HomeMy WebLinkAboutR-2023-152 Approving Task Order Number 1 w/VSM RESOLUTION NO. R-2023-152
A RESOLUTION APPROVING TASK ORDER NUMBER 1 WITH VSM
BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE CITY OF RIVERSIDE,
MISSOURI AS FOLLOWS:
THAT the Riverside Board of Aldermen hereby approves Task Order Number 1 by and
between the City of Riverside and VSM, in substantially the form attached hereto, and the
Mayor is authorized to execute the Task Order Number 1 on behalf of the City; and
FURTHER THAT the Mayor, the City Administrator and other appropriate City officials
are hereby authorized to take any and all actions as may be deemed necessary or convenient
to carry out and comply with the intent of this Resolution and to execute and deliver for and on
behalf of the City all certificates, instruments, agreements and other documents, as may be
necessary or convenient to perform all matters herein authorized; and
FURTHER THAT this Resolution shall be in full force and effect from and after its
passage and approval.
ADOPTED AND PASSED this 17'h day of October 2023.
•
�! r •3 ¢ /
•
Mayor Kathleen eat/din/4:
•
Robin incaid, ity Clerk
1
Task Order Number 1
For Engineering Services
This Task Order is entered into as of the 17th Day of October 2023 (the"Effective Date"),
by and between VSM Engineering, LLC, a Missouri corporation having an office at 8008 N
Chatham Ave, Kansas City, Missouri 64151 ("VSM") and the City of Riverside, Missouri, a
Missouri municipal corporation (the"City").
WHEREAS, the City has engaged VSM to provide engineering services pursuant to the
Agreement for Engineering Services dated October 20,2020 pursuant to which the City may task
VSM to provide additional professional engineering services on a project-specific basis by
acknowledging a separate Task Order.
NOW, THEREFORE, in consideration of the promises and mutual covenants between the
parties and for other good and valuable consideration the receipt of which is acknowledged by
the parties,they agree as follows:
1. Incorporation of Base Agreement. This Task Order is subject to all terms and conditions
contained in the Agreement for Engineering Services dated October 20, 2020, that are not
inconsistent with the specific terms contained herein, and the Agreement for Engineering
Services dated October 20, 2020, between the parties is incorporated herein as if set forth in
full by this reference.
2. Scope of Services. The Scope of Services pursuant to this Task Order are as contained in
Exhibit A.
3. Term. VSM shall begin work pursuant to this Task Order No. 1 upon its Effective Date
and shall continue until the 9 Hwy Connector 225-029 ("Project") is completed as evidenced by
final acceptance of the Project by the City.
4. Compensation. Unless compensation is set forth in this Task Order, compensation shall
be as provided in the Agreement for Engineering Services dated October 20, 2020, between the
parties.
5. Project Schedule. See project schedule in Exhibit A.
1
IN WITNESS WHEREOF, the VSM and the City have executed this Agreement as of the
Effective Date.
VSM ENGINEERING,LLC: CITY OF RIVERSIDE,MISSOURI:
11 ..
By: ) By: '
Name: VA\,"Q5- e_. J- jkCCQkkdo Name: Kathleen L. Rose
Title: Ce ok.Q. f\±, Title: Mayor
Dated: t bl 5Ic 3 Dated: betA_,A., I •] L0 l3
I
. .
. .
�. . ATTESt.
�. • ,k 7 •
Robin Kincaid,City Clerk
' •••
SSC
By: Ipr- ..._ 11
Na -: Brian oral 111
Title: ' • dministrator
Dated: (QC)O i 7, �D
2
Exhibit A to Task Order 1
Scope of Services for
Highway 9 Trail Connector(225-029)
PROJECT DESCRIPTION
The City of Riverside desires to connect the Hwy 9 Trail from Horizons Parkway to NW Platte
Valley Dr. This project will consist of creating "shovel-ready" construction documents for the
City to utilize for bidding and construction.The concrete trail will be 10 feet wide and
approximately 2370 LF long.
SCOPE OF SERVICES
1. Task 100- Project Management-VSM will manage the project, prepare monthly
progress reports, invoicing and contact and insurance.
Meetings/Conference Calls-VSM will participate in in-person meeting with City of
Riverside staff during development of Final Plans and Specifications at an estimated
completion 30% (Alignment and Grade), 60% (Cross Sections confirmation of
construction limits), 95% Plans, Specifications and Estimate. The purpose of this meeting
will be to review project details and plan development. In addition, up to two
conference calls with screen share to discuss the project and plan development will be
scheduled around (before or after)the in-person progress meeting.
2. Task 200-Site Survey-The Site survey will be performed by a sub-consultant to VSM.
This includes a topographic survey of property lines, elevations, utilities, sidewalks,
curbs and other existing features. Tract Map and Legal Descriptions for selected tracts;
estimated 5 tracts.
