HomeMy WebLinkAboutR-2023-014 Approving Change Order 13 with Crossland Const.RESOLUTION NO. R-2023-014
A RESOLUTION APPROVING CHANGE ORDER 13 TO THE AGREEMENT WITH
CROSSLAND CONSTRUCTION COMPANY, INC. FOR ADDITIONS &
RENOVATIONS RIVERSIDE PUBLIC SAFETY RESULTING IN A REVISED
CONTRACT AMOUNT OF $4,904,582.71 FOR SUCH PURPOSES
WHEREAS, the City of Riverside ("City") issued an Invitation to Bid for the Additions
& Renovations Riverside Public Safety (Project No. 537-086) ("Project") which was awarded to
Crossland Construction Company, inc. ("Crossland") pursuant to Resolution R-2022-038; and
WHEREAS, the Board of Aldermen finds that it is in the best interest of the City to
approve Change Order 13 to the agreement with Crossland, resulting in a total revised contract
amount not to exceed $4,904,582.71.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF
THE CITY OF RIVERSIDE, MISSOURI, AS FOLLOWS:
THAT Change Order 13 to the Agreement between the City and Crossland, a copy of
which is attached hereto and incorporated herein, is approved and the Mayor is authorized to
execute the same on behalf of the City. The resulting revised total contract amount shall not
exceed $4,904,582.71.
FURTHER THAT the Mayor, City Administrator and all other required city officials
are authorized to take such other actions and/or execute and deliver for and on behalf of the City
all certificates, instruments, agreements and other documents as may be deemed necessary or
convenient to carry out and comply with the intent of this Resolution.
PASSED AND ADOPTED by the Board of Aldermen of the City of Riverside,
Missouri, the 7th day of February 2023.
/ I
Ka leen L. ' ose, Mayor
ATTEST:
Robin Kinca'd, City Clerk.
-- Document G701' 2017
Change Order
PROJECT: (Name and address)
Additions & Renovation
Riverside Public Safety
2990 NW Vivion Rd.
Riverside, MO 64150
OWNER: (Name and address)
City of Riverside
2950 NW Vivion Road
Riverside, MO 64150
CONTRACT INFORMATION:
Contract For: General Construction
Date: May 16, 2022
Notice to Proceed: July I I, 2022
ARCHITECT: (Name and address)
WSKF, Inc.
110 Armour Road
North Kansas City, MO 64116
CHANGE ORDER INFORMATION:
Change Order Number: 013
Date: January 30, 2023
CONTRACTOR: (Name and address)
Crossland Construction Company, Inc.
833 S. East Avenue
Columbus, KS 66725
THE CONTRACT IS CHANGED AS FOLLOWS:
(Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments
attributable to executed Construction Change Directives.)
I . Per PC00049 dated 1/25/2023, the cost to replace the broken 3" gate valve in the water room.
$835.45 - Increased Cost
2. Per PC00050 dated 1/25/2023, the cost to replace the existing 4X4's at the roof with new rubber roof blocks. Rooflink
provided direction to proceed with pricing as recommended change.
$697.22 - Increased Cost
3. Per PC00047 dated 1/30/23, the cost to install ACT ceiling grid and tile in the storage/ice room. Include dropping FS heads
and diffusers in grid and installing lights to the new ceiling.
$2,035.06 - Increased Cost
$3,567.73 - Total Increased Cost for Change Order No. Thirteen.
The original Contract Sum was
The net change by previously authorized Change Orders
The Contract Sum prior to this Change Order was
The Contract Sum will be increased by this Change Order in the amount of
The new Contract Sum including this Change Order will be
The Contract Time will be unchanged by Zero (0) days.
The new date of Substantial Completion will be March 8, 2023
$ 4,717,000.00
$ 184,014.98
f 4,901,014.98
$ 3,567.73
$ 4,904,582.71
NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract
Time, that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the
Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
WSKF, Inc.
