HomeMy WebLinkAbout1923 Authorizing Amendment to Shaw Agreement Final RetainageBILL No. 2023-032 ORDINANCE NO. 1923
AN ORDINANCE AUTHORIZING AN AMENDMENT TQTHE AGREEMENT AUTHORIZED AND
APPROVED PURSUANT T0ORDINANCE NO. 1703 TO AMEND THE AGREEMENT FOR FINAL
PAYMENT OFRETAINAGE AND CLOSE OUT OF THE GEORGEJ.SHAW CONSTRUCTION CO.
CONTRACT
WHEREAS. the City of Riverside, Missouri ("City"), by and through the Board of Aldermen's
Passage and Approval, and the Mayor's Approval, of Ordinance 1703 on December 24, 2019, found
that it was in the best interest of the City to authorize and approve an Agreement by, between and
amongst the City, Riverside Horizons LLC. a Missouri limited liability company ("Riverside
Horizons'') and NorthPoint Development LLC. Missouri limited liability company (''NorthPoint
Development"), for final payment of retainage and close out of the George J. Shaw Construction Co.
("Shaw'') Contract (''Retainage Agreement") attached hereto as Exhibit A, and incorporated herein,
and that such approval fulfilled a public purpose, furthered the growth of the City, facilitated the
development of the entire Horizons site, improved the environment of the City, fostered increased
economic activity within the City, increased employment opportunities within the City, and otherwise
has been in the beat interests of the City, and has furthered the health, safety, and welfare of its
residents and taxpayers; and
WHEREAS, the City authorized the Mayor of the City to execute and deliver the Shaw
Agreemant, consistent with the terms of Ordinance 1703, Missouri law, and the terms of the Shaw
Agreement, and hereby authorizes the Mayor, the City Administrator, Special Counsel to the City and
other appropriate City officials to take any and all actions as may be deemed necessary or convenient
to carry out and comply with the intent of that Ordinance and to execute and deliver for and on behalf
of the City all certificates, instruments, agreements and other documenta, as may be necessary or
convenient to perform all matters herein authorized; and
WHEREAS. the City Staff, including the City Engineer and City Administrator, Riverside
Horizons and NorthPoint Development recommend an Amendment to the Retainage Agreement be
made in which the City'a n*bainage payment obligations pursuant tothe Retainage Agreement be
reduced by Five Thousand and 00/100 Dollars ($5,000.00), and Riverside Horizons' and NorthPoint
Development's retainage payment obligations pursuant tothe Ratainage Agreement be increased by
Five Thousand and 00/100 Dollars ($5,000.00) and that certain obligations of Shaw be waived as
described in the City Engineer's Shaw Punchlist Report ("Report"), attached hereto as Exhibit B,and
incorporated honein; and.
WHEREAS, the Board of Aldermen find it to be in the best interest of the City in order to further
the objectives of industrial and economic development of the City, and the terms and conditions of the
MDA, as well as in furtherance of the objective to protect the health, safety, and welfare of the
businesses and citizens of the City, to approve the recommended amendment to the Agreement
authorized and executed pursuant to Ordinance 1703 in order to reduce the City's retainage payment
by Five Thousand and 00/100 Dollars ($5,000.00) and to waive certain obligations of Shaw as
described in Exhibit B attached hereto and incorporated herein.
NOW, THEREFORE, BE[TORDAINED BYTHE BOARD OFALDERMEN OFTHE CITY OF
RIVERSIDE, MISSOURI\ AS FOLLOWS:
SECTION 1.BEST INTEREST CITY TO AUTHORIZE AND APPROVE. The Board
of Aldermen finds that it is in the best interest of the City to authorize and approve to amend the
Agreement authorized and approved pursuant to Ordinance 1703 to reduce the City's ratainage
payment by Five Thousand and 00/100 Dollars ($5,000.00) and to waive certain obligations of Shaw
as described in Exhibit B attached hereto and incorporated herein, and that such approval fulfills a
public purpose and will further the growth of the City, facilitate the development of the entire Horizons
site, improve the environment of the City, foster increased economic activity within the City, increase
employment opportunities within the City, and otherwise is in the best interests of the City, by
furthering the health, safety, and welfare of its residents and taxpayers, and the Board of Aldermen
does hereby approve the Shaw Agreement.
