HomeMy WebLinkAboutR-2024-105 Approving CO3 to the Agreement w/Royal Construction Services, LLC for Riverside Pool and Restroom Improvements ($3,357,507.92) RESOLUTION NO. R-2024-105
A RESOLUTION APPROVING CHANGE ORDER 3 TO THE AGREEMENT WITH
ROYAL CONSTRUCTION SERVICES, LLC FOR RIVERSIDE POOL AND
RESTROOM IMPROVEMENTS RESULTING IN A REVISED CONTRACT AMOUNT
OF $3,357,507.92 FOR SUCH PURPOSES
WHEREAS, the City of Riverside ("City") issued an Invitation to Bid for the Riverside
Pool and Restroom Improvements (Project No.222-087, LWCF 29-01759) ("Project")which was
awarded to Royal Construction Services, LLC ("Royal") pursuant to Resolution R-2024-038;
and
WHEREAS, the Board of Aldermen finds that it is in the best interest of the City to
approve Change Order 3 to the agreement with Royal, resulting in a total revised contract
amount not to exceed $3,357,507.92.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF
THE CITY OF RIVERSIDE,MISSOURI, AS FOLLOWS:
THAT Change Order 3 to the Agreement between the City and Royal, a copy of which is
attached hereto and incorporated herein, is approved and the Mayor is authorized to execute the
same on behalf of the City. The resulting revised total contract amount shall not exceed
$3,357,507.92.
FURTHER THAT the Mayor, City Administrator and all other required city officials
are authorized to take such other actions and/or execute and deliver for and on behalf of the City
all certificates, instruments, agreements and other documents as may be deemed necessary or
convenient to carry out and comply with the intent of this Resolution.
PASSED AND ADOPTED by the Board of Aldermen of the City of Riverside,
Missouri, the 20th day of August 2024.
.•
.: Kath een L. Rose, Mayor
A.T TiST: 4: •
q • a
Roliiri.Kinca , City Clerk
CITY OF CHANGE ORDER NO. 3 Date Prepared. 8/15/2024
RIVERS
Contractor Name: Royal Construction Services
Project Name: Riverside Pool&Restroom Improvements Page Number: 1 of 4
Project Number: 222-087,LWCF 29-01759 #of Pgs Attached 3
Contract Date: 4/1/2024 The following changes to the original contract amount were required to cover cost incurred by the
Project Location: Riverside,Missouri Contractor or to reflect savings realized by the Contractor as a result of a change in the actual
constructed quantities from the estimated quantities shown on the Bid Proposal.
REQUIRED CHANGES IN PRESENT CONTRACT
Contract or Contract or Contract or New or New or New or
Line Item No. Previous Previous Previous Unit Item Description &Reason for Change Order Adjusted Adjusted Adjusted
Quantity Unit Price Amount Quantity _ Unit Price Amount
Alternate 5 0.0 $0.00 $0.00 1 Upgrade fire alarm system throughout the Community Center 1.00 _ $17,062.00 $17,062.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
Previous Total $0.00 Adjusted Total $17,062.00
Net Change $17,062.00
Statement of Contract
Original Contract Amount $3,305,000.00
Net Amount of Previous Additions and Deductions $35,445.92
Net Contract Amount Prior to This Request $3,340,445.92
Amount of This Request $17,062.00
New Contract Amount $3,357,507.92
Percent Change in Contract Amount 0.51%
DESIGN ENGINEER: CITY OF RIVERSIDE,MISSOURI: AJ
Company Waters Edge Aquatic Design Capital Projects: /t &J,e5Q4LI..eeg, 08/16/24
Name Primed• Jell Rartley Noel Bennio igned Da e
Signed , Cit Administrator: \
Date. 08f I(r"_d y Brian Korai Dm
CONTRACTOR: ON-SITE PROJECT MANAGER:
CONTRACTOR'S Certification for Chanae Order: ON-SITE PROJECT MANAGER Certification for anae Order:
The undersigned CONTRACTOR certifies that all changes In accordance with the Contract Documents,the on-site observab ,
described above are necessary in order for the CONTRACTOR to the data comprising this change order,the on-site project manager certifies
proceed with execution of the contract documents,and that the to the Owner that to the best of the on-site project manager's knowledge,
values stated above are correct with respect to the work information and belief the above referenced changes are necessary in order to
anticipated under this change order. proceed with the execution of the contract documents,and that the values
��1 A 1/� R7/1 (��� ( stated above are correct with respect to the work anticiippaatedd under this changeg1 order.rdl .�f try) (� `1
Company:Imo`" ki 0'`a l01v t li�Y µJ Company: 2. l4I C% S 1 evi 1t e) S V 1 VLS
Name Printed- 3 0 M� yyyY� � I prCsv A Name Printed VI I tr�l�,('
SignedMID, / Signed.Date: Date t 611.02A+
ROYAL COR-004
CONSTRUCTION SERVICES
2017 W. 104th Street, Leawood, KS 66206
August 15,2024 Project: Riverside Pool& Restroom Improvements
Attn: Jeff Bartley
Water's Edge Aquatic Design
1153 Southwest Blvd.,Suite 202
Kansas City, KS 66103
RE: Fire Alarm Upgrade—Rev.#1
Dear Jeff,
We are pleased to provide you with the price for the upgraded fire alarm system.
For the sum of: $17,062.00
Please contact me at your earliest convenience if you have any questions.
Respectfully,
Royal Construction Services LLC
Steve VanSickle
Project Manager
enclosures
cc: File:Proposal breakdown
ARCHITECT: OWNER:
by: by:
date: date:
Fire Alarm Upgrade -
Description: Total Hours Labor Materials Supplies Equipment Subcontractor
Project Management 1.00 $ 100.00
Superintendent Labor Hours 1.00 $ 84.00 --
Superintendent Labor Overtime Hours $
Superintendent Labor Premium ONLY Hours $ -
Carpenter Labor Hours $ -
Carpenter Labor Overtime Hours $ -
Carpenter Labor Premium ONLY Hours $ -
Laborer Hours $ _
Laborer Overtime Hours $
Laborer Premium ONLY Hours $
Purchased Materials:
J.Webb $ 15,410.00
Subtotals 2.00 $ 184.00 $ - $ - $ - $ 15,410 00
SUBTOTAL: $ 15,594.00
Small Tools $ 4.60
Bond $ 465.06
General Liability $ 188.02
Sales Tax $ -
SUBTOTAL: $ 16,249.68
Overhead and Profit ea 5% $ 812.48
Total Proposal: $ 17,062.17
J Webb Inc
P 0 Box 952
Lawrence,KS 66044 US
planroom@jwebb-kc.com
Estimate
ADDRESS 5049
Riverside Community Center 08/15/2024
DATE ACTIVITY DESCRIPTION OTY
Alternate Pricing Fire Alarm-Riverside Community Center
non-voice evacuation
FACP Fire Alarm Control Panel 1
battery 12v19 12volt 19amphr 2
smoke detector smoke detector 2
pull station pull station 2
monitor module x1 monitor module-single input 7
sprinkler alarm
kitchen hood
duct detector duct detector 2
relay module relay module(HVAC Shutdown) 2
horn/strobe(outdoor) horn/strobe(weatherproof) 1
horn/strobe horn/strobe 12
design design,cad work,submittals 1
labor 1 labor 40
labor 2 labor 10
$15,410.00
Base Bid Price-labor included
horn/strobe horn/strobe 3
strobe strobe 10
$1,300.00
$16,710.00
CITY OF
- RIVERS!
MISSOURI
Upstream from ordinary.
2950 NW Vivion Road
Riverside, Missouri 64150
MEMO DATE: August 15, 2024
AGENDA DATE: August 20, 2024
TO: Mayor and Board of Aldermen
FROM: Noel Bennion
RE: Change Order 3: Royal Construction Services, LLC
Riverside Pool and Restroom Improvements (222-087, LWCF 29-01759)
BACKGROUND: The bid request for the project included an alternate to upgrade the fire alarm
system in the Community Center per the request of the Riverside Fire Marshal.
Bids received varied significantly in cost. Staff determined it was best to take
more time to evaluate this alternate instead of including it in original bid award.
This additional evaluation allowed us to prepare the exact scope of needs and
obtain a lower cost than the original bid alternate. This change is within the
project budget.
BUDGETARY IMPACT: An additional $17,062.00 is requested.
Original Contract Amount $3,305,000.00
Total of Previous Changes $35,445.92
Total this Change Order $17,062.00
Current Contract Total $3,357,507.92
RECOMMENDATION: Staff recommends approval of the resolution and acceptance of the change order
with Royal Construction Services, LLC.