ARCHITECT (Firm name)
Rick Kuhl, RA M'•"">a`::
SIGNATURE
Rick Kuhl, Principal
PRINTED NAME AND TITLE
01/31/2023
DATE
Crossland Construction Company, Inc. City of Riverside
CONTRACTOR (Firm name) 0 (Firm name)
4
ACO-Cle
Ryan Wacker --- a -
SIGNATURE
Ryan Wacker, Project Manager
PRINTED NAME AND TITLE
01/31/2023
DATE
NATURE
sZL/e e7'(. -
PRINTED NAME AND TITLE
,2.44.4 2-ei 7/ 0Q-3
DATE
AIA Document G701" — 2017. Copyright ® 1979, 1987, 2000 , 2001 and 2017 by The American Institute of Architects. All rights reserved. The "American
Institute of Architects," "AIA," the AIA Logo. and "AIA Contract Documents" are registered trademarks and may not be used without permission. This document
was produced by AIA software at 17:33:35 ET on 01/30/2023 under Order No.4104237064 which expires on 10/19/2023, is not for resale. is licensed for one-time
use only, and may only be used in accordance with the AIA Contract Documentsm Terms of Service. To report copyright violations, e-mail copyright@aia.org.
User Notes: (3B9ADA3C)
CROSSLAND
CONSTRUCTION COMPANY. INC.
Potential Change Order
i
Riverside Public Safety Additions and Renovation -
22MO17RWZD
2990 NW Marion Road
Riverside, MO 64150
22MO17RWZD
Date: 1/2512023
Subject: Replacing Broken Gate Valve in Water Room
Number: 0049
Source of Funding: Owner Contract Change Order
Description
1
Cost to replace the broken 3' gate valve in the water room.
Days Requested: 0
Change Total: S835.45
Item Number
01
Approved By:
Description
Cost to replace the broken gate valve.
Profit & Overhead
By
Signature
Date
Amount
$795.67
$39.78
Riverside Roof Blocks and 3" gate vale replacement
coDave Joe <djm@genesisplumbing.com>
To 0 Ryan Wacker
Cc Dave Joe; Shannon Welch
®DO0012523.pdf
104 KB
Reply (K) Reply All —� Forward le ••• I
Wed 1/25/2023 12:09 PM
EXTERNAL EMAIL: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.
Ryan,
ks as follows:
1- 3" gate valve with gaskets and bolts
4 hours labor @ $85 per hour
10% O&P
Total to replace 3" gate valve
$383.34
$340.00
$72.33
$795.67
10 existing roof blocks replaced with new, material per attached
4 hours labor @ 585 per hour
10% O& P
Total to replace roof blocks
Best regards,
David Madden
Genesis Plumbing Enterprises LLC
Cell: (816) 225 4576
Office: (816) 353 6724
Fax :(816)353 2579
Email : dim@genesisplumbing.com
263.66
$340.00
$60.36
$664.02
KC •
COMPANY
4400 E 12TH STREET
KANSAS CITY, MO 64127
PHONE (816) 842-9466
FAX (999) 999-9999
Phone (816) 353-6724
Fax (816) 353-2579
Riverside
le-.'qf::
0061577
ns;:yx.��e
1/25/23
I£��L tsn:�
1
Expiration Date
2/07/23
Revised Date
1/25/23
Bid Due Date _.
1/24/23
• Lt.2:7.,
i
-A ce:. — .r
AtIOMETO
Tony Schallenberg
tscha®kcwindustrial.com
(816) 842-9466
t, .1E
.
4:4;
" uars ".t`r': ro
- :.__i P CIA g.
�TY5'(j �-'x
;3.-
"
003927
1% 10TH
& 25TH NET 30
Tony Schallenberg
ANTHONY SCHALLENBERG
D
c'
nIlF.ir
o F�fr
"
sty
gi`i
�7 4r
6-t5-.it
-k. -,"t
�F'
t,.r
g
',j.
-
, t.+1 ::'' '�
i.-pr. °{r}
D »� ,r.R, t.-�:,,
l '
4,32. inidola•s
9•It-RAi
A.-4*t#YR1M•1]TdY".:,,-; ,..„ R4&::��:ts: P474ove1.' + - �'caK k .I., ,_e
f. iaF�' z'.i- ? .. Alo.t
c1:4*
!i aaly
1.0
1
6GA100B1LFA 3 NRS GATE VLV
354.0917
EA
354.09
F • ED V F6 9
•
. .