SECTION 2. AUTHORITY GRANTED. The City hereby authorizes the Mayor, the City
Administrator, Special Counsel to City and other appropriate City officials to take any and all
actions as may be deemed necessary orconvenient ho carry out and comply with the intent ofthis
Ordinance and to execute and deliver for and on behalf of the City all myrtifiooteo, inotrumanta,
agreements and other documents, as may be necessary or convenient to perform all matters herein
authorized.
SECTION 3. EFFECTIVE DATE. This Ordinance shall be in full force and effect from and after
its passage and approval.
BE|TREMEMBERED that the above was read two times byheading only, PASSED AND
APPROVED by a majority of the Board of Aldermen and APPROVED by the Mayor of the City of
Riverside, Missouri, this 6th day of June 2023.
Kathleen L. Rose, Mayor
ATTEST:
Robin Kincaid, City Clerk
Approved as to form
Spencer Fane LLP,
Special Counsel to the City
By Joe Bednar
JC 17518673.1
EXHIBIT A
ORDINANCE NO. 1703
JC 17518673.1
EXHIBIT B
AMENDMENT TO RETAINAGE AND CLOSE OUT AGREEMENT
JC I7518673,1
AMENDMENT TO THE RETAINAGE AND CLOSE OUT AGREEMENT
This Amended to the Agreement is entered into on the 6th day of June, 2023. by, between
and amongst the CITY OF RIVERSIDE, MISSOURI, a fourth-class city duly organized and existing
under the Constitution and laws of the State of Missouri (the "City"), RIVERSIDE HORIZONS, LLC,
a Missouri limited liability company ("Riverside Horizons") and NORTHPOINT DEVELOPMENT, LLC,
a Missouri limited liability company ("NorthPointDevelopment'). The City, Riverside Horizons, and
NorthPoint Development collectively are hereinafter referred to as the "Parties".
Whereas, In December, 2019. the Parties entered into an Amended and Restated Master
Development Agreement ("Amended & Restated MDA") that addressed and resolved certain issues
that had arisen involving the development and construction of the project commonly referred to as
Riverside Horizons (the "Project"); and
Whereas, the George J.Shaw Construction Co ("Shaw Construction") was retained as the
general contractor for the construction of the Project ("Shaw Construction Contract"); and
Whereas, the City currently holds the sum of $268,000.00 as and for "retainage" for the work
that remained to be completed byS haw Construction on the Project ("Shaw Construction Retainage");
and
Whereas, the Parties entered into an Agreement in regard to certain revisions to the scope
of the Shaw Construction Contract as approved by the City by and through the adoption of Ordinance
No. 1703 on December 24, 201 (the "Agreement");and
Whereas, certain further revisions to the Agreement's scope of work for the retainage
settlement documents for the Shaw Construction Contract are required; and
Whereas, to avoid any future misunderstandings or disagreements between the Parties as to
the changes to be made to the Shaw Construction Contract, and to ensure the Parties are aware of,
and agree to, these changes, the Parties hereby agree to the following as updates to amendment of
the previously approved scope of work:
1. The scope of work for the settlement of the final retainage payment for the Shaw
Construction Contract was originally agreed upon by, between and amongst the City. Riverside
Horizons, and NorthPoint Development in December 2019, and approved by the Board of Aldermen
and the Mayor of the City on December 24, 2019, pursuant to Ordinance No. 1703.
2. The Parties have agreed that said scope of work shall be revised and amended in
accordance with the terms and conditions set forth in that Ordinance No. 1703 and consistent with
the City Engineer's Shaw Punchlist Report ("Report"), attached hereto as Exhibit A.and incorporated
herein, which Report updates the status of work to be completed, memorializes the City Staff
recommended waiver of certain work requirements of Shaw, and which reduces the City's share of
the retainage payment by Five Thousand and 00/100 Dollars ($5,000.00) and increases Riverside
Horizon's and NorthPointDevelopment's retainage payment by Five Thousand and 00/100 Dollars
($5,00.00).
3. Upon approval of this Amended Agreement by the City by Ordinance and upon
execution by the Parties of this Amended Agreement, Riverside Horizons and NorthPnint
Development shall issue a Change Order incorporating scope of work changes contained within the
Report and closing out the Shaw Construction Contract ("Revised Shaw Construction Contract").
