HomeMy WebLinkAbout1701 Approving Change Order 2 to Beemer Construction Co. Contract for 2019 Mattox and 39th Water Main ExtensionBILL NO. 2019-064 ORDINANCE NO. 1701
AN ORDINANCE AUTHORIZING AND APPROVING CHANGE ORDER NO. 2 TO THE
BEEMER CONSTRUCTION CO., INC. CONTRACT FOR THE 2019 MATTOX & 39TH WATER
MAIN EXTENSION (PROJECT 618-227) ORIGINALLY AUTHORIZED BY ORDINANCE NO. 1674.
WHEREAS, the City previously determined the need for certain infrastructure work
necessary to accommodate the doorLink Manufacturing, Inc. ("doorLink") industrial
warehousing and distribution facility, as well as other future projects, to be located
adjacent to the doorLink site; and
WHEREAS, the 2019 Mattox and 39th Water Main Extension fulfills a public
purpose and will further the growth of the City, facilitate the development of the entire
Horizons site, improve the environment of the City, foster increased economic activity
within the City, increase employment opportunities within the City, and otherwise be in
the best interests of the City by furthering the health, safety and welfare of its residents
and taxpayers; and
WHEREAS, the City previously approved the 2019 Mattox and 39t" Water Main
Extension specifications through the passage and approval of Ordinance No. 1663
("Project No. 618-227"); and
WHEREAS, the City and Beemer Construction Co., Inc. ("Beemer"), entered into
a contract authorized by and through Ordinance 1674, for the installation and construction
of Project No. 618-227 (the "Project Agreement") which is beneficial for other City
purposes in exchange for the City paying Beemer no more than Two Hundred Sixty -Five
Thousand Eighty -Seven Dollars and No Cents ($265,087.00); and
WHEREAS, the Board has previously approved Change Order No. 1 to the
Beemer Project Agreement totaling an additional cost of Twenty -Four Thousand Seven
Hundred Eighty and 46/100 Dollars ($24,780.46); and
WHEREAS, the staff recommends approval of Change Order No. 2, as described
in the Change Order No. 2 Memo attached hereto as Exhibit A and incorporated herein,
which increases the authorized expenditure by an additional Thirty -Eight Thousand Thirty
Three and 48/100 Dollars ($38,033.48), for a total amount to be paid pursuant to the
Project Agreement not to exceed Three Hundred Twenty -Seven Thousand Nine Hundred
and 94/100 Dollars ($327,900.94), for Beemer to install the water line along the north side
of 39th Street. The water line was originally to be installed on the south side of 39t" Street.
This change is required due to the -high groundwater table from the flood of 2019; and
WHEREAS, the City has determined that authorization for the aforesaid additional
expenditure pursuant to the Project Agreement with Beemer fulfills a public purpose and
will further the growth of the City, facilitate the development of the entire Horizons site,
improve the environment of the City, foster increased economic activity within the City,
increase employment opportunities within the City, enable the City to direct the
WA 14012832.2
development of the entire Horizons site, and otherwise be in the best interests of the City
by furthering the health, safety, and welfare of its residents and taxpayers.
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF ALDERMEN OF THE
CITY OF RIVERSIDE, MISSOURI, AS FOLLOWS:
SECTION 1 — BEST INTEREST OF THE CITY TO APPROVE CHANGE ORDER
NO. 1. The Board of Aldermen finds that it is in the best interest of the City to approve
Change Order No. 2, attached hereto as Exhibit A and incorporated herein, and that
such approval fulfills a public purpose and will further the growth of the City, facilitate the
development of the entire Horizons site, improve the environment of the City, foster
increased economic activity within the City, increase employment opportunities within the
City, and otherwise is in the best interests of the City, by furthering the health, safety, and
welfare of its residents and taxpayers, and the Board of Aldermen does hereby approve
Change Order No. 2 to increase the authorized expenditure to Beemer by an additional
Thirty -Eight Thousand Thirty Three and 48/100 Dollars ($38,033.48), for a total amount
to be paid pursuant to the Project Agreement not to exceed Three Hundred Twenty -Seven
Thousand Nine Hundred and 94/100 Dollars ($327,900.94).
SECTION 2 — AUTHORITY GRANTED. The City hereby authorizes the City
Administrator and the City Engineer to execute and deliver Change Order No. 2,
consistent with the terms of this Ordinance and Missouri law, and hereby authorizes the
Mayor, the City Administrator, Special Counsel to the City and other appropriate City
officials to take any and all actions as may be deemed necessary or convenient to carry
out and comply with the intent of this Ordinance and to execute and deliver for, and on
behalf of, the City all certificates, instruments, agreements and other documents, as may
be necessary or convenient to perform all matters herein authorized. Further, the City
Administrator is hereby authorized to expend an additional Thirty -Eight Thousand Thirty
Three and 48/100 Dollars ($38,033.48), for a total amount paid pursuant to the Project
Agreement authorized by and through Ordinance No. 1674, not to exceed Three Hundred
Twenty -Seven Thousand Nine Hundred and 94/100 Dollars ($327,900.94).