3. Task 300—Site Drainage -design of cross culverts and large ditch crossing, design of
side ditches and addressing off-site drainage.
4. Permitting- MoDOT permit for work on MoDOT Right-of-Way. —VSM will prepare
documents for MoDOT permit on the MoDOT Right-of-way. Responses for one review
each by the City and MoDOT are included.
5. Plans, Specification and Estimate
• VSM will provide 11x17 construction drawings showing trail alignment, trail profile,
trail details, trail typical sections and cross-sections for the section of the trail from
the connection. The trail alignment and profile will meet design criteria, ADA and
permit requirements.
• VSM will prepare Technical Specifications, as requested, for trail construction. All
front- end specifications and bidding documents will be prepared by the City.
• VSM will prepare a cost estimate for the trail.
• Drawings will be prepared in an AutoCad format and provided to the City.
• All final plan sheets and specifications will be prepared using the U.S. Customary
system of units.
• Prepare final engineers estimate of probable construction costs based upon final
quantities and estimated unit costs.
• Final plans and specifications will be sealed and signed by a Missouri Professional
Engineer.
• The final plan package for the trail shall consist of the following list of plan sheets:
Title Sheet 1
General Notes and Survey Data 1
Survey Data Sheet with BM and CP's (VSM to provide Title Block) 2
Plan and Layout View- 1"=20'for 2300 LF 8
Cross sections-46 sections 10/per sheet 5
Watershed Map and Stormwater Design Data for Trail 1
Sediment and Erosion Control Plan (do by note only for Shop drawing) 0
Construction Traffic Control Plan (needed for MoDOT permit) 2
Details-Typical Trail Section, Handicap ramp detail, Rail for trail, stormwater
details, trench detail for pipe crossings, ditch detail 2
TOTAL SHEETS 22
6. Project Schedule
• Receive Site Survey from sub-consultant on or before November 30, 2023.
• 95% Plans to the City to review on February 15, 2024.
• Signed and Sealed Final Plans and Specification -submit to City on March 15, 2024
for project bid prep by the City.
7. Task 600-Construction Administration and Construction Services-All bidding services
and construction administration will be provided by the City. VSM may be asked to
review shop drawings and answer construction request for information questions using
a separate task order once the project is bid.
8. Exclusions
• The City will prepare and e-file the NPDES storm-water construction Notice of Intent
with Missouri Department of Natural Resources.
• The City will prepare and submit the Land Disturbance Permit with VSM providing
trail layout to the City.
• No Public outreach or public presentation work included.
• No Geotechnical work is included.
• No bridge design is included.
Exhibit B for Task Order Number 1
FEE -See attached spreadsheet.
The scope of services shall be completed under this authorization for an hourly-not-to-exceed
fee of$105,230.The City shall compensate VSM for these services, based upon hourly rates.
VSM Engineering,LLC 10/4/2023
City of Riverside Missouri
Hwy 9 Connector Task 220-02
VSM Project No.20-12
Last Updated 10-03-23 V V S A A/W/M N
c ask Principal Sr.Civil Senior Civil - Civil — Incidental Comments/t.lariticatlons
/Project Engineer Civil Engineer Tech/Drafting Admin
Manager Engineer El Expenses
L.S.$ Description
Meetings/conference calls during project.
Consultant will prepare minutes for
100 Project Management 40 0 0 0 0 8 $0 documentation.QC Review.
Site Survey and base file by subcontractor. Legal
Descriptions 8,Tract Maps-5 Tracts t$700
200 Site Survey 0 4 0 0 0 0 $13,000 each
300 Site Drainage-for 2300 LF of trail 0 12 90 0 0 0 $0
400 Permitting(MoDOT) 0 0 40 0 0 0 $0
500 Trail Plan Development(see attached list)+Cost Estimate 0 16 100 350 100 0 $0 22 sheets
Will Be provided by City of Riverside staff unless
600 Construction Administration/Construction Services 0 0 0 0 0 0 $0 special request to VSM Engr
0 _ 0 0 0 0 0 $0
1000 Expenses-only will be charged actual expenses $400 Estimate-actual will be billed(see list below)
40 32 230 350 50 8 710
Rates $200 $175 $150 $110 $95 $60
Total Costs $8,000 I $5,600 I $34,500 $38,500 I $4,750 I $480 I $13,400 $105,230
Typical Expenses
Mileage-miles at 0.655 cents per mile- $200
Reproduction: Printing,Scanning,courier $200
F Capitol Improvement ProlecSa H Connector225-07Pv5-ConlnchWLOMnctComplenceDoceW5MWSM live,P Connector Fee v.oMehee1100323 v2.x9v 1 of 1