4. Within seven (7) calendar days of the City'a receipt of verification by Terracon
Consultants, Inc. ("Terracon") that the work required pursuant to the Revised Shaw Construction
JC 17518673.1
Contract has been completed ("Engineer's Certification"), the City shall release the total sum of
$99,000.00 from the Shaw Construction Rmtainagm. The City shall have no further or additional
obligation for the payment for Shaw Construction's work on the Project.
5. Also, within seven (7) calendar days of the receipt by Riverside Horizons and
NorthPont Development of the Engineer's Certification, Riverside Horizons and NorthPoint
Development will pay Shaw Construction the sum of $109,000.00, which when combined with the
City's release of the sum of $208,000.00 of the Shaw Construction Retainage, will constitute full and
final satisfaction of all sums due Shaw Construction under the terms of the Revised Shaw
Construction Contract.
6. By entering into this Amendment, the Parties acknowledge and agree that the terms
and conditions set forth in the Amended & Restated MDA remain in full force and affect and that said
terms are wholly unchanged by this Amended Agreement.
IN WITNESS WHEREOF the Parties have signed thimArnmmdnmemt to the Agreement msmfthe
date set forth above.
THE CITY OF RIVERSIDE, MISSOURI
Kathleen L. Rose, Mayor
RIVERSIDE HORIZONS, LLC,
a Missouri limited liability company
By: NorthPoint Holdings, LLC,a Missouri
limited liability company
Its: Manager
Nathaniel Hagedorn, Manager
NORTHPOINT DEVELOPMENT, LLC
a Missouri limited liability company
Nathaniel Hagedorn, Manager
JC 17518673.1
Contract has been completed ("Engineer's Certification"), the City shall release the total sum of
$99,000.00 from the Shaw Construction Rmtainagm. The City shall have no further or additional
obligation for the payment for Shaw Construction's work on the Project.
5. Also, within seven (7) calendar days of the receipt by Riverside Horizons and
NorthPont Development of the Engineer's Certification, Riverside Horizons and NorthPoint
Development will pay Shaw Construction the sum of $109,000.00, which when combined with the
City's release of the sum of $208,000.00 of the Shaw Construction Retainage, will constitute full and
final satisfaction of all sums due Shaw Construction under the terms of the Revised Shaw
Construction Contract.
6. By entering into this Amendment, the Parties acknowledge and agree that the terms
and conditions set forth in the Amended & Restated MDA remain in full force and affect and that said
terms are wholly unchanged by this Amended Agreement.
IN WITNESS WHEREOF the Parties have signed thimArnmmdnmemt to the Agreement msmfthe
date set forth above.
THE CITY OF RIVERSIDE, MISSOURI
Kathleen L. Rose, Mayor
RIVERSIDE HORIZONS, LLC,
a Missouri limited liability company
By: NorthPoint Holdings, LLC,a Missouri
limited liability company
Its: Manager
Nathaniel Hagedorn, Manager
NORTHPOINT DEVELOPMENT, LLC
a Missouri limited liability company
Nathaniel Hagedorn, Manager
JC 17518673.1
Shaw scope regarding final/agreed upon punchlist items
SHAW CONSTRUCTION CONTRACT CLOSEOUT AGREEMENT -
CORRECTIVE ACTIONS TRACKING CHART
PROJECT - - - - ISSUE
1. Spec Building #6-
1.(a) Cleanup
TASK
George J. Shaw Construction will clean up excess pipe and take
possession of the pipe to be utilized in the construction of the
crossing for the fire hydrant.
COMPLETED/WORK REMAINING?
completed
TASK
Northpoint Development will determine who owns any equipment,
trailers, misc. steel left on the site and George Shaw will move the
trailer to a designated parking spot within the limits of the Horizons
Industrial Park
COMPLETED/WORK REMAINING?
completed
TASK
Area will be rough graded and dressed up. If stabilization and/or
erosion control of this area is required, it will be performed by
others outside of George J. Shaw Construction (removed from GJS's
scope of work in CO #7.)
COMPLETED/WORK REMAINING?
completed
TASK
Upon completion of the area, Northpoint Development will meet,
with the city of Riverside, confirm the area is acceptable and will
remove "Spec Building #6 cleanup" from the list of remaining work.