SECTION 3 — EFFECTIVE DATE. This Ordinance shall be in full force and effect
from and after its passage and approval.
[Remainder of Page Intentionally Blank]
2
WA 14012832.2
BE IT REMEMBERED that the above was read two times by heading only,
PASSED AND APPROVED by a majority of the Board of Aldermen and APPROVED by
the Mayor of the City of Riverside, Missouri, this 17th day of December 2019.
/s/ Kathleen L. Rose
Kathleen L. Rose Mayor
ATTEST:
/s/ Robin Kincaid
Robin Kincaid, City Clerk
Approved as to form:
Spencer Fane LLP
Special Counsel to the City
by Joe Bednar
3
WA 14012832.2
EXHIBIT A
CHANGE ORDER NO. 2 WITH COVER MEMO
4
WA 14012832.2
CITY OF
RIVERSIDE
MISSOURI
CHANGE ORDER NO. 2
Contractor Name: Beemer Construction Co., Inc.
Project Name: 2019 Mattox & 39th Water Main Extension
Protect Number: 618-227
Contract Date: 8/6/2019
Project Location: Riverside, Missouri
The following changes to the original contract amount were required to cover cost incurred by
the Contractor or to reflect savings realized by the Contractor as a result of a change in the
actual constructed quantities from the estimated quantities shown on the Bid Proposal.
REQUIRED CHANGES IN PRESENT CONTRACT
Date Prepared: 12/9/2019
Page Number: 1 of 6
# of Pgs Attached: 5
Line Item No.
Contract or
Previous
QuantityUnit
Contract or
Previous
Price
Contract or
Previous
Amount
Unit
Item Description & Reason for Change Order (Please describe item below and then follow with reason for
Change Order) 1) Requested by City 2) Unknown Site Condtions 3) Not incorporated in plans/specs
New or
Adjusted
Quantity
New or
Adjusted
Unit Price
New or
Adjusted
Amount
n/a
0.0
$0.00
$0.00
1
Details listed in November 5 letter- see attached
1.00
$9,920.42
$9,920.42
n/a
0.0
$0.00
$0.00
1
Details listed in October 16 letter - see attached
1.00
$28,113.06
$28,113.06
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
DESIGN ENGINEER:
Company:
Name Printed:
Signed:
Date:
Previous Total $0.00
Statement of Contract
Original Contract Amount
Net Amount of Previous Additions and Deductions
Net Contract Amount Prior to This Request
Amount of This Request
New Contract Amount
Percent Change in Contract Amount
CONTRACTOR:
CONTRACTOR'S Certification for Change Order:
The undersigned CONTRACTOR certifies that all changes
described above are necessary in order for the CONTRACTOR to
proceed with execution of the contract documents, and that the
values stated above are correct with respect to the work
anticipated under this change order.
Company: L— iiY.r_ +K y r_ZIt' ✓ •, '
Name Printed:, —
Signed:
Date: .._.-..t.4 tizt• ,
CITY OF RIVERSIDE, MISSOURI:
City Engineer:
Travis Hoover
City Administrator::
Brian Korall
ON -SITE PROJECT MANAGER:
$265,087.00
$24,780.46
$289,867.46
$38,033.48
$327,900.94
13.12%
ON -SITE PROJECT MANAGER Certification for Change Order:
In accordance with the Contract Documents, the on -site observations, and
the data comprising this change order, the on -site project manager certifies
to the Owner that to the best of the on -site project manager's knowledge,
information and belief the above referenced changes are necessary in order to
proceed with the execution of the contract documents, and that the values
stated above are correct with respect to the work anticipated under this change order
Company:
Name Printed:
Signed:
Date:
Adjusted Total $38,033.48
Net Change $38,033.48
AP1I ° AP9
D E.C l' _22U19
Cityr"ridministratO,r
€€, m 0:0.,tedAaettivt
Utility Contractor
606 S.E. Central Drive
Blue Springs, MO 64014-3311
(816) 229-2266 Fax (816) 229.2571
November 5, 2019
To: City of Riverside
Attn: Mr. Travis Hoover
From: Chad Sipes
Re: 39th & Mattox Rd. Water Main Extension
Riverside, MO
Mr. Hoover,
The following are the additional items associated with the water main that Missouri American request we provide and install at the
south end. During the excavation of the proposed water main, the soil conditions became very soft which created concern the water
main would separate, therefore Missouri American asked that we install an oversized straddle block with reinforcement at the end of
the line. Missouri American also asked we provide and install permanent blow off assemblies at the ends of the line.
