HomeMy WebLinkAbout1706 CO 3 Beemer Construction 2019 Mattox & 39th Water Main Extension BILL NO. 2020-004 ORDINANCE NO.
AN ORDINANCE AUTHORIZING AND APPROVING CHANGE ORDER NO. 3 TO THE
BEEMER CONSTRUCTION CO., INC. CONTRACT FOR THE 2019 MATTOX & 39TH WATER
MAIN EXTENSION (PROJECT 618-227) ORIGINALLY AUTHORIZED BY ORDINANCE NO.
1674.
WHEREAS,the City previously determined the need for certain infrastructure work
necessary to accommodate the doorLink Manufacturing, Inc. ("doorLink") industrial
warehousing and distribution facility, as well as other future projects, to be located
adjacent to the doorLink site; and
WHEREAS, the 2019 Mattox and 39th Water Main Extension fulfills a public
purpose and will further the growth of the City, facilitate the development of.the entire
Horizons site, improve the environment of the City, foster increased economic activity
within the City, increase employment opportunities within the City, and otherwise be in
the best interests of the City by furthering the health, safety and welfare of its residents,
and taxpayers; and
WHEREAS, the City previously approved the 2019 Mattox and 39th Water Main
Extension specifications through the passage .and approval of Ordinance No. 1663
("Project No. 618-227"); and
WHEREAS, the City and Beemer Construction Co., Inc. ("Beemer"), entered into
a contract authorized by and through Ordinance 1674, for the installation and construction
of Project No. 618-227 (the "Project Agreement") which is beneficial for other City
purposes in exchange for the City paying Beemer no more than Two Hundred Sixty-Five
Thousand Eighty-Seven Dollars and No Cents ($265,087.00); and
WHEREAS, the Board has previously approved Change Order No. 1 to the
Beemer Project Agreement totaling an additional cost of Twenty-Four Thousand Seven
Hundred Eighty and 46/100 Dollars ($24,780.46), for Beemer to directional drill the water
line under the drive approaches along the west side of Mattox Road, which allowed for
no disruption of the business as well as a simpler method of dealing with the additional
costs associated with the high groundwater table in Horizons; and
WHEREAS, the Board has previously approved Change Order No. 2 to the
Beemer Project Agreement totaling an additional cost of Thirty-Eight Thousand Thirty
Three and 48/100 Dollars ($38,033.48), for Beemer to install the water line along the north
side of 39th Street rather than the original plan for installation on the south side of 39th
Street, such change necessitated due to the high groundwater table from the flood of
2019; and
WHEREAS, the staff recommends approval of Change Order No. 3, as described
in the Change Order No. 3 Memo attached hereto as Exhibit A and incorporated herein,
which increases the authorized expenditure by an additional Fourteen Thousand Four
Hundred Forty-Six and 38/100 Dollars ($14,446.38), for a total amount to be paid
pursuant to the Project Agreement not to exceed Three Hundred Forty-Two Thousand
WA 14237896.2
Three Hundred Forty-Seven and 32/100 Dollars ($342,347.32), for additional materials,
as recommended by Missouri American Water Company (along with related labor costs),
incurred by Beemer while installing the water line along the north side of 39th Street; and
WHEREAS, the City has determined that authorization for the aforesaid additional
expenditure pursuant to the Project Agreement with Beemer fulfills a public purpose and
will further the growth of the City, facilitate the development of the entire Horizons site,
improve the environment of the City, foster increased economic activity within the City,
increase employment opportunities within the City, enable the City to direct the
development of the entire Horizons site, and otherwise be in the best interests of the City
by furthering the health, safety, and welfare of its residents and taxpayers.