. . 1 .
1.
O.
ROOF BLOCK
3.0
2
B2011-1-1/4" PLTD P/PR CLAMP
1.6306
EA
3.26
PLATED UNISTRUT CLAMP
4.0
8
B2013-2" PLTD P/PR CLAMP
2.3813
EA
19.05
PLATED UNISTRUT CLAMP
5.0
20
B22SH GALV 20FT CHANNEL
3.5000
FT
70.00
1-5/8 SLOTTED STRUT%%%%%%%%%%%
6.0
20
B201 3/8" ZN SQUARE WASHER
.5885
EA
11.77
AS 619 EG
7.0
20
N228WO 3/8 STRUT NUT
.3994
EA
7.99
LESS SPRING (ASNS)
ZINC PLATED
9.0
2
3" NON-ASB FF FLG-PAK BOLT-PAK
14.6229
EA
29.25 -
Begin Components ******
I 5 0 C
4
5/8X3-1/4 Z-PLTD HEX CAP SCREW
EA
4
42443 5/8" PLTD HEX NUT
EA
****** End Components ******
Tax Area Id
Net Sales
647.81
Freight
.00
Tax
.00
Quotation Total
647.81
CROSSLAND
CONSTRUCTION COMPANY. INC.
Potential Change Order
i
Riverside Public Safety Additions and Renovation -
22MO17RWZD
2990 NW Vivion Road
Riverside. MO 64150
22M017RWZD
Date: 1/25/2023
Subject: New Roof Blocks at Existing Gas Lines
Number. 0050
Source of Funding: Owner Contract Change Order
Description
Cost to replace the existing 4x4's at the roof with new rubber roof blocks. Rooflink provided direction to proceed with pricing as a recommended change.
Days Requested: 0
Change Total: S697.22
Item Number
01
Approved By:
Description
Cost for new rubber roof blocks at the existinggas line.
Profit & Overhead
By
Signature
Date
Amount
$664.02
$33.20
Riverside Roof Blocks and 3" gate vale replacement
0 Dave Joe <djm@genesisplumbing.com>
To O Ryan Wacker
Cc Daveloe Shannon Welch
®D00012523.pdf
104 KB
<7 Reply <E) Reply All -3 Forward
Wed 1/25/2023 12:09 PM
EXTERNAL EMAIL: This email originated from outside of the organization. Do not dick links or open attachments unless you recognize the sender and know the content is safe.
Ryan,
Per the attached pricing, please find our price to replace the 3" gate valve and the roof blocks as follows:
1- 3" gate valve with gaskets and bolts
4 hours labor @ $85 per hour
10%O&P
$383.34
$340.00
$72.33
10 existing roof blocks replaced with new, material per attached
4 hours labor @ $85 per hour
10%O&P
Total to replace roof blocks
$263.66
$340.00
$60.36
$664.02
David Madden
Genesis Plumbing Enterprisesilk
Cell: (816) 225 4576
Office: (816) 353 6724
Fax : (816) 353 2579
Email : djm@genesisplumbing.com
4400 E 12TH STREET
KANSAS CITY, MO 64127
PHONE (816) 842-9466
FAX (999) 999-9999
Phone (816) 353-6724
Fax (816) 353-2579
.....ram
jiiktikb
't £•t'.rGa?^�_ Puy`""
Riverside
a.- ...•gym
°�.•E"�"'riTY s��t"l��:,X�r`'
ems- y_ -.:..� ,,
`n'{dic�+i,.l+��j�+���K��:':+_'.,;n��£Y4
ci
�`•tt
0061577 1/25/23
1
Expiration Date
2/07/23
Revised Date
1/25/23
Bid Due Date
1/24/23
y "b r%j.`1-fie, .{Fjc�w2 .1-� _��� c.t sa�.c->'tc-.ri'�•'i�F
:G[+4ar+..4.Y-•
.J
Tony Schallenberg
tschac&kcwindustrial.com
(816) 842-9466
CuStomer_
003927
Payment Terth,s Quoted:' To
1% 10TH & 25TH NET 30
Tony Schallenberg
- Salesperson
ANTHONY SCHALLENBERG
D
D e c r 1 A L 1 0 n
Unit
Price
Fxton 0.!
UO*4 Price
'1.0B LF
F D 61'
2.0 10 C10 MIFAB C-PORT
ROOF BLOCK
3.0 2 82011-1-1/4" PLTD P/PR CLAMP
PLATED UNISTRUT CLAMP
4.0 8 B20132" PLTD P/PR CLAMP
PLATED UNISTRUT CLAMP
5.0 20 B22SH GALV 2.0FT CHANNEL
1-5/8 SLOTTED STRUT%arois%% %%%
6.0 20 B201 3/8" ZN SQUARE WASHER
AS 619 EG
7.0 20'N228W0 3/8 STRUT NUT
LESS SPRING (ASNS)
8.0 20 3/8-16 HEAVY HEX NUT
Z C P 'T D
4
Begin Components ******
3 IFG5500 150# 1/16 FULL FACE
5/8X3-1/4 Z-PLTD HEX CAP SCREW
42443 5/8" PLTD HEX NUT
****** End Components ******
ax Area Id
354.
15.0000 EA
1.6306
2.3813
3.5000
.5885
.3994
.1200
150.00
3.26
19.05
70.00
11.77
7.99
2.40
Net Sales 647,81
Freight .00
Tax
Ouotation Total 647.81
CROSSLAND
CONSTRUCTION COMPANY. INC.
Potential Change Order
i
Riverside Public Safety Additions and Renovation -
22MO17RWZD
2990 NW Vivion Road
Riverside, MO 64150
22MO17RWZD
Date: 1/30/2023
Subject: PR034 - Storage/Ice Room Option A
Number: 0047
Source of Funding: Owner Contract Change Order
Description
Cost to install ACT ceiling grid and tile in the storage/ice room. Include dropping FS heads and diffusers in grid and installing lights to the new ceiling.
Days Requested: 0
Change Total: $2,035.06
Item Number
01
02
03
Approved By:
Description
Installing new ACT grid and tile
Installing lights to new grid.
Dropping FS heads in new ACT.
Profit & Overhead
By
Signature
Date
Amount
$732.00
$307.16
$899.00
$96.90
Riverside Public Safety PR 034
®Kevin Kimbrough <aaabuilders@gmail.com>
To Ryan Wacker
Start your reply all with:
Thank you!
Got it, thanks!
Received, thank you.
Q Feedback
(-) Reply «) Reply All -3 Forward •••
Fri 1/20/2023 12:18 PM
EXTERNAL EMAIL: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.
Ryan,
PR 034
ACT:
Material: $332.00
Labor: $400.00
Total: $732.00
rywall:
Material: $336.00
Labor: $500.00
Total: $836.00
Wachter
WACHTER, INC.
16001 W 99th St
Lenexa, Kansas 66219
Client Address:
Proposed Change Order
Contract Name: Riverside- Crossland Construction
Contract #: 1
Project Name: Riverside Public Safety
Project #: 47570
Client PCO #:
Work Description
PR# 034-Reinstall lights below drop ceiling in Room A137
Saturday. January 28. 2023 4 54 PM 1/3
Proposed Change Order
WACHTER, INC.
16001 W 99th St
Lenexa. Kansas 66219
Client Address:
Contract Name: Riverside- Crossland Construction
Contract #: 1
Project Name: 47570
Project #: Riverside Public Safety
Client PCO #:
Itemized Description
Description Qty Total Mat. $ Total Hours
4'Luminaire Linear Surface Mount w/ Lens - LED Integral Lamp 3.000 0.00 1.500
Luminaire T-Bar Support 6.000 15.06 0.600
Demolition - Luminaire Linear 4' Long 3.000
0.00 0.750
Totals 12.000 15.06 2.850
Saturday. January 28. 2023 4:54 PM 2/3
Proposed Change Order
WACHTER, INC.
16001 W 99th St
Lenexa. Kansas 66219
Client Address
Contract Name: Riverside- Crossland Construction
Contract #: 1
Project Name: 47570
Project #: Riverside Public Safety
Client PCO #:
Summary
Extension Materials
Database Material
Total Extension Material Cost
Material Markup
Total Extension Material
Labor Hours Rate Sub Total
Field Labor
Crew RATE ST
Total Field Labor
Total Labor Cost
Labor Markup
Total Labor
Sub Total 1
Sub Total 2
Total
2.850
92.69 264.17
OA
Total
15.06
15.06
10.00 1.51
Total
264.17
264.17
10.000 26.42
16.57
290.59
307.15
307.16
307.16
Contractor Certification
Name:
Date:
Signature:
I hereby certify that this quotation is complete and accurate based on the information provided
Client Acceptance
PCO #:
23
Final Amount: $ 307.16
Name:
Date:
Signature:
Change Order #:
I hereby accept this quotation and authorize the contractor to complete the above described work
Work Description
Saturday, January 28, 2023 4.54 PM
3/3
ADVANTAGE FIRE PROTECTION SYSTEMS, INC.
404B NW 11th St.
Blue Springs, MO 64015
Phone 816-224-3400 Fax 816-224-0401
Date: January 25. 2023
To: Crossland Construction
ATTN: Ryan
RE: Riverside PR 34
PLEASE SEE ADDITIONAL COST TO PROVIDE CHANGES PER PR 34, OPTION #1
LABOR 6 x $65.00 $390.00
MATERIALS $425.00
OH/MU $ 84.00
TOTAL $899.00
Option #2 No Cost
IF THERE ARE ANY QUESTIONS CONCERNING THE ABOVE PLEASE ADVISE, OTHERWISE, WE
AWAIT YOUR RESPONSE.
RESPECTFULLY SUBMITTED,
ROB KNOX
PRESIDENT
CITY OF
RIVESI�
MISSOURI
Upstream from ordinary.
2950 NW Vivion Road
Riverside, Missouri 64150
MEMO DATE:
AGENDA DATE:
TO:
FROM:
RE:
BACKGROUND:
BUDGETARY IMPACT:
January 31, 2023
February 7, 2023
Mayor and Board of Aldermen
Noel Bennion
Change Order 13: Crossland Construction Company, Inc.
Additions & Renovation Riverside Public Safety (537-086)
A broken gate valve was found in the water room and needed to be replaced.
The roof had wood blocks supporting RTU piping. These blocks will be replaced
with a material that won't degrade as easily and is better for the roof. The fire
storage/ice room was not designed with a ceiling. The ceiling is necessary to
deliver HVAC to this room.
An increase of $3,567.73.
Original Contract Amount
$4,717,000.00
Total of Previous Changes**
$ 184,014.98
Total this Change Order
$ 3,567.73
Current Contract Total
$4,904,582.7 I
RECOMMENDATION: Staff recommends approval of the resolution and acceptance of the change order
with Crossland Construction Company, Inc.
**LISTING OF PREVIOUS CHANGE ORDERS:
COI: Relocate conduit in walls
$ 33,413.48
CO2: Replace degraded sewer pipe
$ 9,671.55
CO3: Reuse existing VAV units
-$ 2,535.81
C04: Keep existing windows
-$ 3,520.91
C05: Lighting, vapor barrier, panels
$ 2,425.95
C06: Rated Ceilings, floor drains, roof coping, broken sanitary pipe
$ 62,533.52
C07: Vanity, interview & bunk lights, locker ventilation
$ 5,982.93
C08: Remove soap dispensers
$-1,751.19
C09: PRI3, Fire Kitchen Hood, Fire Conference Room, etc.
$ 29,269.94
CO 10: New flashing for existing condenser roof units
$ 6,899.55
CO I I: Parapet walls, window caulking, drain tile & RTU curb
$ 17,176.88
CO 12: Cat 6A, records wall, pinhole cameras, louver, RGBW,
countertops & fitness room ceiling tiles.
$ 24,449.09
Total
$184,014.98