HomeMy WebLinkAboutR-2023-161 Approving Task Order #1 with SFS RESOLUTION NO. R-2023-161
A RESOLUTION APPROVING TASK ORDER NUMBER 1 WITH SFS
BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE CITY OF RIVERSIDE,
MISSOURI AS FOLLOWS:
THAT the Riverside Board of Aldermen hereby approves Task Order Number 1 by and
between the City of Riverside and SFS, in substantially the form attached hereto, and the Mayor
is authorized to execute the Task Order Number 1 on behalf of the City; and
FURTHER THAT the Mayor, the City Administrator and other appropriate City officials
are hereby authorized to take any and all actions as may be deemed necessary or convenient
to carry out and comply with the intent of this Resolution and to execute and deliver for and on
behalf of the City all certificates, instruments, agreements and other documents, as may be
necessary or convenient to perform all matters herein authorized; and
FURTHER THAT this Resolution shall be in full force and effect from and after its
passage and approval.
ADOPTED AND PASSED this 7th day of November 2023.
•
Mayor Kathleen L. ose
ATTEST:"- -.
•
Robin Kincaid, City Clerk
1
Task Order Number 1
For Architectural/Engineering Services
This Task Order is entered into as of the 7th day of November, 2023 (the "Effective
Date"), by and between SFS Architecture Inc, a Missouri corporation having an office at 2100
Central St, Suite 31, Kansas City, MO 64108 (the "Consultant") and the City of Riverside,
Missouri, a Missouri municipal corporation(the"City").
WHEREAS, the City has engaged Consultant to provide architectural / engineering
services pursuant to the Agreement for Architectural / Engineering Services dated October 3,
2023 pursuant to which the City may task the Consultant to provide additional professional
architectural /engineering services on a project-specific basis by acknowledging a separate Task
Order.
NOW, THEREFORE, in consideration of the promises and mutual covenants between the
parties and for other good and valuable consideration the receipt of which is acknowledged by
the parties,they agree as follows:
1. Incorporation of Base Agreement. This Task Order is subject to all terms and conditions
contained in the Agreement for Architectural / Engineering Services dated October 3, 2023,
that are not inconsistent with the specific terms contained herein, and the Agreement for
Architectural / Engineering Services dated October 3, 2023, between the parties is
incorporated herein as if set forth in full by this reference.
2. Scope of Services. The Scope of Services pursuant to this Task Order are as contained in
Exhibit A.
3. Term. Consultant shall begin work pursuant to this Task Order No. 1 upon its Effective
Date and shall continue until the City Hall Renovation 540-023 ("Project") Task Order 1 is
completed.
4. Compensation. Unless compensation is set forth in this Task Order, compensation shall
be as provided in the Agreement for Architectural /Engineering Services dated October 3, 2023,
between the parties.
5. Project Schedule. See Exhibit A.
1
IN WITNESS WHEREOF, the Consultant and the City have executed this Agreement as of the
Effective Date.
SFS ARCHITECTURE,INC.: CITY OF RIVERSIDE,MISSOURI:
1V/1(71114m,
By: By:
Name: Kerry Newman, AIA Name: Kathleen L. Rose
Title: Principal Title: Mayor
Dated: November 3, 2023 Dateda B'tr`' .20L 3
.
bATTES
Robin Kincai ,City Clerk
BY: Ir.., i��.,
Name: :rian Kora•
Title: CI • dministrator
Dated: 40 terx. 5? 2LQ
2
Exhibit A to Task Order 1
sfsarchitecture
drivenbyconnections
PROJECT TEAM
SFS Architecture Prime Consultant / Architect
Smith & Boucher Mechanical, Electrical, Plumbing Engineering
Strategic Value Solutions Cost Estimator
PROJECT UNDERSTANDING
The current City Hall building was completed in 2001.Since that time department sizes,responsibilities and
visitor interface needs have evolved. The city desires a comprehensive analysis of current and future
needs to address current deficiencies and inefficiencies.
The scope of this Task Order 1 includes condition assessment, programming, concept planning and cost
estimating for departments within the current City Hall. Departments include Administration, City Clerk,
Community Development, Engineering, Finance/IT and Human Resources. In addition, Public Works,
Police and Municipal Court will be interviewed for potential needs in City Hall. Along with the
programming and concept planning, an exterior envelope condition assessment and MEP analysis will
be performed to provide recommendations for improvements. It is anticipated that once a direction has
been established and approved by the City, Task Order 2 will be issued for complete design and
construction administration services.
Budget
We understand a preliminary budget of $1.5 million was anticipated for construction of the desired
improvements. However, the city desires a total project budget to be determined based on the desired
concept direction.
Schedule
The City anticipates notice to proceed following City Council approval. SFS anticipates completion of
Task Order 1 programming and concept planning and exterior envelope/MEP assessment in
approximately 3 months following the Kickoff Meeting. A complete design schedule will be prepared for
Task Order 2 upon request by the City.
SCOPE OF WORK
Professional Services will include the disciplines of Architecture and Mechanical/Electrical/Plumbing
Engineering.
Task Order 1
Programming and Concept Planning:
• Refer to the attached Phase 1 Workplan
• Presentation to City Council as desired.
• Preparation of the total project budget for Owner confirmation and approval.
• Compilation of space needs program, concept design drawings and cost opinions for Owner
confirmation and direction.
MEP Assessment:
• Review existing systems to determine age, condition, suitability for current installation. Systems
include HVAC, plumbing, lighting/controls, power systems, fire sprinkler and fire alarm.
• Develop summary of existing equipment, existing HVAC zoning diagram and code change
impacts.
• Review of overall available power watts/sf.
• Review generator capacity and connected systems.
• Provide recommendations for replacement and upgrades for all systems.
2100 CENTRAL STREET I SUITE 31 KANSAS CITY j MISSOURI 64108 T 816.474.1397 F 816.421.8024 W SFSARCH.COM
sfsarchitecture
drivenbyconnections
Exterior Building Envelope Assessment:
• Visual condition assessment of exterior envelope conditions including masonry walls,exterior doors,
windows and roofing.
• Provide recommendations for repair and or upgrades to exterior envelope systems and materials.
Basic Services Exclusions
The following items are excluded from our Professional Services Fee noted above. These may be added
on an as needed basis as additional services:
• 3-Dimensional renderings of potential improvements.
• Site design or engineering services.
• Hazardous materials assessment or abatement design.
• Furniture, fixtures, and equipment (FFE) design services.
• Detailed design or engineering services.
• Community engagement services.
• Interior architectural condition assessment.
• Removal of existing building materials or destructive testing.
BASIC SERVICES COMPENSATION
SFS Architecture proposes basic professional services fees at the following lump sum amounts:
Task Order 1:
Programming, MEP Assessment and Concept Design: $ 54,710.00
Exterior Envelope Assessment: $ 8,450.00
Additional Services
During the project additional services may be requested. Fees for additional services outside of the
scope outlined in this proposal will be discussed and mutually agreed upon prior to SFS Architecture and
the consultants proceeding with those services.
REIMBURSABLE PROJECT FEES AND EXPENSES
Reimbursable expenses are not included in the above basic services compensation. Items such as
printing, reproductions, mileage, and postage, are considered reimbursable project expenses incurred
by SFS and its consultants shall be billed and itemized by each cost incurred. We estimate reimbursable
project related supplemental fees and expenses to be less than $500.00 and will invoice the City for
expenses monthly at a rate of 1.0 times the actual cost to the Architect.
Invoicing
Invoicing will occur monthly for services rendered and are due upon receipt.
This task order is pursuant to the terms outlined in the Agreement for Architectural / Engineering Services
between the City of Riverside, Missouri and SFS Architecture dated October 3, 2023.
2100 CENTRAL STREET SUITE 31 KANSAS CITY ! MISSOURI 64108 ; T 816.474.1397 F 816.421.8024 W SFSARCH.COM
sfsarchitecture 101
Riverside, Missouri November 2, 2023
City Hall Renovation
Draft Workplan
Task Order 1
Kick Off Meeting 1 week
Discuss project goals and objectives
Review project workplan,schedule,deliverables and construction delivery methods
Review program questionnaire and space programming process
Condition Assessment and Space Needs Programming 4 weeks
Distribute space needs programming questionnaire
Perform existing MEP building assessment
Perform existing exterior building envelope assessment
Collect progam questionnaire information
On site program interview
Prepare space needs program draft
Team Review Meeting 1 1 week
Review space needs program
Review outline of MEP existing conditions
Review outline of exterior building envelope conditions
Solicit feedback from key staff members
Work Period: Concept Design 2 weeks
Prepare concept plan options
Prepare rough order of magnitude pricing
Concept Design Workshop 1 week
Mechanical systems recommendations
Present concept plan options
Solicit feedback from key staff members
Confirm preferred direction
Discuss priorities and potential phasing
Concept Refinement and Cost 2 weeks
Refine preferred concept plan
Project and construction cost opinion
Prepare phasing plan
Team Review Meeting 2 1 week
Review refined concept plan
Confirm mep approach
Review cost information
Discuss phasing options and timelines
City Council Presentation