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF ALDERMEN OF THE
CITY OF RIVERSIDE, MISSOURI, AS FOLLOWS:
SECTION 1 — BEST INTEREST OF THE CITY TO APPROVE CHANGE ORDER
NO. 1. The Board of Aldermen finds that it is in the best interest of the City to approve
Change Order No. 3, attached hereto as Exhibit A and incorporated herein, and that
such approval fulfills a public purpose and will further the growth of the City, facilitate the
development of the entire Horizons site, improve the environment of the City, foster
increased economic activity within the City, increase employment opportunities within the
City, and otherwise is in the best interests of the City, by furthering the health, safety, and
welfare of its residents and taxpayers, and the Board of Aldermen does hereby approve
Change Order No. 3 to increase the authorized expenditure to Beemer by an additional
Fourteen Thousand Four Hundred Forty-Six and 38/100 Dollars ($14,446.38), for a total
amount to be paid pursuant to the Project Agreement not to exceed Three Hundred Forty-
Two Thousand Three Hundred Forty-Seven and 32/100 Dollars ($342,347.32).
SECTION 2 — AUTHORITY GRANTED. The City hereby authorizes the City
Administrator and the City Engineer to execute and deliver Change Order No. 3,
consistent with the terms of this Ordinance and Missouri law, and hereby authorizes the
Mayor, the City Administrator, Special Counsel to the City and other appropriate City
officials to take any and all actions as may be deemed necessary or convenient to carry
out and comply with the intent of this Ordinance and to execute and deliver for, and on
behalf of, the City all certificates, instruments, agreements and other documents, as may
be necessary or convenient to perform all matters herein authorized. Further, the City
Administrator is hereby authorized to expend an additional Fourteen Thousand Four
Hundred Forty-Six and 38/100 Dollars ($14,446.38), for a total amount to be paid
pursuant to the Project Agreement not to exceed Three Hundred Forty-Two Thousand
Three Hundred Forty-Seven and 32/100 Dollars ($342,347.32).
SECTION 3 — EFFECTIVE DATE. This Ordinance shall be in full force and effect
from and after its passage and approval.
[Remainder of Page Intentionally Blank]
2
WA 14237896.2
BE IT REMEMBERED that the above was read two times by heading only,
PASSED AND APPROVED by a majority of the Board of Aldermen and APPROVED by
the Mayor of the City of Riverside, Missouri, this 4th day of February, 2020.
kaWeen L. Rose, M yor
;ATT-ESf
Robin Kincaid, city:Clerk
Approved as to form:
SWecial
ane LLP
Sunsel to the City
bnar
3
WA 14237896.2
EXHIBIT A
CHANGE ORDER NO. 3 WITH COVER MEMO
4
WA 14237896.2
Corr OF
RSMISSOURI
Upstream from ordinary.
2950 NW Vivion Road
Riverside, Missouri 64150
MEMO DATE: January 22, 2020
AGENDA DATE: February 4, 2020
TO: Mayor and Board of Aldermen
FROM: Travis Hoover
RE: Change Order 3: BEEMER CONSTRUCTION CO., INC.
2019 Mattox & 39' Water Main Extension (618-227)
i
BACKGROUND: This change order is for an additional $14,446.38. Due to the high groundwater
table from the Flood of 2019, the sanitary sewer is not able to be installed until
the water subsides. In order to continue the project for DoorLink, the water
line and sanitary sewer switched locations along 39`h St. Switching the water line
from the south side of 39`h St to the north side incurred additional costs for
material and labor.
BUDGETARY IMPACT: $14,446.38 would be authorized for budget year 2019-2020.
Original Contract Amount $ 265,087.00
Total of Previous Changes $ 62,813.94
Total this Change Order $ 14,446.38
Current Contract Total $ 342,347.32
RECOMMENDATION: Staff recommends approval of the ordinance and acceptance of the change order
with Beemer Construction Co., Inc.
CITY OF CHANGE ORDER NO. 3 Date Prepared: 1/22/2020
MISSOURI Contractor Name: Beemer Construction Co., Inc.
