HomeMy WebLinkAbout1761 CO 4 Hoy Excavating, LLC 2019 Mattox & 39th Project BILL NO. 2021-004 ORDINANCE NO. 171 l
AN ORDINANCE AUTHORIZING AND APPROVING CHANGE ORDER NO. 4 TO THE HOY
EXCAVATING, LLC CONTRACT FOR THE 2019 MATTOX & 39TH PROJECT (618-227)
ORIGINALLY AUTHORIZED BY ORDINANCE NO. 1646 AND AMENDED BY ORDINANCE
NO. 1653.
WHEREAS, the City previously determined the need for certain infrastructure work
necessary to accommodate the doorLink Manufacturing, Inc. ("doorLink") industrial
warehousing and distribution facility, as well as other future projects, to be located
adjacent to the doorLink site; and
WHEREAS, the 2019 Mattox and 39th Project fulfills a public purpose and will
further the growth of the City, facilitate the development of the entire Horizons site,
improve the environment of the City, foster increased economic activity within the City,
increase employment opportunities within the City, and otherwise be in the best interests
of the City by furthering the health, safety and welfare of its residents and taxpayers; and
WHEREAS, the City previously approved the 2019 Mattox and 39th Project
specifications through the passage and approval of Ordinance No. 1646 ("Project No.
618-227") which was amended by Ordinance No. 1653; and
WHEREAS, the City and Hoy Excavating, LLC ("Hoy"), entered into a contract
authorized by and through Ordinance 1653, for the installation and construction of Project
No. 618-227 (the "Project Agreement") which is beneficial for other City purposes in
exchange for the City paying Hoy no more than One Million Seven Hundred Fifty-Four
Thousand Four Hundred Sixty-Eight Dollars and No Cents ($1 ,754,468.00); and
WHEREAS, the Board has previously approved Change Order No. 1 to the Hoy
Project Agreement totaling an additional cost of Fourteen Thousand Three Hundred
Ninety-Eight and 60/100 Dollars ($14,398.60), for Hoy to extend the sanitary service line
for the benefit of doorLink while allowing 39th Street to be constructed without delaying
the project, which otherwise would have necessitated a delay until the groundwater table
subsided from the flood of 2019; and
WHEREAS, the Board has previously approved Change Order No. 2 to the Hoy
Project Agreement totaling an additional cost of Eight Thousand Six Hundred Seventy-
Two and 95/100 Dollars ($8,672.95), for Hoy to modify the elevation and beneficial angles
of the extension to the sanitary service line for the benefit of doorLink while allowing 39th
Street to be constructed without delaying the project, which otherwise would have
necessitated a delay until the groundwater table subsided from the flood of 2019; and
WHEREAS, the Board has previously approved Change Order No. 3 to the Hoy
Project Agreement totaling an additional cost of Nine Thousand One Hundred Seventy-
One and 62/100 Dollars ($9,171.62), for Hoy to add a second entrance along 39th Street
at doorLink's request; and
WA 14549397.2
WHEREAS, staff recommends approval of Change Order No. 4, as described in
the Change Order No. 4 Memo attached hereto as Exhibit A and incorporated herein,
which increases the authorized expenditure by an additional Two Hundred Twenty-Eight
Thousand Three Hundred Fifty-One and 99/100 Dollars ($228,351.99), for a total amount
to be paid pursuant to the Project Agreement not to exceed Two Million Fifteen Thousand
Sixty-Three and 16/100 Dollars ($2,015,063.16), for Hoy to change structure elevations
due to relocating the sewer line to the south side of the road and to extend Helena Road
between Doorl-ink and Horizons XI; and
WHEREAS, the City has determined that authorization for the aforesaid additional
expenditure pursuant to the Project Agreement with Hoy fulfills a public purpose and will
further the growth of the City, facilitate the development of the entire Horizons site,
improve the environment of the City, foster increased economic activity within the City,
increase employment opportunities within the City, enable the City to direct the
development of the entire Horizons site, and otherwise be in the best interests of the City
by furthering the health, safety, and welfare of its residents and taxpayers.
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF ALDERMEN OF THE
CITY OF RIVERSIDE, MISSOURI, AS FOLLOWS:
SECTION 1 — BEST INTEREST OF THE CITY TO APPROVE CHANGE ORDER
NO. 4. The Board of Aldermen finds that it is in the best interest of the City to approve
Change Order No. 4, attached hereto as Exhibit A and incorporated herein, and that
such approval fulfills a public purpose and will further the growth of the City, facilitate the
development of the entire Horizons site, improve the environment of the City, foster
increased economic activity within the City, increase employment opportunities within the
City, and otherwise is in the best interests of the City, by furthering the health, safety, and
welfare of its residents and taxpayers, and the Board of Aldermen does hereby approve
Change Order No. 4 to increase the authorized expenditure to Hoy by an additional Two
Hundred Twenty-Eight Thousand Three Hundred Fifty-One and 99/100 Dollars
($228,351.99), for a total amount to be paid pursuant to the Project Agreement not to
exceed Two Million Fifteen Thousand Sixty-Three and 16/100 Dollars ($2,015,063.16).
SECTION 2 — AUTHORITY GRANTED. The City hereby authorizes the City
Administrator and the City Engineer to execute and deliver Change Order No. 4,
consistent with the terms of this Ordinance and Missouri law, and hereby authorizes the
Mayor, the City Administrator, Special Counsel to the City and other appropriate City
officials to take any and all actions as may be deemed necessary or convenient to carry
out and comply with the intent of this Ordinance and to execute and deliver for, and on
behalf of, the City all certificates, instruments, agreements and other documents, as may
be necessary or convenient to perform all matters herein authorized. Further, the City
Administrator is hereby authorized to expend an additional Two Hundred Twenty-Eight
Thousand Three Hundred Fifty-One and 99/100 Dollars ($228,351.99), for a total amount
to be paid pursuant to the Project Agreement not to exceed Two Million Fifteen Thousand
Sixty-Three and 16/100 Dollars ($2,015,063.16).
2
SECTION 3 — EFFECTIVE DATE. This Ordinance shall be in full force and effect
from and after its passage and approval.
BE IT REMEMBERED that the above was read two times by heading only,
PASSED AND APPROVED by a majority of the Board of Aldermen and APPROVED by
the Mayor of the City of Riverside, Missouri, this 5th day of January 2021 .
All
AO
Ka leen L. Rose, M yor
ATTEST-
E C
Robin Kincaid; Ci#yjClerk
EXHIBIT A
CHANGE ORDER NO. 4 WITH COVER MEMO
4
CITY OF
RSI
MISSOURI
Upstream from ordinary.
2950 NW Vivion Road
Riverside, Missouri 64150
MEMO DATE: December 17, 2020
AGENDA DATE: January 5, 2021
TO: Mayor and Board of Aldermen
FROM: Travis Hoover
RE: Change Order 4: HOY EXCAVATING, LLC
2019 Mattox & 39`h Project (618-227)
BACKGROUND: This change order is for an additional $228,351.99. This includes changing
structure elevations due to relocating the sewer line to the south side of the
road. This change order also includes an extension of Helena Rd. to close the
gap between DoorLink and Horizons XI. This additional work is warranted
because at the time of the 2019 Mattox and 39`h Street Project, the resulting gap
in Helena Road in relation to the development of the Horizons XI site was
unknown but has now been realized, and delay in causing the natural extension
of Helena Road to connect up to the Horizons XI site will negatively impact
short-term traffic conditions in the area.
BUDGETARY IMPACT: $228,351.99 would be authorized for budget year 2020-2021.
Original Contract Amount $ 1,754,468.00
Total of Previous Changes $ 32,243.17
Total this Change Order $ 228,351.99
Current Contract Total $ 2,015,063.16
RECOMMENDATION: Staff recommends approval of the ordinance and acceptance of the change order
with Hoy Excavating, LLC.
CITY OF CHANGE ORDER NO. 4 o.n P,.,vi 12/17/2020
RIVERS
ns3ouRl Contractor Name: Hoy Excavating, LLC
Prop<t N.m.r 2019 Mattox&39th Project Pap•Number i of 1
Propct NumD•r: 618-227 •at Pq.•nacn.d t
contncr Det.: 4/25/2019 The follovnng changes to the Ongtnal contract amount were required to cover cost incurred by
Prop"Lodatlon: Riverside,MISSOuh the Contractor or to reflect sivin9e reNded by the Contractor as a result of a charge In the
actual constructed quantities from the estimated quantities shown on the Bid Proposal.
REQUIRED CHANGES IN PRESENT CONTRACT
Contract or Contract W contract or New or New or New or
Ram Description a Reason/or Chan"Order(Please dascnba Ham below and than follow with mason r
Line Item No PreviousQualnitPrIPrevious PreAmountous Unit Change Order) 1) Regtrnted by Cry 2)Unknown Site Conditions 3)Not Incorporated In planwe OunAdjusted Adjusted Adjusted
mount
Quant UM Pnoa AHMta1I Ouand Unit Price Amount
Ns 0.0 50.00 50.00 1 Change older request aid 12/17/2020•sea attached for details 1.00 $5.127.96 $5,127.96
Na 0.0 $0.00 $0.00 1 Helena Road Extension dated 11/9/2020-see attached for details 1,00 9223,224.03 $223.224.03
50.00 $0.00
$0.00 50.00
50.00 $0.00
$0.00 $0.00
Previous Total 50.00 Adjusted Total 2228,351.99
Net Change $228,351.99
Statem.nl or cont.Ol
Original Contract Amount $1,754,468.00
Net Amount of Previous Additions and Deductions 532,243.17
Net Contract Amount Prior to This Request 51,788,711.17
Amount of This Request 5228,351.99
New Contract Amount 52,015,083.16
Percent Change in Contract Amount 12.78%
DESIGN ENGINEER: CITY OF RIVERSIDE,MISSOURI:
City Engineer: ( APPROVED
�}.� �
N•m.PnMe
Travis Hoover oftA r r R V V E LJ
City Administrator:
Der Brian Koval
CONTRACTOR: ONSITE PROJECT MANAGER:
CONTRACTOR'S Cereecatlon for Chabot Order CTM A City Administrator
The undenipnM CONTRACTOR carne,that eve dnnges In accordanq win The Contract Documents me orvute observations,snot
oesmbN,above are necessary in order for The CONTRACTOR to the den oompr i nig ml.Onenge order,an on-wte protect manag.r cenMes
proceed w111,eee"Ibon of do mntrect dowmeMe,and mel me to he Owner ant n the best of me bn-en prop"man lk"e.Knp'Medge.
veiue.stand ebava an correct with need n Dte•Alk inlor,,abon aid belief m.Wove r.Mertdetl dtwges we recess in oder To
anbpppted under Ma dNnge order prdwed`Mm IM..ervnon of the COMrq dpburwnle,aid Thal This velu•f
.feted Wove are coma env,nbpW To The won anbopeted under this Onen"order
Nem Pnntee Nene Pww•d
sgao _ Seed
wN // 4ey'/ D.n —
H
OY ING
i
i
CommunitiesI Construction
12/17/2020
Change Order to raise Manholes A6,A7,&A8
Unit of 5%Overhead Extended Unit
Desription Measure Quantity Unit Price 5%Profit Price
2'x 4' Dia Barrel Section Each 1 $ 440.00 $ 44.00 $ 484.00
3'x 4' Dia Barrel Section Each 1 $ 660.00 $ 66.00 $ 726.00
3'-6"x 4' Dia Barrel Section Each 1 $ 770.00 $ 77.00 $ 847.00
4'x 4'Dia Barrel Section Each 1 $ 880.00 $ 88.00 $ 968.00
Installation of Barrel Sections LS 1.00 $1,911.78 $ 191.18 $ 2,102.96
Total $ 5,127.96
OY E XC AVAT. I N G
' r
"Building Communities and Providing Construction Serzices-
11/9/2020
Helena Road Extension
Unit of
Desription Measure Quantity Unit Price Extended Unit Price
Mobilization LS 1 $ 23,543.80 $ 23,543.80
Clear&Grub LS 1 $ 4,281.89 $ 4,281.89
Const.Staking LS 1 $ 2,943.05 $ 2,943.05
Unclassified Excavation CY 790 $ 12.85 $ 10,151.50
Compaction of Earthwork CY 484 $ 9.51 $ 4,602.84
6"of Type 5 Base SY 2,274 $ 7.44 $ 16,918.56
2"Asphalt Surface SY 1,949 $ 10.25 $ 19,977.25
9"Asphalt Base SY 1,949 $ 39.89 $ 77,745.61
Curb&Gutter LF 975 $ 24.59 $ 23,975.25
Pavement Markings LF 975 $ 1.46 $ 1,423.50
4"Sidewalk SF 2,437 $ 5.22 $ 12,721.14
18"RCP Storm Sewer LF 87 $ 76.23 $ 6,632.01
Curb Inlet 15'x 41 EA 2 $ 4,033.34 $ 8,066.68
18"End Section EA 1 $ 748.75 $ 748.75
18"Rip-Rap SY 5 $ 122.74 $ 613.70
Sediment Fence LF 1,128 $ 2.52 $ 2,842.56
Inlet Protection EA 4 $ 70.20 $ 280.80
Construction Entrance EA 1 $ 1,511.61 $ 1,511.61
Temp Seeding Acre 1 $ 1,050.00 $ 1,050.00
Seeding Permanent Acre 0.237 $ 3,721.52 $ 882.00
Sodding Permanent SY 266 $ 8.69 $ 2,311.54
$ 223,224.03