Materials
Blow off assemblies (see attached quote) $3,494.28
Rebar (see attached quote) $142.16
Concrete (see attached quote) $1,295.25
Labor
4 man crew (straddle block) .75 days @ $3,426.81 per day $2,570.11
4 man crew (blow off assemblies) .5 days @ $3,426.81 per day $1,713.41
Equipment
PC228 Excavator/WA 150 Loader/ Pickup .75 days @ $642.94 per day $482.21
PC228 Excavator/Pickup .5 days @ S446.00 per day $223.00
Total $9.920.42
*The additional time of 1.5 days impact the substantial completion contract time.
Member of Heavy Constructors Association
°An Equal opportunity Employer"
FORTILINE WATERWORKS
a MORSCO brand
QUOTE
"*Pricing for some of the.products included in this quote may -be impacted by,
:Section 301 List 3: the proposed China tariff. In the event that the tariff is
implemented, we will be forced to pass it on to the market. The actual price
Hof these items may increase up to the rate of the tariff that is imposed.**
CUSTOMER NO 207187
QUOTING BRANCH FORTILINE KANSAS CITY
QUOTE NO 5900275
QUOTE DATE 10/16/19
PAGE 1
CUSTOMER
BEEMER CONSTRUCTION CO
606 SE CENTRAL DRIVE
BLUE SPRINGS, MO 64014
PROJECT INFORMATION
MADDOX RD - BLOW -OFF ASSEMBLIES
LINE | QTY | UOM | DESCRIPTION | UNIT PRICE | TOTAL PRICE
10 4 EA 12" MEGALUG MJ REST DIP 1112 76.2500 305.00
20 2 EA 12"X2" MJ TAPT CAP C153 128.6600 257.32
30 16 EA 3/4" X4" T-HEAD B&N BLUE 2.9500 47.20
40 2 EA 2"X6" BRASS NIPPLE 23.5500 47.10
50 2 EA 2" BALL VLV FIPXFIP NO LEAD B11-777-NL 275.0000 550.00
60 4 EA 2"X12" BRASS NIPPLE 45.0000 180.00
70 2 EA 2" BRASS 90 NO LEAD 19.0000 38.00
80 4 EA 2" BRASS STREET 90 NO LEAD 30.0000 120.00
90 2 EA #TF500 BLOW -OFF HYDRANT 4'0" 665.0000 1,330.00
100 4 EA 562S SCREW VB COMP 24"-36" 55.0000 220.00
110 2 EA #6 VLV BOX BASE 41.0000 82.00
Subtotal: 3,176.62
Tax: 134.21
Bid Total: 3,310.83
ALL STOCK DELIVERIES ARE SUBJECT TO SHIPPING CHARGES
All PVC and HOPE material is quoted for shipment within 7 days of quote/bid date. All other material is quoted for shipment within 30 days of quote/bid date.
After 7 days for PVC and HDPE or 30 days for all other material, ALL quoted pricts are subject to review based on current market conditions.
Ent By TJH 10/16/19 14:28:41
BIDCNNEW
K.C. Bobcat
WWW.KCBOBCAT.COM
BLUE SPRINGS, MO 64015 2209 W. 40 Highway, 816.229.4006 - 800 697.4228, FAX 816.229.7631
OLATHE, KS 66061, 1220 S. Hamilton Circle, 913.829 4600. 800.598.4228, FAX 913.829.1552
TRACY, MO 64079,100 Tracy Dr. 816.431.3001 •800.984.3001, FAX 816.431.3002
SPRINGFIELD, MO 65803, 2520 N Eastgate, Ave. 417.865.3535 877.808.1062, FAX 417.865.6186
REMIT TO: P. O. Box 844511 Dallas, TX 75284-4511
Invoice
INVOICE # 18157234
LOCATION 18
DATE 10/17/19
PAGE 1 OF 1
BILL TO
038558
BEEMER CONSTRUCTION
606 SE CENTRAL DR
BLUE SPRINGS, MO 64014-3311
SHIP TO
BEEMER CONSTRUCTION
ORDER NUMBER 18287066
ORDER DATE 10/17/19
JOB NUMBER
CUSTOMER NUMBER Mattox
FREIGHT TERMS Allow
WRITTEN BY Hunter Ballinger
CONTACT DAVID BEEMER
SHIP VIA Customer Pickup
PAYMENT TERMS
Charge Net/30
F.O.B.
JOB QTY | PROBLEM/SOLUTION PART DESCRIPTION | LABOR | PARTS | OTHER | SUBTOTAL
1/2X2OREBARGR40 20 20 0 5.95 EA 119.00
1/2X20(#4) GR40 DOMESTIC
150/BOL (ORANGE)
Signature
Print Name
Tell us about your Bobcat experience! Receive a chance in a $500
drawing. Go to: www.reviewbobcat.com and enter code 1866. You can
also complete a survey by calling 855.745.7814.
VENDOR # 386 PERIOD 7
INVOICE DATE 10-17-19 DUE DATE
INVOICE # 18157234 INTIALS PREPAY _ CR MEMO _
G/L # | [illegible] | [illegible] | COST TYPE | EQUIP NO | AMOUNT
CHECK NO.
CHECK DATE NET AMOUNT
MERCHANDISE TOTAL | FREIGHT & MISC | TAX | TOTAL CHARGES | DEPOSIT BALANCE | DEPOSIT APPLIED | DEPOSIT AMOUNT | INVOICE TOTAL
119.00 0.00 10.24 129.24 0.00 0.00 0.00 129.24
BLUE SPRINGS CTR FIRE SP -0.60 MISSOURI - 5.03
JACKSON COUNTY - 1.49
BLUE SPRINGS CITY - 2.97
JACKSON COUNTY KANSAS CITY 15
Returns for credit of parts and supplies must be returned with invoice copy within 15 days of purchase, must be in new and salable condition and will be subject to a
restocking charge. Special order, special use, and non -stocking items may be deemed non -returnable. Electrical components are not returnable if package is opened.
Geiger READY-MIX
Central Dispatch 913-281-0111
Leavenworth: Accounting 913-772-4010
Fax 913-772-8661
INVOICE
REMIT TO:
GEIGER READY-MIX
P.O. BOX 875439
KANSAS CITY, MO 64187-5439
Sold to: Beemer Construction
606 SE Central Drive
Blue Springs MO 64014
Delivered to. Mattox Rd & 39th St
DETACH AND RETURN
INVOICE DATE 10/29/19
INVOICE NO. 948548
CUSTOMER NO. 467
OUR JOB NO 93
CUST. P.O. NO. 2230
OWNER:
PLEASE READ
REVERSE SIDE.
Geiger Ready Mix Invoice #: 948548 page:
DATE (MO/DAY) | DELIVERY TICKET | QUANTITY | UNIT PRICE | TOTAL AMOUNT
10/28 A559-3/4-4.46 FUEL SURCHARGE Order: 252 10.00 117.75 1,177.50
1.00
*226654
[illegible stamp with check information]
CHG Sales Tax 77.72
TO INSURE PROPER CREDIT, RETURN REMITTANCE COPY WITH YOUR PAYMENT.
PAYMENT TERMS: PROVIDED NO PRIOR INVOICES ARE PAST DUE AND THIS INVOICE
IS PAID BY 11/10/19 YOU MAY DEDUCT $25. 10
AMOUNT DUE 1.255.22
ACCOUNTS NOT PAID WITHIN TERMS ARE SUBJECT TO A 1% MONTHLY FINANCE CHARGE
Beemer Construction Co., Inc.
Utility Contractor
606 S.E. Central Drive
Blue Springs, MO 64014.3311
(816) 229-2266 Fax (816) 229.2571
October 16, 2019
To: City of Riverside
Attn: Mr. Travis Hoover
From: Chad Sipes
Re: 39th & Mattox Rd. Water Main Extension
Riverside, MO
Mr. Hoover,
The following are the items we have encountered that were modified from the original set of plans.
1. Due to existing utilities we encountered in conflict and the lack of cover over the proposed water main due to the slope for
which the main was to be installed, the water main alignment shifted from a 7 foot offset from back of curb to approximately
12 feet offset from back of curb from approximate station 14+00 to 20+05. This caused the main to be installed near the toe
of the slope which generated extra depth on the water main and additional disturbance to both existing swales. The shift in
alignment also impacted crossing an existing storm sewer line not shown on the plans for which was potholed determining
the water main required going under to achieve adequate cover. Missouri American also required restrained joints within this
segment of the main; therefore field lok gaskets were added at each joint. The additional depth required additional time
installing the main and re -grading the existing swales. We also had additional labor and materials installing the fire hydrant at
station 17+28 and labor and materials at the tie-in location on the north end due to the change in the water main alignment.
Materials
12" Field Lok Gasket $4,335.75
12" 45 degree bends $1,698.51
12" 221/2 degree bends $1,122.88
12" Solid Sleeve $467.17
Labor
4 man crew $17,134.05
Equipment
25 Each @ $173.43
3 Each @ $566.17
2 Each @ $561.44
1 Each @ $467.17
5 days @ $3,426.81 per day
PC228 Excavator/WA 150 Loader/ Pickup 5 days @ $642.94 per day $3,214.70
Bobcat T-153 Skid Steer 1 days @ $154.00 per day $140.00
Total $28,113.06
*The additional time of 5 days impacted the substantial completion contract time.