Project Name: 2019 Mattox&39th Water Main Extension Page Number: 1 of 3
Project Number: 618-227 It of Pgs Attached: 2
Contract Date: 8/6/2019 The following changes to the original contract amount were required to cover cost incurred by
Project Location: Riverside,Missouri the Contractor or to reflect savings realized by the Contractor as a result of a change in the
actual constructed quantities from the estimated quantities shown on the Bid Proposal.
REQUIRED CHANGES IN PRESENT CONTRACT
Contract or Contract or Contract or Item Description &Reason for Change Order(Please describe item below and then follow with reason for New or New or New or
Line Item No. Previous Previous Previous Unit Change Order) 1) Requested by City 2)Unknown Site Condtions 3)Not incorporated in plans/specs Adjusted Adjusted Adjusted
Quantity Unit Price Amount Quantity Unit Price Amount
n/a 0.0 $0.00 $0.00 1 Details listed in December 23,2019 letter-see attached 1.00 $2,540.58 $2,540.58
n/a 0.0 $0.00 $0.00 1 Details listed in January 13,2020 letter-see attached 1.00 $11,905.80 $11,905.80
$0.00 $0.00
$0.00 $0.00
$0.00 1 $0.00
$0.00 $0.00
Previous Total 1 $0.00 Adjusted Total $14,446.38
Net Change $14,446.38
Statement of Contract
Original Contract Amount $265,087.00
Net Amount of Previous Additions and Deductions $62,813.94
Net Contract Amount Prior to This Request $327,900.94
Amount of This Request $14,446.38
New Contract Amount $342,347.32
Percent Change in Contract Amount 4.41%
DESIGN ENGINEER: CITY OF RIVERSIDE, MISSOURI:
Company: City Engineer:
Name Printed: Travis Hoover Signed Date
Signed: City Administrator:
Date: Brian Koral Signed Date
CONTRACTOR: ON-SITE PROJECT MANAGER:
CONTRACTOR'S Certification for Change Order: ON-SITE PROJECT MANAGER Certification for Change Order:
The undersigned CONTRACTOR certifies that all changes In accordance with the Contract Documents,the on-site observations,and
described above are necessary in order for the CONTRACTOR to the data comprising this change order,the on-site project manager certifies
proceed with execution of the contract documents,and that the to the Owner that to the best of the on-site project manager's knowledge,
values stated above are correct with respect to the work information and belief the above referenced changes are necessary in order to
anticipated under this change order. proceed with the execution of the contract documents,and that the values
stated above are correct with respect to the work anticipated under this change order
Company: Company:
Name Printed: Name Printed:
Signed: Signed:
Date: Date:
Utility Contractor
606 S.E.Central Drive
Blue Springs,MO 64014.3311
(816)229.2266 Fax(816)229-2571
December 23,2019
To: City of Riverside -
Attn: Mr.Travis Hoover
From: Chad Sipes
Re: 391&Mattox Rd.Water Main Extension
Riverside,MO
Mr.Hoover,
The following are the additional items incurred for mobilizing to the project site on December 12,2019 to install approximately 124
LF of 12"DIP under the proposed roadway to allow the roadway contractor to install curbs.Also,the 124 LF of pipe were restrained
with field lok gaskets per Missouri American Water Company.
Mobilization $1,500.00
12"Field Lok Gaskets 6 Each @$173.43 $1,040.58
Total $2.540.58
Member of Heavy Constructors Association
"An Equal Opportunity Employer
Ce-.V
Utility Contractor
606 S.E.Central Drive
Blue Springs,MO 64014-3311
(816)229.2266 Fax(816)229.2571
January 13,2020
To: City of Riverside
Attn: Mr.Travis Hoover
From: Chad Sipes
Re: 3911&Mattox Rd.Water Main Extension
Riverside,MO
Mr.Hoover,
The following is the additional mobilization of equipment to complete the remaining portion of the project.Also,Missouri American
Water Company is requiring we restrain the remaining portion of the water main left to install.Below are the additional costs.
Mobilization 1 Each @$1,500.00 $1,500.00
12"Field Lok Gaskets 60 Each @$173.43 $10,405.80
Total $11,905.80