: Riverside,Missouri Contractor or to reflect savings realized by the Contractor as a result of a change in the actual
constructed quantities from the estimated quantities shown on the Bid Proposal.
REQUIRED CHANGES IN PRESENT CONTRACT
Contract or Contract or Contract or New or New or New or
Item Description 8 Reason for Change Order(Please describe item below and then follow with reason for
Line Item No. Previous Previous Previous Unit Adjusted Adjusted Adjusted
Quantity Unit Price Amount Change Order) 1) Requested by City 2)Unknown Site Conditions 3)Not incorporated in plans/specs
Y Quantity Unit Price Amount
n/a 0.0 $0.00 $0.00 1 Directional Drill of the water line for drive approaches along the west side of Mattox Rd. 1.00 $24,780.46 $24,780.46
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 1 1 $0.00
$0.00 1 1 $0.00
Previous Total $0.00 $0.00
Adjusted Total $24,780.46
Net Change $24,780.46
Statement of Contract
Original Contract Amount $265,087.00
Net Amount of Previous Additions and Deductions $0.00
Net Contract Amount Prior to This Request $265,087.00
Amount of This Request $24,780.46
New Contract Amount $289,867.46
Percent Change in Contract Amount 9.35%
DESIGN ENGINEER: CITY OF RIVERSIDE,MISSOURI:
Company: City Engineer: _
Name Printed: Travis Hoover Signed Date
Signed: City Administrator: _ __
Date: Brian Koral Signed Date
CONTRACTOR: ON-SITE PROJECT MANAGER:
CONTRACTOR'S Certification for Chanqe Order: ON-SITE PROJECT MANAGER Certification for Change Order:
The undersigned CONTRACTOR certifies that all changes In accordance with the Contract Documents,the on-site observations,and
described above are necessary in order for the CONTRACTOR to the data comprising this change order,the on-site project manager certifies
proceed with execution of the contract documents,and that the to the Owner that to the best of the on-site project manager's knowledge,
values stated above are correct with respect to the work information and belief the above referenced changes are necessary in order to
anticipated under this change order. proceed with the execution of the contract documents,and that the values
stated above are correct with respect to the work anticipated under this change order.
Company: Company:
Name Printed: _ _ _ Name Printed:
Signed: Signed:
Date: Dale: