HomeMy WebLinkAboutR-2022-125 Approving CO6 to the Agreement with Crossland Construction Co., Inc for Additions to Public Safety RESOLUTION NO. R-2022-125 A RESOLUTION APPROVING CHANGE ORDER 6 TO THE AGREEMENT WITH CROSSLAND CONSTRUCTION COMPANY, INC. FOR ADDITIONS & RENOVATIONS RIVERSIDE PUBLIC SAFETY RESULTING IN A REVISED CONTRACT AMOUNT OF $4,818,987.78 FOR SUCH PURPOSES WHEREAS, the City of Riverside ("City") issued an Invitation to Bid for the Additions & Renovations Riverside Public Safety (Project No. 537-086) ("Project") which was awarded to Crossland Construction Company, Inc. ("Crossland")pursuant to Resolution R-2022-038; and WHEREAS, the Board of Aldermen finds that it is in the best interest of the City to approve Change Order 6 to the agreement with Crossland, resulting in a total revised contract amount not to exceed $4,818,987.78. NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE CITY OF RIVERSIDE, MISSOURI,AS FOLLOWS: THAT Change Order 6 to the Agreement between the City and Crossland, a copy of which is attached hereto and incorporated herein, is approved and the Mayor is authorized to execute the same on behalf of the City. The resulting revised total contract amount shall not exceed $4,818,987.78. FURTHER THAT the Mayor, City Administrator and all other required city officials are authorized to take such other actions and/or execute and deliver for and on behalf of the City all certificates, instruments, agreements and other documents as may be deemed necessary or convenient to carry out and comply with the intent of this Resolution. PASSED AND ADOPTED by the Board of Aldermen of the City of Riverside, Missouri, the 15th day of November 2022. Kat leen L. Rose, Mayor Robin Kinca'r City'C1_erk CITY OF (2RIVYERSI MISSOURI Upstream from ordinary. 2950 NW Vivion Road Riverside, Missouri 64150 MEMO DATE: November 10, 2022 AGENDA DATE: November 15, 2022 TO: Mayor and Board of Aldermen FROM: Noel Bennion RE: Change Order 6: Crossland Construction Company, Inc. Additions & Renovation Riverside Public Safety (537-086) BACKGROUND: This change order includes several items. Fire-rated ceilings are needed in the Fire Captain & Lieutenant bunk rooms ($3,816.75). The design for these ceilings had to change to accommodate HVAC equipment. Floor drains were added to accommodate ice machines and a mop sink for the fire storage area. There are also deducts for compressed air piping that can remain ($10,462.20). Structural X-bracing in the wall at the fire kitchen addition had to be adjusted ($6,898.69). New coping cap for the roof will be added instead of re-using the old coping cap ($35,663.25). A broken sanitary pipe was found at the sally port that will be repaired ($5,692.63). BUDGETARY IMPACT: An increase of$62,533.52. Original Contract Amount $4,717,000.00 Total of Previous Changes** $39,454.26 Total this Change Order $62,533.52 Current Contract Total $4,818,987.78 RECOMMENDATION: Staff recommends approval of the resolution and acceptance of the change order with Crossland Construction Company, Inc. **LISTING OF PREVIOUS CHANGE ORDERS: CO I: Relocate conduit in walls $33,413.48 CO2: Replace degraded sewer pipe $ 9,671.55 CO3: Reuse existing VAV units -$ 2,535.81 C04: Keep existing windows -$ 3,520.91 C05: Lighting, vapor barrier, panels $ 2,425.95 Total $39,454.26 v�ii '\e ® ■.� Document G 7 0 ■n 2017 Change Order PROJECT.(Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION: Additions&Renovation Contract For:General Construction Change Order Number.006 Riverside Public Safety Date:May 16,2022 Date:October 24,2022 2990 NW Vivion Rd. Notice to Proceed:July 11,2022 Riverside,MO 64150 OWNER:(Name and address) ARCHITECT:(Name and address) CONTRACTOR:(Name and address) City of Riverside WSKF,Inc. Crossland Construction Company,Inc. 2950 NW Vivion Road 110 Armour Road 833 S.East Avenue Riverside,MO 64150 North Kansas City,MO 64116 Columbus,KS 66725 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description of the change and,if applicable,attach or reference specific exhibits.Also include agreed upon adjustments attributable to executed Construction Change Directives) 1.Per PRO11,Add rated ceilings in Captain's A148 and Lieutenant's bunk rooms. $3,816.75 2.Per PRO19,Add a mop sink and floor drain to Gear Wash A 160. Additionally,revise the air piping system in the apparatus bays as requested. $10,462.20 .3.Per PC00023,Revised existing X-bracing in the west wall of Dining A138. This revision will also involve the relocation of the existing roof drain and existing Fire Department Connection. $6,898.69 4.Per PC00024,Replace the existing prefmished metal coping where the roof overlay is being installed per on site meeting; approximately 620 LF of coping to be replaced. $35,663.25 5.Per PC00026,Replace existing broken sanitary sewer pipe located beneath sally port footing. This work also involves the removal and replacement of existing asphalt paving to facilitate this work. $5,692.63 $62,533.52-Total Increased Cost for Change Order No.Six AIA Document G701"—2017.Copyright @ 1979.1987.2000,2001 and 2017 by The American Institute of Architects.All rights reserved.The'American Institute of Architects;'AIA,'the AIA Logo,and'AIA Contract Documents'are registered trademarks and may not be used without permission.This document was produced by AIA software at 16:13:15 ET on 1 0124/2 0 2 2 under Order No.4104237064 which expires on 10/19/2023,is not for resale,is licensed for one-time use only,and may only be used in accordance with the AIA Contract Documents°Terms of Service.To report copyright violations,e-mail copyright@aia.org_ User Notes: (389ADA39) The original Contract Sum was $ 4,717,000.00 The net change by previously authorized Change Orders $ 39,454.26 The Contract Sum prior to this Change Order was $ 4,756,454.26 The Contract Sum will be increased by this Change Order in the amount of $ 62,533.52 The new Contract Sum including this Change Order will be $ 4,818,987.78 The Contract"time will be increased by Zero(0)days. The new date of Substantial Completion will be March 8,2023 NOTE:This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price,or the Contract Time,that have been authorized by Construction Change Directive until the cost and lime have been agreed upon by both the Owner and Contractor,in which case a Change Order is executed to supersede the Construction Change Directive. NOT VAUD UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER. WSKP, ne. Crossland Construction Company.Inc. City of Riverside ARC 4IT 1�hrm m Y CONTRACTOR(Firm name) ;7�-- R/Firm mane Ryan Wacker 0. L4-61 SIG TUBE SIGNATURE S i7ATURE Rick Kuhl,Principal Ryan Wacker, Project Manager ja4 i e6w L. As-e PRINTED NAME AND TITLE PRINTED NAME AND Tan Wacker, ProjecFN IT D§AME AND TITLE DATE DATE DAT CROSSLAND Potential Change Order CONSTRUCTION COMPANY.INC. Riverside Public Safety Additions and Renovation- 22MO17RWZD 22MO17RWZD 2990NW Vivion Road Riverside,MO 64150 Date: 10/20/2022 Number: 0011 Subject: PR011-Rated Ceiling in Captain A148_Revised Source of Funding: Owner Contract Change Order Description Cast for the added layer of drywall at the ceiling and around the lights for the rated ceiling.Captain and Lieutenant bunk rooms. Da s Re guested: 0 Change Total: $3,816.75 Item Number Description lAmount 01 Cost for installing an added layer of drywall and wrapping light fixture boxes for a rated assembly. $3,635.00 02 P&O $181.75 Approved By: By Signaturep.��'(;ems-7U L Date Re:Riverside PS-Framing Re < Re Ail ® Kevin Kimbrough<aaabuilders@gmaiLtom> Farward �7 PH EJ PN� ;U To Ryan Wacker Wed 1WI91202212:14 PI.1 (D tou replied to this message an 10119Q0224:15 Mi. EXTMALIff"L-This-email orQEatedfrom outside aft7ie orgarilmtbn.Donutdkk Fln�oropen atbdisnentz unless.you Re thesender ars know dse corstent is safe;;e:.' _u�:= Ryan, Below are the cost assisted with the above list 1 am still working on PR 13 but will hate R to you shortly. Sd eut nan s Ce ling.for framing around fights:$240.00 Drywall $243.00rame/hang around lights:$1,60D.00 flat ceiling: $1,552.00$3,635.00ht Patches: Material-Drywall$627.00 labor- $4,098.00 TOTAL-$4,715.00 -Column Bumpout In Detectives Material:$173.00 Labor. $980.00 TOTAL: $1,153.00 -Swapping ceiling for ACT in lobby restrooms Material:$2,600.00 Labor: $2,600.00 TOTAL: $5,200.00 CROSSLAND Potential Change Order CONSTRUCTION COMPANY,INC. Riverside Public Safety Additions and Renovation- 22MO17RWZD 22MO17RWZD 2990 NW Vivion Road Riverside,MO 64150 Date: 1 111 0/2 0 22 Number: 0019 Subject: PR019-Gear Storage Floor Drain Mop Sink and Revised Air Source of Funding: Owner Contract Change Order Piping Revised Description Cost for revisions per PRO19.Cost includes all labor,material,and equipment for new scope of work. Days Re guested: 0 Chan a Total: $10,462.20 Item Number Description lAmount 01 PRO19-Air Piping,mop sink,floor drain revisions. $9 964.00 02 P&0 -- — ------ —--._... $498.20 Approved By: By Signature Date zz BID RECAP SHEET 11/912022 Company: Genesis Plumbing Enterprises LLC dobNeme: G:IMy DrivelFastPiPElFastEST-Shared.siteUobsiRIVERSIDE PUBLIC SAFETY.job i"ia1�"!a6 Bid: Labor Crew SA Equipment Fixtures Materials Hours Rate Labor$ Total Piping Materials BLabor $2,258 322 $ 85.00 $2,734 $4,993 Pipe Equipment Total VI/Summary $0 $0 Pipe Fixtures Total wlSummary $0 $0 Pipe Specialties Total w/Summary $0 $0 Pipe Other Total w/Summary SO $0 Equipment $0 0.0 $ 73.75 $0 $0 Fixtures $0 0.0 $ 73.75 $0 $0 OTHER COST $0 0.0 Varies $0 $0 Rental Equipment $0 $D Overtime Pay $20A0 $0 $0 Double Time Pay $40.82 $0 so Supervision 0.0 $77.00 $0 $0 Project Management 1.3 $60.00 $77 $77 Project Assistant 00 W00 $0 $0 Warehouse Help 0.0 $40.00 $0 $0 Truck Driver O.0 $6000 $0 $0 Sub Total $0 $0 $2,258 $2,811 $5.070 Sales Tax $0 $0 $0 $0 $0 Sub Total $2.268 $2.811 $5,070 TOTAL FITTERIPLUMBERHOURS 37-2 TOTAL ADMINITRUCK DRIVERANAREHOUSE HOURS 1.3 TOTAL OT HOURS 0.0 TOTAL DOUBLE TIME HOURS 0.0 Subcontracts Including Sales Tax $718 Sub Total $5,788 Start-up Equipment Hours Warranty Material Escalation Freight Start-Up Travel Permits Cost Total $5,788 0.00°k Contingency $0 Subtotal $5,788 10.0% Labor $273 10.0% ProjectMngmnt $8 20.07 Project Assist $0 20.0°A Truck DrivedWarehouse s0 10.0-A Materials $m 10.0% Rental $0 20.0% Fixtures $0 20.0% Equipment $0 10.0% Warranty $0 $36.00 10.0% Subcontracts -31�$72 Sub Total $8,367 $6,331.00 Overall Mark-up% 10.0% TOTAL PROFIT $579 DOES NOT INCLUDE CONTINGENCY Sales Tax $0 Sub Total $6.367 0.0% Bond $0 QUOTED PRICE $8,367 P9 SUBCONTRACTORS including Sales Tax Company. Genesis Plumbing Enterprises LLC JobName: G:1My Drive%FastPIPEIFastEST-SharedsiteWobsIRIVERSIDE PUBLIC SAFETY.job Description Total Price Subcontractor Used NOTES 1 Controls 2 Test&Balance 3 insulation $368 Midland Thermal 4 lExcavallon 5 Hoisting 6 Chemical Treatment 9 Core Drilling $350 KC Coring, 11 Sheet Metal 14 Abatement 15 Fire Protection 16 lEfectrical 17 Paintin 18 General Construction 19 Concrete Cutting&Patching 20 Floor Repair 21 Roof Re arc 22 IStructural Steel 23 jEngineeft 24 Plumbing 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 Totals $718 Report Chart Company. Genesis Plumbing Site: FastEST-Sharedsite Job: FastEST-Shared»RIVERSIDE PUBLIC SAFETY(Plumbing) Report: Material/Labor Summary Type: Selected Sections Report Includes: Pipe Report Sections: 11,12,13 Material Labor Product Type Pipe y; ® Fittings k� Valves f Joints $f 41M Hangers/Excav 4 k , i s f'9 g t ' Job Items ;S Summary Statistics 1 Pipe LF: 10 Insulation al LF/H 0 0 Tot r. 3.27 Diameter Inches: 0 =' Diameter Inches/Hr. 0.00 Weight(LS): 93 Surface Area(SF): 63 Total Cost:$2.258.45 Total Hours:32.2 Volume ): 2 Volume(GalGal): 16 FastPIPE® 11/8/2022 Price List Company: Genesis Plumbing Site: FastFST-Sharedsite Job: FastEST-Shared»RIVERSIDE PUBLIC SAFETY(Plumbing) Qty Part Size Description Material Group List Date Mfgr Part# Source Modified List Factor Net 14 EA % Hex Nuts Bolts 6/8/2021 Bolt-Pak <Catalog> 6/82021 $021 0.800 $0.17 1 EA 2 NH Cl Soil San Tee Cast Iron Soil NH Ftgs Char 4/1/2022 Charlotte NH-28 <Catalog> 4/112022 6:10 AM $47.20 0.385 $18.17 1 EA 2 NH Cast Iron 1/4 Bend Cast Iron Soil NH Ftgs Char 4/12022 Charlotte NH-4 <Catalog> 4/112022 6;10 AM $3420 0.385 $13.17 3 LF 2 No-Hub Cast Iron Soil Pipe Cast Iron Soil NH Pipe Char 4/12022 Charlotte NH-2 <Catalog> 4/112022 6:10 AM $23.19 0385 $8.93 11 EA 1h Wrot Copper 90 Ell Copper Fittings Elkhart 3/182022 Elkhart Prod 107-C <Catalog> 3282022 6:16 AM $6.74 0.135 $0.91 2 EA 'h Wrot Copper Tee Copper Fittings Elkhart 3/182022 Elkhart Prod 111 <Catalog> 3282022 6:16 AM $1132 0.135 $1.53 4 EA 'h Wrot Copper Cap Copper Fittings Elkhart 3/1812022 Elkhart Prod 117 <Catalog> 3282022 6:16 AM $4.86 0.135 $0.66 2 EA 3/;h Wrot Copper Reducing Tee Copper Fittings Elkhart 3/182022 Elkhart Prod 111-R <Catalog> 3282022 6:16 AM $25.98 0.135 SSS1 46 LF 'h Type L Hard Copper Tube Copper Tube Mueller 8/122022 Mueller <Catalog> 82320226:44 AM $5.79 0.439 $2.54 1 LF Va Type L Hard Copper Tube Copper Tube Mueller 811Z/2022 Mueller <Catalog> 8/232022 6A4 AM $9.44 OA39 $4.14 1 EA 2 Plain Standard Clevis Hanger Hangers 6/152022 B-Line 83100 <Catalog- 6272022 8:39 AM $923 0390 $3.60 6 EA 21h Plain Standard Clevis Hanger Hangers 6/152022 B-Line B3100 <Catalog> 6/272022839 AM $14.90 0.390 $5.81 14 EA 3/s Plain Washer Miscellaneous 6/82021 Varies <Catalog> 6/82021 $0.04 1.000 $0.04 5 EA 2 No-hub Couplings No-Hub Oamps Charlotte 6/1/2022 Charlotte NH-1 <Catalog> 6/3/2022&40 AM $30.70 0.160 ;$4.91 2 EA 2 PVC DWV P-Trap PVC DWV Fittings 5/22022 Charlotte 706-X <Catalog> 6/3/2022 8.40 AM $10055 0.100 $10.06 1 EA 3 PVC DWV P-Trap PVC DWV Fittings 52/2022 Charlotte 706-X <Catalog> 6/32022 SAO AM $33954 0.100 $33.95 4 EA 2 PVC DWV Wye PVC DWV Fittings 5/2/2022 Charlotte 600 <Catalog> 6/32022&40 AM $69.72 0.100 $6.97 4 EA 2 PVC DWV 1/4 Bend PVC DWV Fittings 522022 Charlotte 300 <Catalog> 6/32022 8:40 AM $35.14 0.100 $3.51 1 EA 3 PVC DWV 1/4 Bend PVC DWV Fittings 52/2022 Charlotte 300 <Catalog> 6/32022 SAO AM $10322 0.100 $10.32 4 EA 2 PVC DWV 1/8 Bend PVC DWV Fittings 522022 Charlotte 321 <Catalog> 6/32022 SAO AM $32.55 0.100 $326 1 EA 3 PVC DWV 1/8 Bend PVC DWV Fittings 52/2022 Charlotte 321 <Catalog> 6/32022 SAO AM 592.42 0.100 $9.24 2 EA 4 PVC DWV 1/8 Bend PVC DWV Fittings 522022 Charlotte 321 <Catalog> 6/32022 SAO AM $169.28 0.100 $16.93 1 EA 3,2 PVC DWV Reducing Wye PVC DWV Fittings 522022 Charlotte 601 <Catalog> 6/32022 8:40 AM $139.32 0.100 $1393 2 EA 4,2 PVC DWV Reducing Wye PVC DWV Fittings 522022 Charlotte 601 <Catalog> 6/3/2022 SAO AM $204.52 0.100 $20AS 51 LF 2 Sch 40 PVC DWV PE Pipe PVC DWV Pipe 1/12022 Charlotte 7200 <Catalog> 1/1/2022 54.73 OA60 $2.13 3 LF 3 Sch 40 PVC DWV PE Pipe PVC DWV Pipe 1/12022 Charlotte 7300 <Catalog> 1/12022 $9.53 0.450 $429 1 LF 4 Sch 40 PVC DWV PE Pipe PVC DWV Pipe 1/12022 Charlotte 7400 <User> 922202210:28 AM $12.82 O-590 $7.57 2 EA 1 Ve,20 Stub Out Cop Pltd Extrdd Bracket Residential Hangers 8/15/2022 Sioux Chief 521-118R <Catalog> 6/32022 SAO AM $6.05 1.000 $6.05 6 EA 2%.12 Galy Insulation Prot Shield Shields/Saddles 6/152022 S-Line 83151-3X <Catalog> 627/2022 B39 AM $37.84 0390 $14.76 28 LF 3/9 Plain Threaded Rod Threaded Rod 6/152022 B-Line 83205 <Catalog> 627/2022 839 AM $220 0.440 $0.97 2 EA 1h UPBA-150 2Pc Srz LF Swt Ball Valve wW9J#Ure Low Lead Valves 7/12022 Milwaukee UPSA-150 <Catalog> 7/192022 6:01 AM $7633 0350 $26.72 7EA % Plain Wide Jaw Top C-Clamp Upper Attachments 6/152022 B-Line B3033 <Catalog> 6/2720228:39AM $13.07 0.350 $4.57 38 EA 'h Lead-Free Solder Joints Joints 8/172021 Varies <Catalog> 8/17/2021 $020 1.000 $020 4 EA VC Lead-Free Solder Joints Joints 8/1-12021 Varies <Catalog> 8/172021 $024 1.000 $0.24 35 EA 2 PVC Solvent Weld Joints Joints 8/172021 Varies <Catalog> 8/172021 $027 1.000 $0.27 8 EA 3 PVC Solvent Weld Joints Joints 8/172021 Varies <Catalog> 8/17/2021 $0.40 1.000 $0.40 8 EA.4 PVC Solvent Weld Joints Joints 8/17/2021 Varies <Catalog> 8/17/2021 $0.52 1.000 $0.52 FastPiPEO 11/8/2022 f Qty Part Sae Description Material Group List Date Mfgr Part# Source Modified List Factor Net 2 FA 2 FD Floor Drain Drains and Carriers 4/21/2022 8:15 AM <Jobltem> 4/21/2022 8:15 AM $330.00 1.000 $330.00 1 FA <None> MOP Mop Sink Plumbing Fixtures 9/28/2022 1:05 PM <Jobltem> 9/28/2022 t05 PM $74364 1.000 $74364 FastPIPEm -2- 11/8/2022 Invoice Invoice No: 176629 Invoice date: 7 Nov 2022 KC Coring&Cutting PO No.: 7240 Central St Requisition No.: Kansas City, MO 64114 Quote No.: (816)523-2015 Phone • (816)523-8493 Fax Name: COMMERCIAL BUILDING Site Address: 2990 NW VIVION RD RIVERSIDE,MO 64150 Bill To: GENESIS PLUMBING ENT. Terms: Net 30 Day P.O.BOX 1263 BLUE SPRINGS,MO 64014 DI:of Sry Item Qty WO No. Ref.Number Description Price Taxable Total 1.00 10/31/2022 Core DOI Diameter, 8" 175.00 EACH No 175.00 050263 Depth: 12" Material: Concrete Wall Drilled on foundation outside of building 1.00 10/31/2022 Core Drill Diameter. 6" 175.00 No 175.00 050263 Depth: 12" Material: Concrete Wall Drilled on foundation outside of building Sub Total: 350.00 Tax: 0.00 Invoice Total: 350.00 Page 1 of 1 BID RECAP SHEET 11/9I2022 Company. Genesis Plumbing Enterprises LLC .IobName: G:1My DrivelFastPIPEIFastESTShered.siteUobsIRNERSIDE PUBLIC SAFETY.job Bid: Labor Crew 3A Equipment Fixtures Materials Hours Rate Labor$ Total Piping Materials&Labor $1,865 41.0 $ 8 .00 $3,484 $5.349 Pipe Equipment Total w/Summary $0 $0 Pipe Fixtures Total w/Summary $0 --so - Pipe Specialties Total w/Summary s0 $0 Pipe Other Total w/Summary $0 $0 Equipment $0 0.0 $ 73.75 $0 $0 Fixtures $'0 0.0 $ 73.75 $0 $0 OTHER COST $o 0.0 varies $0 s0 Rental Equipment $0 $0 Overtime Pay $20A0 $0 0 Double Time Pay $40.82 s0 s0 Supervision 0.0 $77.00 so $0 Project Management 1.6 $60.00 $98 $98 Project Assistant 0.0 $30.00 s0 $0 Warehouse Help 0.0 $40.00 $0 $0 Truck Driver 0.0 $60.00 s0 $0 Sub Total $0 $0 $1,865 $3,563 $5,448 Sales Tax so 50 so $0 $0 Sub Total $0 $1.865 $3,583 $5,448 TOTAL FITTERIPLUMBER HOURS 41.0 TOTAL ADMINITRUCK DR111ERI WAREHOUSE HOURS 1.6 TOTAL OT HOURS 0.0 TOTAL DOUBLE TIME HOURS 0.0 Subcontracts including Sales Tax $0 Sub Total SS,448 Startup Equipment Hours Warranty Material Escalation Freight Start-Up Travel Permits Cost Total $5.448 0.00% Contingency $0 Subtotal $5,448 10.0% Labor $S48 10.0% Project Mngmnt $10 20.0% Project Assist $0 20.0% Truck Driver/Warebouse so 10.01A Materials $187 10.0% Rental $0 20.0% Fixtures $0 20.0% Equipment $0 10.0% Warranty $0 10.0% Subcontracts $0 Sub Total $5XA Overall Mark-up% 10.0% TOTAL PROFIT DOES NOT INCLUDE CONTINGENCY Sales Tax $0 Sub Total 993 0.0% t3ond� QUOTED PRICE�$5,983 P � I V Czl-rri N (� -- ��� I Price List Company: Genesis Plumbing Site: FastEST-Sharedsite Job: FastEST-Shared»RIVERSIDE PUBLIC SAFETY(Plumbing) Qty Part Sae Description Material Group List Date Mfgr Part!! Source Modified List Factor Net 1 EA 3/4 BA400 2Pc FP Bmz Thd Ball Valve w/CP B8811 Valves Milwaukee 7/1/2022 Milwaukee BA400 <Catalog> 7/19/2022 6:01 AM $85.95 0350 $30.08 i 1 EA 1 BA400 2Pc FP Bmz Thd Ball Valve w/CP BBtlII Valves Milwaukee 7/1/2022 Milwaukee BA400 <Catalog> 7/19/2022 6:01 AM $95.86 0350 $3355 26 EA 31a Hex Nuts Botts 6/8/2021 Bolt-Pak <Catal > 6 8 021 09 /2 $021 0.800 $0.17 3 EA V4 Plain Standard Clevis Hanger Hangers 6/152022 B-Une B3100 <Catalog> 6/2712022 8:39 AM $5.79 0390 $126 10 EA 1 Plain Standard Clevis Hanger Hangers 6/152022 B-Une B3100 <Catalog> 6/272022 8:39 AM S607 0390 $2.34 26 EA 3h Plain Washer Miscellaneous 6/82021 Varies <Catalog> 6/82021 $0.04 1.000 $0.04 ' 20 EA 1,4 Standard Galy Steel Nipple Steel Nipples Capitol 10/82021 Capitol <Catalog. 10/8/2021 $12-61 OS00 $631 5 EA 1,6 Standard Galy Steel Nipple Steel Nipples Capitol 10/8/2021 Capitol <Catalog> 10/8/2021 S17.56 OS00 $8.78 21 LF 3/4 Sch 40 Blk Steel Pipe A53 T&C Steel Pipe Columbia 911712022 Columbia <Catalog> 10/1720221:35 PM $1134 0210 $238 94 LF 1 Sch 40 Blk Steel Pipe A53 T&C Steel Pipe Columbia 9/172022 Columbia <Catalog> 10/1720221:35 PM $15.36 0210 $3.22 4 EA 3/4 1500 Blk Mall 90 Ell Thd Malleable Fittings Anvil 4252022 Anvil Int 1101 <Catalog> 6/32022 8.40 AM $9.87 0.121 $1.19 12 EA 1 150#Blk Mall 90 Ell Thd Malleable Fittings Anvil 425/2022 Anvil Int 1101 <Catalog> 6/32022 8:40 AM $1720 0.121 $2.08 8 EA 1 1500 Blk Mall Tee Thd Malleable Fittings Anvil 4252022 Anvil Int 1105 <Catalog> 6/3/2022 8:40 AM $26.93 0.121 $3.26 1 EA 3/4 150#Blk Mall Coupling Thd Malleable Fittings Anvil 4252022 Arml Int 1121 <Catalcg> 6/32022 8:40 AM $1328 0.121 $1.61 5 EA 1 1500 Blk Mail Cap Thd Malleable Fittings Anvil 4252022 Anvil Int 1124 <Catalog, 6/32022 8:40 AM $13.57 0.121 $1.64 5 EA 1 150#Blk Mail GJ Union Thd Malleable Fittings Anvil 4252022 Anvil Int 463 cCatalog> 6132022 8.40 AM $5736 0.121 $6.94 1 EA 3/a,1/z 150#Blk Mall Red Tee Thd Malleable Fittings Anvil 425/2022 Anvil Int 1105R <Catalog> 6/32022 8:40 AM $2433 0.121 $294 52 LF 3h Plain Threaded Rod Threaded Rod 6/152022 B-Line B3205 <Catalog> 6272022 8:39 AM $2.20 0.440 $097 13 EA % Plain Wide Jaw Top C-Clamp Upper Attachments 6/152022 B-Line B3033 <Catalog> 627/2022 839 AM $13.07 0350 $4S7 50 EA 1 Male Iron Pipe Thread Joints Joints 8/17/2021 Varies <Catalog> 8/172021 $0.00 0.000 S0.00 1 EA rh Female Iron Pipe Thread Joints Joints 8/172021 Varies <Catalog> 8/17/2021 $0.13 1.000 $0.13 14 EA 3/4 Female Iron Pipe Thread Joints Joints 8/172021 Varies <Catalog> 8/17/2021 $0.13 1.000 $0.13 65 EA 1 Female Iron Pipe Thread Joints Joints 8/172021 Varies <Catalog> 8/172021 $0.13 1.000 $0.13 1 EA <None> HR Hose Reel Job Items 11/82022 3:08 PM <Jobltem> 11/82022 3:08 PM $957.07 1.000 $957.07 1 EA <None> QC Quick Connect Fitting Job Items 11/82022 7A8 AM <Jobltem> I1/B/2022 T48 AM $12.75 1.000 $12.75 2 EA <None> REHR Raise Existing Hose Reel Job Items 11/920 22 10.09 AM <Jobitem> 11/9202210 09 AM $25.00 1.000 $25.00 i I i FastPIPE® i1 /2022 i i Report Chart Company: Genesis Plumbing 1 Site: FastEST-Shared.site Job: FastEST-Shared»RIVERSIDE PUBLIC SAFETY(Plumbing) Report. Material/Labor Summary Type: Selected Sections Report Includes: Pipe Report Sections: 15 I I Material Labor Product Type Pipe Fittings r" ? Valves " K - 3'` , Specialties 11111110 Joints � ?< :Hangers/Excav ty Job Items $170 E 3A - $3S3 SummaryStatistl cs Pipe LF: 115 Insulation LF: 0 Total LF/Hr. 2.30 �. Diameter Inches: 0 Diameter Inches/Hr. 0. Weight(LB): 217 Surface Area(SF): 46 i Total Cost:$1,865.11 Total Hours:41.0 Volume ): 1 Volume(GalGal): 5 i i FasMPE® 1 /9/2022 K C ,y III� mI£r 3- coMPANY Hose Reel 4400 E 12TH STREET KANSAS CITY, MO 64127 _ �' ; PHONE (816) 842-9466 ' �` .. FAX (999) 999-9999 0060768 11/08122 1 Expiration Date 11122122 F $�' ,� Revised Date 11108122 ME Bid Due Date 1I/08/22 GENESIS PLUMBING ENTERPRISES PO BOX 18456 KANSAS CITY, MO 64133-8456 _ j� � =- x-- Phone (816) 353-6724 Tony Schallenberg Fax (816) 353-2579 tscha@kcwindustrial.com (816) 842-9466 ROM q�} r " . � 003927 11* 10TH & 25TH NET 30 Tony Schallenberg ANTHONY SCHALLENBERG D mg A 1.0 1 REEL CRAFT DP7850 OLP HOSE REE 957.0705 957.07 2CAGG Tax Area Id Net Sales 957.07 Frei ght .00 Tax .00 Quotation Total 957.07 E. r:LCFIAFTI' #E Pfcyjljcfs Wleog. Resou're-., OurCompany- coniactus; Home,.1nteraC!;ve Catalog'Air Hose Ree:s'General Ku Hose Reels A5030 OILP-112,n.,.50k. A5850 OLP-1/2 In.x 50 ft.Premium Duty Hose Reel S2ri&s,SX` err durable in.comp-clk.,a ri"'13 ol.p.el cara!,.s'Ail U&C",spice -Ilh,Serx wb -­i�l dtlp ofik's iirnoaLh i'.3-,va.,Siml vao tht jad lile J�A Spedfications PDr,s(A­,so,l.s lechnlcal Support Vid... CAD Ot,virigs ;AQs Reel Specifications and Dimensions %V.Ight 41 lbs A 17.625- 5erles 5005 B 10.75 Hasa I.D. 112' C 9 75' Hose O.D. 0.75- D 2.5' Hose Length 50, E 7.25, Pressure 300 psi I. H...End 112,NPTOA) Fluid Path Materials Inlet 18,NPT(,) Reel Outlet I/.`UPT(F) Internal Fluld?ath Steel Hose Included Y. SwNel Assembly Stet! hiaxTemperature 150:F sivivel Seal Buna UPC 609567031119 Print PDF Page company Support: videos 'I ]REELCRA-F—TI� -rxl" 92, 6 no BID RECAP SHEET 1v6rzozz Company. Genesis Plumbing Enterprises LLC JobName: O:IMy DrivelFasIPIPEIFastESTShared sitsUobstRIVERSIDE PUBLIC SAFETY.job Bid: Labor Crew 3A Equipment Fixtures Materials Hours Rate Labor$ Total Piping.Materials&Labor $0 5.6 $ SS.OD $480 $480 Pipe Equipment Total w/Summary $0 $0 Pipe Fixtures Total w/Summary $0 $0 Pipe Specialties Total w/Summary $D $0 Pipe Other Total w/Summary 65 $0 Equipment $0 0.0 $ 73,75 $D $0 Fixtures $0 0.0 $ 73.75 $0 $0 OTHER COST $0 0.0 Varies $0 w Rental Equipment $0 $0 Overtime Pay $20A0 $0 $0 Double Time Pay $40.82 $0 $0 Supervision 0.0 $77.00 $0 $0 Project Management 02 $60.00 $14 $14 Project Assistant 0.0I $0 $0 Warehouse Help 1 0.0 $40.00 $0 $0 Truck Driver 0.0 $60.00 SD $0 Sub Total $D $0 40 $493 $493 Sates Tax $0 $0 so $0 $0 Sub Total $0 $493 $493 TOTAL FITTERIPLUMBER HOURS 5.6 TOTAL ADMINrTRUCK DRIVQtNYAREHOUSE HOURS 0.2 TOTAL OT HOURS 0.0 TOTAL DOUBLE TIME HOURS 0.0 Subcontracts including Sales Tax $0 Sub Total $493 Start-up Equipment Hours Warranty Material Escalation Freight Start-up Travel Permits Cost Total $493 O.OD% Contingency $0 Subtotal $493 10.0% Labor $48 10.0% Project Mngmnt $1 20.0% Project Assist $0 20.0% TruckDriver/Warehouse $0 20.0% Materials $0 o 0% Rental $0 20.0% Fixtures $0 20.0% Equipment $0 10.0% Warranty $0 10.0% Subcontracts $0 Sun Total $543 Overall Mark-tip% 10.0% TOTAL PROFIT $49 DOES NOT INCLUDE CONTINGENCY S Tax Sub Total $543 OA% Bond $0 QUOTED PRICE Aid 1 ------------------- ---.__...._... --.. - ------- - ..._.. 141 � Report Chart Company: Genesis Plumbing Site: FastEST-Sharedsite Job: FastEST-Shared»RIVERSIDE PUBLIC SAFETY(Plumbing) Report: Material/Labor Summary Type: Selected Sections Report Includes: Pipe Report Sections: 17 Material Labor i Product Type Pipe ® Fittings 3.0 Joints Hangers/Excav $67 ZZ Summa y Statistics Pipe LF. 50 J- - Insulation LF: I 0 Total LF/Hr. 8.8 Diameter Inches: 0 Diameter Inches/Hr.. 0.00 Weight(LB): 9 Surface Area(SF): 18 Total Cost:$230.38 Total Hours:5.6 volume ): - Volume(GalGal 2): 2 FastPIPE® �� � � �" Pi��/iTJ'O�" 1 /8/2022 BID RECAP SHEET 11/8/2022 Cempany. Genesis Plumbing Enterprises LLC JobName: G:1My DrivelFastPIPEIFasLEST-SharedsitelJobsIRIVERSIDE PUBLIC SAFETY.Job Bid: Labor Crew 3A Equipment Fixtures Materials Hours Rate Labor$ Total Piping Materials&Labor $0 12.9 $ 85.00 $1.095 $1.095 Pipe Equipment Total wlSummary $0 $0 Pipe Fixtures Total wlSumm $0 $0 Pipe Specialties Total w/summary, $0 $0 Pipe Other Total wlSummary $0 $0 Equipment $0 0.0 $ 73.75 $0 $0 Fixtures $0 0.0 $ 73.75 $0 $0 OTHERCOST $0 0.0 Varies $0 $0 Rental Equipment $0 $D Overtime Pay $20A0 $0 $0 Double Time Pay $40.82 $0 $0 Supervision 0.0 $77.00 $0 $0 Project Management 0.5 $60.00 $31 531 Project Assistant 0.0 $30.00 so SO Warehouse Help 0.0 $40.00 $0 $0 Truck Driver 0.0 60.00 $0 $D Sub Total 1 $0 $0 $0 $1,126 $1,126 Sates Tax $0 $0 $0 LE SO SO Sub Total $01 $1,126 $1,126 TOTAL FITTERIPLUMBERHOURS 129 TOTAL ADMI N/TRUCK DRI VERIWAREHOUSE HOURS 0.5 TOTAL OT HOURS 0.0 TOTAL DOUBLE TIME HOURS 0.0 Subcontracts including Sales Taxi $0 Sub Total $1,128 Start-up Equipment Hours Warranty Material Escalation Freight Start-Up Travel Permits Cost Total $1,126 0.00% Contingency $D Subtotal $1,126 10.0% Labor $11D 10.07 ProjectMngmnt $3 20.0% Project Assist $0 20.0% Truck DriverANarehouse $0 20.096 Materials $0 10.oS5 Rental $0 20.0% Fixtures $0 20.01A Equipment $0 10.0% Warranty $0 10.0% Subcontracts $D SubTatal $1,239 Overall Mark-up% 10.0% TOTAL PROFIT $113 DOES NOT INCLUDE CONTINGENCY Sales Tax $0 Sub Total S'1,239 0.0°b Bond $0 QUOTED PRICE $1,239 1 -- - .ion - --- --- Report Chart Company: Genesis Plumbing Site: FastEST-Sharedsite Job: FastEST-Shared»RIVERSIDE PUBLIC SAFETY(Plumbing) Report: Material/Labor Summary Type: Selected Sections Report Includes: Pipe Reporl[Sections: 14 Material labor `.i Product Type Pipe ® Fittings 6.9 Joints - Hangers/Excav $157 I, r :r �364Yy i _ Ir .. Summary Statistics j Pipe LF. 113 } Insulation LF: 0 Total LF/Hr. 8.77 a , Diameter Inches: 0 Diameter Inches/Hr. 0.00 Weight(LB): 203 Surface Area(SF): 41 Total Cost: 2 Total Hours:12.9 Volume(CF): 1 Volume(Gal): 4 f FastPIPE® 0 ��iNG O 11/8/2022 BID RECAP SHEET 11/8/2022 Company: Genesis Plumbing Enterprises LLC JobNams: GAMY DrivelFastPIPEIFastEST-Shared.site)JobsUWERSIDE PUBLIC SAFETY.job Bid., Labor Crew 3A Equipment Fixtures Materials Hours Rate Labor$ Total Piping Materials&Labor $378 13.0 $ 85.00 $1.103 $1,482 Pipe Equipment Total w/Summary $0 $0 Pipe Fixtures Total w/Summary $0 $0 Pipe Specialties Total wlSumme $0 $0 Pipe Other Total w/Summ $0 $0 Equipment $0 0.0 $ 73.75 $0 $o Fixtures $0 0.0 $ 73.79 $0 $0 OTHER COST $0 0.0 Varies $0 $0 Rental Equipment $0 $0 Overtime Pay $20.40 $0 $0 Double Time Pay $40.82 $0 $0 Supervision 0.0 $77.00 $0 :S1,513 Project Management 0.5 $80.00 $31 Project Assistant 0.0 $30.00 $0 Warehouse Help 0.0 $40.00 $0 Truck Driver 0.0 $60.00 $0 Sub Total $0 $0 $378 $1,135 Sales Tax $0 $0 SO $0 $0 Sub Total $0 $378 $1,135 $1,513 TOTAL FITTER/PLUMBFJ2 HOURS 13.0 TOTAL ADmiwrRUCK DRIVERANAREHOUSE HOURS 0.5 TOTAL OT HOURS 0.0 TOTAL DOUBLE TIME HOURS 0.0 Subcontracts including Sales Tax $0 Sub Total $1.513 Start-up Equipment Hours Warranty Material Escalation Freight Start-Up Travel Permits Cost Total $1,513 0.00% Contingency $0 Subtotal $1,513 10.0% Labor $110 10.0% Project Mngmnt $3 20.0% Project Assist $0 20.0% Truck DriverlWarehouse $0 10.0% Materials $38 10.0% Rental $0 20.01A Fixtures $0 20.01/0 Equipmenti $0 10.0% warwrityl $0 10.01A Subcontracts $0 Sub Total $1,664 Overall Mark-up°k 10.0% TOTAL PROFIT $151 DOES NOT INCLUDE CONTINGENCY Sales Tax $0 Sub Total 884 6.0 o Bond 1 $0 QUOTED PRICE Q fs�d a� Report Chart Company: Genesis Plumbing Site: FastEST-Sharedsite Job: FastEST-Shared»RIVERSIDE PUBLIC SAFETY(Plumbing) Report: Material/Labor Summary Type: Selected Sections Report Includes: Pipe Report Sections: 16 Material Labor Product Type Pipe Fittings Specialties $34 Joints Hangers/Excav 3 t Summary Statistics Pipe LF: 69 Insulation LF: .0 Total LF/Hr. 5.35 Diameter Inches: 0 Diameter Inches/Hr. 0.00 Weight(LB): 133 Surface Area(SF): 27 Total Cost:$378.25 Total Hours:13.0 volume Gal)* 3 Volume(Gal): 3 1 FastPIPE® C(J��� 11/8/2022 R'1 r'�JCI �sr�I� Price List Company: Genesis Plumbing Site: FastEST-Shared.site .lob: FastEST-Shared»RIVERSIDE PUBLIC SA..FETV(Plumbing) Qty Part Size Description Material Group List Date Mfgr Part# Source Modified List Factor Net 14 EA 3/a Hex Nuts Bolts 6/8/2021 Bolt-Pak <Catalog> 6/8/2021 $0.21 0.800 $0.17 7 EA 1 Plain Standard Clevis Hanger Hangers 6/15/2022 B-Line B3100 <Catalog> 6/27/2022 8:39 AM $6.01 0.390 $2.34 14 EA 3/a Plain Washer Miscellaneous 6/8/2021 Varies <Catalog> 6/8/2021 $0.04 1.000 $0.04 4 EA 1,4 Standard Galv Steel Nipple Steel Nipples Capitol 10/8/2021 Capitol <Catalog> 10/8/2021 $12.61 0.500 $6.31 1 EA 1,6 Standard Galy Steel Nipple Steel Nipples Capitol 10/8/2021 Capitol <Catalog> 10/8/2021 $17.56 0.500 $8.78 69 LF 1 Sch 40 Blk Steel Pipe A53 T&C Steel Pipe Columbia 9/17/2022 Columbia <Catalog> 10/17/26221:35 PM $15.36 0.210 $3.22 9 EA 1 150#Blk Mall 90 Ell Thd Malleable Fittings Anvil 4/25/2022 Anvil Int 1101 <Catalog> 6/3/2022 8:40 AM $17.20 0.121 $2.08 2 EA 1 150#Blk Mall Tee Thd Malleable Fittings Anvil 4/2S/2022 Anvil Int 1105 <Catalog> 6/3/2022 8:40 AM $26.93 0.121 $3.26 1 EA 1 150#Blk Mall Coupling Thd Malleable Fittings Anvil 4/25/2022 Anvil Int 1121 <Catalog> 6/3/2022 8:40 AM $19.89 0.121 $2.41 2 EA 1 150#Blk Mall Cap Thd Malleable Fittings Anvil 4/25/2022 Anvil Int 1124 <Catalog> 6/32022 B:40 AM $13.57 0.121 $1.64 1 EA 1 150#Blk Mall GJ Union Thd Malleable Fittings Anvil 4/25/2022 Anvil Int 463 <Catalog> 6/3/2022 8:40 AM $57.36 0.121 $6.94 28 LF 3/s Plain Threaded Rod Threaded Rod 6/15/202R B-Line B3205 <Catalog> 6/27/2022 8:39 AM $2.20 0.440 $0.97 7 EA 3/a Plain Wide Jaw Top C-Clamp Upper Attachments 6/152022 B-Line B3033 <Catalog> 6/27/2022 8:39 AM $13.07 0.350 $4.57 10 EA 1 Male Iron Pipe Thread Joints Joints 8/17/2021 Varies <Catalog> 8/17/2021 $0.00 0.000 $0.00 30 EA 1 Female Iron Pipe Thread Joints Joints 8/17/2021 Varies <Caialog> 8/17/2021 $0.13 1.000 $0.13 C r FastPIPE® 11/8/2022 CROSSLAND Potential Change Order CONSTRUCTION COMPANY.INC. Riverside Public Safety Additions and Renovation- 22MO17RWZD 22MO17RWZD 2990 NW Vivion Road Riverside,MO 64150 Date: 10/21/2022 Number: 0023 Subject: Cost for Relocating X Bracing in West Wall Source of Funding: Owner Contract Change Order Description Cost to remove and relocate the x bracing in the existing exterior west wall.Cost includes relocating the roof drain and FDC location to accommodate the new x bracing. Days Requested: 0 Chan a Total: $6,898.69 Item Number Description Amount 01 Cost to relocate the existing roof-drain in wall. $1,984.85 02 _ Cost to relocate the FDC location for x bracing__ $1,298.00 03 — Cost to patch back the FDC location after moving the Iambs tongue. _ $350.00 04 Labor to remove and relocate the x bracing_ _ $1,824.00 OS Additional mist steel plates and.materials to weld x bracing $350.00 06 Additional wall demo to expose FDC and roof drain piping. $656.00 _— _- Profit&-Overhead(Items 01_03.&06=51%.Items 04_O5=10% —_ — $431.84 Approved By: By / l Z�) `' / Signature / Date (�` Black Dog Enterprises, LLC 9300 E. 155th Street Kansas City, MO. 64149 816-591-2622 10/12/22 Riverside Public Safety 22MO17RWZ9 Black Dog Enterprises, LLC proposes to complete the following demolition Interior wall and studs due to expose red steel in area adjacent to previous work. 4 hour minimum/per employee $656.00 Richard"Kenny" Burnett President/Owner kburnett(Wblackdogkc.com Service Disabled Veteran Enterprise 816-591-2622 Direct 816-331-7050 Fax www.blackdogkc.com ADVANTAGE FIRE PROTECTION SYSTEMS, INC. 404B NW 11" St. Blue Springs, MO 64015 Phone 816-224-3400 Fax 816-224-0401 Date: October 14, 2022 To: Crossland ATTN: Ryan RE: Riverside F.D.C. Change AFP to relocate F.D.C. to allow for new steel work. Labor 8HR $ 520.00 Materials $ 275.00 Design 1HR $ 60.00 Core $ 325.00 Sub Total $ 1,180.00 OH/MU $ 118.00 Total $ 1,298.00 IF THERE ARE ANY QUESTIONS CONCERNING THE ABOVE PLEASE ADVISE, OTHERWISE,WE AWAIT YOUR RESPONSE. RESPECTFULLY SUBMITTED, ROB KNOX PRESIDENT BID RECAP SHEET 10/17/2022 Company: Genesis Plumbing Enterprises LLC JabName: G:Wy DrivelFastPIPEIFastEST-SharedsiteUobsiA RIVERSIDE PR#.job _ Bid: Labor Gran 3A Equipment Fixtures Materials Hours Rate Labor$ Total Piping Materials&Labor $782 6.9 $ 77.00 $531E30 Pipe Equipment Total w/Summary $0Pipe Fixtures Total w/Summary $0Pipe Specialties Total w/Surnmary $0Pipe Other Total w/Summ $0Equipment $D 0.0 $ 73.75 $0OTHER COST $0 0.0 Vales $0 $ Rental Equipment $0 $0 Overtime Pay $20.40 $0 $0 Double Time Pay $40.82 So $0 Supervision 0.0 $77.00 $0 $0 Project Management 0.3 $60.00 $17 $17 Project Assistant 0.0 $30.00 $0 $0 Warehouse Help 0.0 $40.00 $0 $0 Truck Driver 0.0 $60.00 $0 - $0 Sub Total $o $0 $782 S548 $1,330 Sales Tax $0 $0 $0 $0 $0 Sub Total $0 $782 $548 $1,330 TOTAL HTTERIPLUMBER HOURS 6.9 TOTAL ADMINITRUCK DRIVERMIAREHOUSE HOURS 0.3 TOTAL OT HOURS 0.0 TOTAL DOUBLE TIME HOURS 0.0 Subcontracts including Sales Tarr $497 Sub Total $1,827 Start-up Equipment Hours Warranty Material Escalation Freight Start-Up Travel Permits Cost Total $1,827 0.00% Contingency $0 Subtotal $1,827 10.01/5 Labor $53 10.01A ProjectMngmnl $2 20.0% Project Assist $0 20.0% Truck Driver/Warehouse $0 1 ON Materials 8 10.0% Rental $0 20.0% Fixtures $0 5% M20.0% Equipment $0 $24.85 10.0% Warranty SO 10.0% Subcontracts $50 Sub Total 010 $1,984.85 Overall Mark-up% 10.0% TOTAL PROFIT $163 DOES NOT INCLUDE CONTINGENCY Sales7ax � $1,984.85 Sub Total $$010 r-o-.-O-%l Bond $0 QUOTED PRICE $2,010 $1,984.85 Report Chart Company: Genesis Plumbing Site: FastEST-Sharesite Job: FastEST-Sh.arei I> A RIVERSIDE PR#(Proposal Request) Report: Material/Labo Summary Type: Selected Sections Report Includes: Pipe Report Sections: 2 Mat arial Labor Product Type Pipe Fittings Joints $302 Hangers/Excav Job Items $42 2{8 Summary Statistics Pipe LF: 10 Insulation LF: 0 Total LF/Hr. 1.45 h u j Diameter Inches: 0 Diameter Inches/Hr. 0.00 Weight(LB): 233 Surface Area(SF): 28 Total Co Volume(CF): 4$1,275.48 Total Hours:6.9 Volume(Gal): 31 FastPIPE® 10/17/2022 .. I Price List Company: Genesis Plumbing Site: FastEST-Sharedsite Job: FastEST-Shared»A F IVERSIDE PR#(Proposal Request) Qty Part Size Description Material Group List Date Mfgr Part# Source Modified List Factor Net 2 EA 8 NH CI Soil 1/8 Bend Cast Iron Soil NH Ftgs Char 4/1/2022 Charlotte NH-12 <Catalog> 4/11/2022 6:10 AM $330.60 0385 $12728 10 LF 8 No-Hub Cast Iron Soi Pipe Cast Iron Soil NH Pipe Char 4/1/2022 Charlotte NH-2 <Catalog> 4/11/2022 6:10 AM $111.26 0385 $42.84 1 EA 8 Plain Std Riser Clamp Hangers 6/15202.2 B-Line B3373 <Catalog> 6/27/2022 8:39 AM $103.64 0390 WA2 4 FA 6 No-hub Couplings No-Hub Clamps Charlotte 6/1/2022 Charlotte NH-1 <Catalog> 6132022 8:40 AM $109.50 0.160 $17.52 7 FA 8 No-hub Couplings No-Hub Clamps Charlotte 6/l2022 Charlotte NH-1 <Catalog> 6/32022 8:40 AM $20720 0.160 $33.15 1 EA <None> CD Core Doll Job Items 10/172022 9:17 AM <Jobltem> 10/172022 9:17 AM $250.00 1.000 $250.00 FastPIPE® 10/17/2022 Dave Joe From: noah@midlandthermal.com Sent: Monday,October 17,2022 9:10 AM To: Dave Joe Cc: allison@midlandthermal.com Subject: Riverside Overflow Relocation We can do the work described via our phone conversation for$497 Respectfully, Noah Collichio Project Manager/Estimator Midland Thermal, Inc. 4600 Dr Martin Luther King Jr Blvd, Kansas City, MO 64130 noah@midland_t_hermal.com Office(816)231-8844 Cell(816)215-7702 www.midiandthermal.com A= . . &1%LVffl& MIDLAND THERMAL MECHANICAL INSULATION CON'FRACTORS 1 CROSSLAND Potential Change Order CONSTRUCTION COMPANY,INC. Riverside Public Safety Additions and Renovation - 22MO17RWZD 22MO17RWZD 2990 NW Vivion Road Riverside,MO 64150 Date: 11/2/2022 Number: 0024 _Subject: Cost to Replace the Existing Coping Cap—Revised Source of Funding: Owner Contract Change Order Description Cost to remove and replace the existing coping cap where the roof overlay is being installed per onsite roof meeting.Cost includes all labor,equipment,and materials to complete coping cap scope.See attached for extent of new coping cap.The assumption is the wood blocking below is to remain and reuse. Days Requested: 0 Change Total: $35,663.25 Item Number Description lAmount 01 Cost for new coping cap cleat and metal.Approximately 620LF of coping cap plus waste. $33,965.00 Profit&Overhead $1,698.25 f / Approved By: By Signature GAL Date 4141 FAIRBANKS AVE KANSAS CITY,KS 66106 �LIDELTA 913-371-7100 PHONE 913-371-7107 FAX INNOVATIVE SERVICES INC. wyyw.dehaservices.com October 26,2022 Crossland Construction Re: Riverside Public Safety Attn:Ryan Wacker Roof Replacement 3252 Roanoke Road Kansas City,MO 64111 Re: New coping at perimeter Mr.Wacker, Please find below associated cost of cleat and coping as requested during pre-construction meeting at Riverside Public Safety.Please note inclusions and exclusions. If days are required to extend schedule due to material procurement,Delta/DB2 will readily advise. Subcontractor proposal(DB2 Services) $ 31,713.52 Markup of Subcontractor 5%: $ 1,585.68 Bonding: $ 665.80 Total: $ 33,965.00 Respectfully Yours, J"X" Jamie Fletchall Project Manager t D 2 ml'l=L B SERVICES INC. 4141 FAIRBANKS AVE ARCHITECTURAL SHEETMETAL PHONE:913-677-2408 KANSAS CITY,KS 66106 www.db2services.com FAX:913-677-0909 October 26,2022 PROPOSAL To: Delta Innovative Services Attn: Jamie Fletchall Project: Riverside Public Safety SCOPE: Remove Existing Perimeter Copings and Cleat. Install New High Temp Underlayment Over Top of Parapet and Install New 22ga Galvanized G90 Perimeter Cleat and New 24ga Prefinished Copings. -Labor and Material to Shop Fabricate and Install, Shop Drawings: $0.00 Material: $15,701.70 Shop Fab: $1,410.93 Equipment: $0.00 Demo: $0.00 Field Labor: $11,717.63 Sub-Total: $28,830.26 OH& P 10%: $2,883.26 Total Sum Of. $31,713.52 Exclusions: • Wood Blocking • Masonry Work Schedule: • Shop Fab: • Field Install: Sincerely, Kyle Hanks Project Manager DB2 Services,Inc. xis ry iFs: '8 _ $'jENERAL O /I m H/ ROOF DETAIL AT LINK " G4iHRU WALL SCUPPER DETAIL Qx.a"""���._ \ 0, G 12 DETAIL pp U iF a oo Y� A8ROOF PLAN-NORTHROOFPLAN- ..` A 1.06 ,------- ------j, -------------------- GENERAL NOTES � " a.o+eawuu.• cm.ao..,.� - " u..,• uu PLAN NOTES:2 ...... H3 COPING DETAIL @ MTL STUDY ❑- '""" p-= H 8 COPING DETAIL @ CMU ,� " ❑ H JC PARAPET DETAIL H 1 2 SCUPPER DETAIL ❑,.Y..s,.. c 4..,...'°F..m., _ — i =— g � �� - p v:.,°..,. •�.._w. "°ate e.wa �„ f LEGENOe.,, E12 r 1 W 9 ° y _ / x CIO ROOF PLAN-SOUTH ROOFP AN- -\ SOUTH °S DETAIL I' A9 DETAIL �x 1i I Al2.. A1.o7 CROSSLAND Potential Change Order CONSTRUCTION COMPANY,INC. Riverside Public Safety Additions and Renovation- 22MO17RWZD 22MO17RWZD 2990 NW Vivian Road Riverside,MO 64150 Date: 10/28/2022 Number: 0026 Subject: Cost for Replacing Broken Pipe Under Sally Port Footing-Rev Source of Funding: Owner Contract Change Order Description Cost to replace the broken sanitary sewer pipe beneath the sally port footing.Cost includes all labor,materials,equipment to remove and replace the broken pipe.Includes sawcut and removal of asphalt on the exterior to tie on to existing pipe. Days Requested: 0 Change Total: $5,692.63 Item Number Description lAmount 01 Cost to repaethe cracked sanita �iping_ — - - _ - -$4,738.50 _ P&O 03 Concrete to replace exterior paving that needs to be removed forplumbing.. $140.00 --- _.. 04 Concrete labor to replace pavng _— —- $512.00 05.------ ---. ---P&O_ .......- Approved By: By Signature (� Date BID RECAP SHEET 10/2112022 Company. Genesis Plumbing Enterprises LLC JpbName: G:Wy DrivelFastPIPEIFastESr-Mared.siteUobsICITYOF RIVERSIDE MO PS2.job Bid: Labor ICrew 3A Equipment Fixtures Materials Hours Rate Labor$ Total Piping Materials&Labor $1.569 16.6 $ 85.00 $1,410 $2,979 Pipe Equipment Total w/Summary $0 $0 Pipe Fixtures Total W/Summ $0 $0 Pipe Specialties Total w/Summary $0 $0 Pipe Other Total wlSsnmary SO $0 Equipment $0 0.0 $ 73.75 $0 $0 Fixtures $0 0.0 $ 73.75 $0 $0 TO ;lU Rental Equipment $0 0 Overtime Pay $20AO $0 $0 Double Time Pay $40.82 $0 $0 Supervision 0.0 $77.00 $0 Project Management 0-7 $60.00 $40 $40 Project Assistant 0.0 $30.D0 $0 $0 Warehouse Help 0.0 $40.00 $0 $0 Truck Driver ..0 $60,00 $0 s0 Sub Total $0 10 $1.569 $1,450 53,019 Sales Tax $6 $0 $0 $0 $0 Sub Total $0 $1,569 $1,450 1 $3,019 TOTAL FITTERIPLUMBER HOURS 16.6 TOTAL ADMINIiRUCK DRIVERWAREHOUSE HOURS 0.7 TOTAL OT HOURS 0.0 TOTAL DOUBLE 11ME HOURS OA Subcontracts including Sales Tax $1,350 Sub Total $4,359 Start-up Equipment Hours Warranty Material Escalation Freight Start-Up Travel Permits Cost Total $4,389 0.00% Contingency $0 Subtotal $4,369 10.0% Labor $141 10.0° ProjectMngmnt $4 20.0% Project Assist $0 20.0% Truck Driver/Warehouse $0 0.0° Materials $157 10.0% Rental $0 20.0°A Fixtures $D 20.0% Equipment $0 $67.50 5% 10.056 Warranty $0 10.0% Subcontracts 4135 Sub Total $4.N6 $4,738.50 Overall Mark-up% 10.0% TOTAL PROFIT $437 DOES NOT INCLUDE CONTINGENCY Sales Tax $0 -- Sub Total $4,808 $4,738.50 Bond $D QUOTED PRICEI $4,e08 $4,738.50 Price List Company: Genesis Plumbing Site: FastEST-Sharedsite Job: FastEST-Shared»CITY OF RIVERSIDE MO PS2(remodel) Qty Part Size Description Material Group List Date Mfgr Partd Source Modified Ust Factor Net 120 CF <None> cu It Excavated Dirt Backfill Excavation 9/1/2021 N/A <Catalog, 9/12021 SO-SO 1.000 50.50 40 SF <None> sq ft Sand Bedding 6 in Deep Excavation 9/1/2021 N/A <Catalog> 9/12021 SOAS 1.000 50.15 160 CF <None> a ft Excavation Excavation 9/12021 N/A <Catalog, 9/1/2021 SL50 1.000 $1.50 3 EA 6 PVC DWV Coupling PVC DWV Fittings 5/2/2022 Charlotte 100 <Catalog, 6/32022 8:40AM $27835 0.100 $27.84 20 LF 6 Sch 40 PVC DWV PE Pipe PVC DWV Pipe 1/12022 Charlotte 7600 <Catalog> 1/12022 $24.24 0.450 510.91 6EA 6 PVC Solvent Weld Joints Joints 8/17/2021 Varies <Catalog> 8/17/2021 $1.52 1.000 51.52 1 EA <None> CD core drill ands saw cut Job Items 10212022 935 AM <Jobltem> 10212022 935 AM S952.00 1.000 5952.00 FastPIPEa 10/312022 F ti • � t tµ � 1a • r � ♦ �. �;.�;�' � ." �. * •� .- .. �+.at .fir►