All agreements will be provided by Northpoint Development and
issued to George J. Shaw Construction and signed off by the City of
Riverside. All documentation will be distributed via email.
COMPLETED/WORK REMAINING?
completed
TASK
Re-distribution of topsoil in this area is excluded as it was removed
from GJS's scope of work in CO #10.
n/a
Shaw scope regarding final/agreed upon punchlist items
PROJECT - - - - ISSUE
1.(b) Erosion
TASK
George J. Shaw Construction will add gabion rock to the washout
shown in the photo titled "to be completed prior to retainage
Over excavation of these areas or work within the ditch south of
spec building #6 is not included. These areas will have received
added stone to stabilize the area.
COMPLETED/WORK REMAINING?
completed
TASK
If stabilization and/or erosion control of this area is required, it will
be performed by others outside of George J. Show Construction
(removed from GJSs scope of work in CO #7).
COMPLETED/WORK REMAINING?
completed
TASK
Upon completion of the area NorthPoint Development will meet
with the city of Riverside, confirm the area is acceptable and will
remove "Spec Building #6 erosion" from the list of remaining work.
All agreements will be provided by Northpoint Development and
issued to George J. Shaw Construction and signed off by the City of
Riverside. All documentation will be distributed via email.
COMPLETED/WORK REMAINING?
completed
TASK
Re-distribution of topsoil in this area is excluded as it was removed
from GJSs scope of work in CO #10.
COMPLETED/WORK REMAINING?
n/a
Shaw scope regarding final/agreed upon punchlist items
PROJECT - - - - ISSUE
1.(c) Gate & Crossing for Fire
Hydrant
TASK
George J. Shaw Construction will utilize left over piping materials
from Spec Building #6 cleanup as culvert pipes to install the crossing
shown in the "to be completed prior to retainage release photo".
Crossing will be constructed with soil and silt spoils generated by
the regrading operation at 43rd street ditch regrading
COMPLETED/WORK REMAINING?
completed
TASK
Northpont Development to provide a detail of the dimensions of
the crossing required prior to construction beginning
COMPLETED/WORK REMAINING?
completed
TASK
Gate and fencing will be by others outside of George J. Shaw
Construction Co.
COMPLETED/WORK REMAINING?
completed
TASK
Area will be rough graded and dressed up. If stabilization ond/or
erosion control of this area is required, it will be performed by
others outside of George J. Shaw Construction (removed from GJS's
scope of work in CO #7.)
COMPLETED/WORK REMAINING?
completed
TASK
Upon completion of the area, NorthPoint Development will meet
with the city of Riverside, confirm the area is acceptable and will
remove "Gate & Crossing for Fire Hydrant" from the list of
remaining work. All agreements will be provided by Northpoint
Development and issued to George J. Shaw Construction and signed
off by the City of Riverside. All documentation will be distributed via
email
COMPLETED/WORK REMAINING?
completed
TASK
Re-distribution of topsoil in this area is excluded as it was removed
from GJSs scope of work in CO #10.
COMPLETED/WORK REMAINING?
n/a
Shaw scope regarding final/agreed upon punchlist items
PROJECT - - - - ISSUE
1.(d) 41st Street Ditch Grading
TASK
George J. Shaw will perform re -grading of the area once additional
information is provided by Northpoint Development of what is
required/what is wrong
COMPLETED/WORK REMAINING?
waived for jetting the pipe
(completed), removing eroded
material (completed), and $5000
credit to the City
TASK
George J. Shaw will not remove any plastic liner in order to
complete this work. If additional gabion stone is required to
complete this area it will be distributed on top of the existing stone
COMPLETED/WORK REMAINING?
n/a
TASK
Area will be rough graded and dressed up. If stabilization and/or
erosion control of this area is required, it will be performed by
others outside of George J. Shaw Construction (removed from GJS's
scope of work in CO #7.)
COMPLETED/WORK REMAINING?
waived for jetting the pipe
(completed), removing eroded
material (completed), and $5000
credit to the City
TASK
Upon completion of the area, Northpoint Development will meet
with the city of Riverside, confirm the area is acceptable and will
remove "41street ditch grading" from the list of remaining work.
All agreements will be provided by Northpoint Development and
issued to George J. Shaw Construction and signed off by the City of
Riverside. All documentation will be distributed via email
COMPLETED/WORK REMAINING?
waived for jetting the pipe
(completed), removing eroded
material (completed), and $5000
credit to the City
TASK
Re-distribution of topsoil in this area is excluded as it was removed
from GJS's scope of work in CO #10 .
n/a
Shaw scope regarding final/agreed upon punchlist items
PROJECT - - - - ISSUE
1.(e) 43rd Street Ditch Grading
TASK
Re-grading/maintenance grading of the north 43rd street ditch will be
completed per the elevations provided in the original Riverside
Horizons drawings. Grading will take place in and around the
culverts/crossing installed by others along with the new crossing
installed by GJS
COMPLETED/WORK REMAINING?
completed
TASK
Dewatering will dictate the scheduling of this work as it cannot be
done with the standing water in the ditch
COMPLETED/WORK REMAINING?
completed
TASK
All silt/spoils generated by this activity will be spread out on the
north side ofthe existing ditch. George J. Shaw Construction will not
be required to haul spoils off or to any designated locations onsite.
COMPLETED/WORK REMAINING?
completed
TASK
Area will be rough graded and dressed up. If stabilization and/or
erosion control of this area (or additional area where spoils are
spread) is required, it will be performed by others outside of George
J. Shaw Construction (removed from GJS's scope of work in CO #7.
COMPLETED/WORK REMAINING?
completed
TASK
Upon completion of the area, Northpoint Development will meet
with the city of Riverside, confirm the area is acceptable and will
remove "43d street ditch regrading" from the list of remaining
work. All agreements will be provided by Northpoint Development
and issued to George J. Shaw Construction and signed off by the City
of Riverside. All documentation will be distributed via email.
COMPLETED/WORK REMAINING?
completed
TASK
Re-distribution of topsoil in this area is excluded as it was removed
from GJS's scope of work in CO #10.
COMPLETED/WORK REMAINING?
n/a
Shaw scope regarding final/agreed upon punchlist items
PROJECT - - - - ISSUE
Stacked wall repair at failure
TASK
As previously discussed George J. Shaw Construction will not
complete the work associated with the stacked wall failure but will
provide a credit of $60,000 which is the estimate from the
Terracon Report. Please note the following:
COMPLETED/WORK REMAINING?
work was completed by others
TASK
The "failure" is not due to constructability as it has stood in place
along with numerous feet of other walls throughout the site for 5+
years and is outside the contractual warranty period.
COMPLETED/WORK REMAINING?
n/a
TASK
Following "a top five wettest year" in the history of Kansas City,
we feel the issue with the wall is an issue created by "an act of god"
and/or water table fluctuation
COMPLETED/WORK REMAINING?
n/a
TASK
Compromising the liner in this area will require mobilization of
the liner contractor for extremely minor work (compared to their
original scope).
COMPLETED/WORK REMAINING?
n/a
TASK
GJS believes it would be prudent to leave the wall area
untouched and monitor for any additional movement
n/a
Shaw scope regarding final/agreed upon punchlist items
Following Completion of the "5" items and scopes identified above and providing a wall credit of $60,000.00, GJS will receive the following
retainage value within 1 week of completion
Retainage Value Owed to George J. Shaw Construction from the original contract
ORIGINAL AGREEMENT
$268,000.00
AMENDMENT TO AGREEMENT
$268,000.00
Wall repair credit from Shaw
ORIGINAL AGREEMENT
($60,000.00)
AMENDMENT TO AGREEMENT
($60,000.00)
Wall repair credit from NorthPoint to City
ORIGINAL AGREEMENT
($5,000.00)
AMENDMENT TO AGREEMENT
($5,000.00)
Retainage Value to be issued by the City of Riverside (City 56%)
ORIGINAL AGREEMENT
$150,000.00 (56%)
AMENDMENT TO AGREEMENT
$11,480.00 (56% of $208k less $5k)
Retainage Value to be issued by Northpoint Development (NorthPoint 44%)
ORIGINAL AGREEMENT
$118,000.00 (44%)
AMENDMENT TO AGREEMENT
$96,520.00 (44% of 208k plus $5k)
Total Value of Retainage due to GJS within I week of the 5 items noted above
$208,000.00